Home / Browse projects / Thane, Maharashtra / ARYAN ONE WING G AND H

Completed No litigation declared Residential / Group Housing project

ARYAN ONE WING G AND H

By Konark Lifespaces

RG-MH-24707 · RERA P51700002130 · Last updated on MahaRERA portal: 30 Sep 2019

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2019Possession promisedregistration recorded completed
13 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 97%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

ARYAN ONE WING G AND H is a Residential / Group Housing project by Konark Lifespaces in Thane, Maharashtra, registered with MahaRERA as P51700002130 on 31 Jul 2017. The registration is recorded completed; possession was promised by 31 Jul 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameARYAN ONE WING G AND H
  • TypeResidential / Group Housing
  • Location
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700002130
  • ReraGenie IDRG-MH-24707

Builder

  • NameKonark Lifespaces
  • Entity typePartnership
  • PartnersRITESH MUKESH KIMTANI, MUKESH GOBINDRAM KIMTANI, KONARK INFRASTRUTURE LIMITED, NANDLAL GOBINDRAM KIMTANI, NANDLAL RAMCHAND JETHANI
  • Other registrations2 more →
  • Completed3 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017First promiseJul 2018Revised toJul 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Jul 2017
  • Promised completion31 Jul 2019
  • Revised completionRevised to 31 Jul 2019 (originally 31 Jul 2018)
  • Buildings2 building records
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARYAN ONE WING GNA140000
ARYAN ONE WING HNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Sep 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

ARYAN ONE WING G90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises93%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
ARYAN ONE WING H89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises93%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%

Progress on shared amenities15

As on 30 Sep 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes98%
Landscaping & Tree PlantingYes100%
Street LightingYes95%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes20%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes75%
Open ParkingYes100%

Parking filed215

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots215
Closed/Covered49
Open Space166
BuildingClosed/CoveredOpen SpaceTotal
ARYAN ONE WING G2695121
ARYAN ONE WING H237194

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,119 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6829.39
Proposed, not sanctioned6,829 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLBS MARG, VIKHROLI WEST MUMBAI

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECT INCORPORATE
PartnerRole in project
Konark Lifespaces-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700000483Jul 2018 → Jul 2019

Reason as filed by the promoterPROJECT IS COMPLETED IN ALL CIVIL ASPECTS, WE ARE WAITING FOR ONLY FIRE NOC FROM FIRE DEPARTMENT WHICH WE HAVE ALREADY APPLIED PLEASE FIND ATTACHED APPLICATION TO FIRE DEPARTMENT AND LETTER FROM ARCHITECT ABOUT WORK COMPLETION.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: WING G,H.pdf30 Sep 2019
Certificates of Architect (Form 4)File: FORM 4 G-H.pdf20 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERT JAN 2019.pdf20 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERT JAN 2019.pdf20 Feb 2019
Certificates of CA (Form 3)File: CA FORM CERT JAN 19.pdf20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERTIFICATE JUNE 18.pdf2 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERT JAN 2019.pdf2 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERTIFICATE SEPT 18.pdf2 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTFICATE JUNE 18.pdf2 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERT JAN 2019.pdf2 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTFICATE SEPT 18.pdf2 Feb 2019
Certificates of CA (Form 3)File: CA CERT JUNE 18.pdf2 Feb 2019
Certificates of CA (Form 3)File: CA CERT SEPT 18.pdf2 Feb 2019
Certificates of CA (Form 5)File: Form_GH.pdf15 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Certificate GH 31st Mar 18.PDF16 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Cer GH 31st Mar 18.PDF16 May 2018
Certificates of CA (Form 3)File: Form 3 CA Certificate GH 31st Mar 18.PDF16 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: G H Architects Inc.PDF29 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GH.PDF29 Jan 2018
Certificates of CA (Form 3)File: CAC G H.PDF29 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Certificte GH Nov17.PDF13 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Cer Aryan GH Nov17.PDF13 Jan 2018
Certificates of CA (Form 3)File: CA CERTIFICATE UPTO 30TH SEP GH WING.PDF13 Jan 2018
Proforma of Allotment letterFile: Aryan One Wing G and H Updated Agreement.pdf24 Aug 2017
Layout approvalFile: Aryan One Common Layout 1 Wing A To J.pdf27 Jul 2017
Building plan approvalFile: Aryan One Layout 14 Wing H.pdf27 Jul 2017
Building plan approvalFile: Aryan One Layout 13 Wing H.pdf27 Jul 2017
Building plan approvalFile: Aryan One Layout 11 Wing G.pdf27 Jul 2017
Building plan approvalFile: Aryan One Layout 12 Wing G.pdf27 Jul 2017
PAN CardFile: Konark Lifespaces PAN CARD.PDF27 Jul 2017
Copy of the legal title reportFile: AryanOne TR ( 75-2 )-( 79-9 )-(78-3).pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR (70-2)-(76-2)-(98-6).pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 75-1.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 75-3_opt.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 75-5.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 75-6.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 76-1.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 76-3.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 77.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 79-10.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 98-5.pdf27 Jul 2017
Copy of the legal title reportFile: AryanOne TR 102-6.pdf27 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.PDF27 Jul 2017
Copy of Layout Approval (in case of layout)File: Aryan One Common Layout 1 Wing A To J.pdf27 Jul 2017
Building Plan Approval (IOD)File: Aryan One Layout 11 Wing G.pdf27 Jul 2017
Building Plan Approval (IOD)File: Aryan One Layout 12 Wing G.pdf27 Jul 2017
Building Plan Approval (IOD)File: Aryan One Layout 13 Wing H.pdf27 Jul 2017
Building Plan Approval (IOD)File: Aryan One Layout 14 Wing H.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Aryan one Commencement Certificate 2014-2015-2016.pdf27 Jul 2017
Declaration in FORM BFile: FORM B Aryan One Wing G H.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Certificate Aryan G H.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Aryan One Wing G H.pdf27 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Aryan One Wing G H.pdf27 Jul 2017
Proforma of Allotment letterFile: Aryan One Final Agreement Wing G H.pdf27 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
ARYAN ONE WING A B C DSHIRGAON BADLAPUR196CompletedJan 2017Late, May 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARYAN ONE WING G AND H on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur (M Cl)7,600+ in Thane

2 kmARYAN ONE WING G AND HCompleted 144Lapsed / revoked 52Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 289 registered projects within 2 km.

Builder: Konark Lifespaces

Konark Lifespaces has 3 registrations on MahaRERA, including ARYAN ONE WING E AND F and ARYAN ONE WING G AND H. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ARYAN ONE WING G AND H is delayed beyond 31 Jul 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARYAN ONE WING G AND H?

The registered promoter entity is Konark Lifespaces, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARYAN ONE WING G AND H?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARYAN ONE WING G AND H?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARYAN ONE WING G AND H?

The professionals named in the filing: Architect: ARCHITECT INCORPORATE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARYAN ONE WING G AND H?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARYAN ONE WING G AND H. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARYAN ONE WING G AND H to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.