Arvind Elan
RG-MH-81987 · RERA P52100018613 · Last updated on MahaRERA portal: 28 Nov 2024
Source: official MahaRERA filing
Red flags
- 2 complaints at MahaRERA
- 1 extension taken
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Arvind Elan is a Residential / Group Housing project by Yogita Shelters LLP in Pune, Maharashtra, registered with MahaRERA as P52100018613 on 22 Nov 2018. The registration is recorded completed; possession was promised by 30 Dec 2023. 2 complaints are on record with the regulator.
At a glance
Project
- NameArvind Elan
- TypeResidential / Group Housing
- Location
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- RERA no.P52100018613
- ReraGenie IDRG-MH-81987
Builder
- NameYogita Shelters LLP
- Entity typeOthers
- Named personsAnkit Jain, SAURABH AGARWAL
- PartnerPRAKASH BHOGIBHAI MAKWANA
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Nov 2018
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings2 building records
- Documents filed107 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Arvind Elan Block A and B | NA | 15 | 0 | 0 | 0 | 0 |
| Block C MHADA | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 28 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 60%.
Arvind Elan Block A and B87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Block C MHADA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 28 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed133
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Arvind Elan Block A and B | 122 | 5 | 127 |
| Block C MHADA | 6 | 0 | 6 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Yogita Shelters LLP | Kothrud | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arch. Vikas Achalkar, A & T Consultants |
| Engineer | M/s JW Consultants LLP |
| Engineer | SANGRAM LAIGUDE |
| Chartered Accountant | RAVI SHAH |
| Chartered Accountant | MEET DIPAKBHAI SHAH |
| Partner | Role in project |
|---|---|
| Yogita Shelters LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTill date we had completed about 75% Project Development. After registration of project we have got some additional development potentials from MHADA as per their fresh policies. We already had submitted our fresh approvals and further CC to RERA. We need additional time to explore further potentials available to us. Hence we are hereby applying for 1st Extension of our real estate project
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000177757 | YOGESH SHAMLAL THAKUR | M/S YOGITA SHELTERS, LLP | 09/11/2022 |
| CC005000000290116 | TUSHAR ANIL MORE | Yogita Shelters LLP | 17/01/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Nov 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Nov 2024
Documents filed107
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Promoter Signed.pdf | 28 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Arvind Elan Wing A AND B Certificate .pdf | 28 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Arvind Elan Wing C Certificate .pdf | 28 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy certificate Elan A,B C.pdf | 28 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy certificate Elan Club.pdf | 28 Nov 2024 |
| Other - FinanceFile: closure RERA account hdfc.pdf | 28 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA Architects Q2 2024-25 FINAL.pdf | 17 Oct 2024 |
| Certificates of CA (Form 3)File: Elan CA Certificate Promoter Signed.pdf | 17 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA ENGINEER FORM 2 KOTHARUD Q2 2024-25 FINAL.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Elan_Signed.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCHITECT CERTIFICATE Q1-2024-25.PDF | 11 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 engineer Certificate Q1-2024-25.pdf | 11 Jul 2024 |
| Certificates of CA (Form 3)File: CA Certificate Promoter signed.pdf | 9 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM_2 A 223-24.pdf | 2 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Elan Architect Certificate Q4.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate Q4 2023-24.pdf | 18 Apr 2024 |
| Certificates of CA (Form 3)File: ca.pdf | 16 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM -1 Architect certificate Q2 2023-24_compressed.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer certificate Q3 2023-24_compressed.pdf | 17 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Elan_compressed.pdf | 17 Jan 2024 |
| Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf | 2 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold declaration 30 december 2023.pdf | 2 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA Architects Q2 202324 FINAL.pdf | 18 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (FY 19-20).pdf | 18 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 engineer q2 2324.pdf | 17 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (FY 21-22).pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A (FY 22-23).pdf | 12 Oct 2023 |
| Certificates of CA (Form 3)File: form 3 q2 23 24_compressed.pdf | 12 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed_Form 5 2223_compressed.pdf | 7 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Elan Form 1 Engineer Q1 2324 signed.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Elan Form 2 Engineer Q1 2324 signed.pdf | 19 Jul 2023 |
| Certificates of CA (Form 3)File: Fina Form 3 Q 1 2324.pdf | 17 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 ARCHITECT'S CERTIFICATE Q4 2022-23_compressed.pdf | 8 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE Q4 2022-23.pdf | 8 May 2023 |
| Certificates of CA (Form 3)File: Arvind Elan Form 3_Signed q3.pdf | 8 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From 1 Architect's Certificate rera Q3 202-23_compressed.pdf | 17 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 engineer certificate rera Q3 2022-23_compressed.pdf | 17 Jan 2023 |
| Certificates of CA (Form 3)File: Elan Form 3_merged ARVIND Q 3.pdf | 13 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_compressed.pdf | 15 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf | 15 Oct 2022 |
| Certificates of CA (Form 3)File: ca q2 2223_compressed.pdf | 8 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ELAN FORM 5.pdf | 8 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 18 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure - A_compressed.pdf | 18 Jul 2022 |
| Certificates of CA (Form 3)File: ca certificate_compressed.pdf | 18 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM -1 ARCHITECTURE CERTIFICATE Q4 2021-22_compressed.pdf | 14 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE Q4 2021-22.pdf | 14 Apr 2022 |
| Certificates of CA (Form 3)File: ELAN CA Certifiacte 31-03-2022_compressed.pdf | 14 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA Architects Q3 25012022_compressed.pdf | 29 Jan 2022 |
| Building plan approvalFile: DRAWING 1 OF 8_compressed (1).pdf | 27 Jan 2022 |
| Layout approvalFile: DRAWING 1 OF 8_compressed (1).pdf | 27 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: DRAWING 1 OF 8_compressed (1).pdf | 27 Jan 2022 |
| Building Plan Approval (IOD)File: DRAWING 1 OF 8_compressed (1).pdf | 27 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE DEC 2021.pdf | 27 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA Architects Q3 25012022.pdf | 27 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Elan Engineer's Certificate Q-3.pdf | 27 Jan 2022 |
| Certificates of CA (Form 3)File: CA Q3 2122_compressed (1).pdf | 26 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2 A 20 21.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ELAN FORM 5 CERTIFICATES 18 19.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ELAN FORM 5 CERTIFICATES 19 20.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ELAN FORM 5 CERTIFICATES 20 21.pdf | 7 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RERA Architects Q2 30122021_compressed.pdf | 4 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA ENGINEER FORM 2 KOTHARUD 30122021Q2 FINAL_compressed.pdf | 4 Jan 2022 |
| Certificates of CA (Form 3)File: CA Q2 2122.pdf | 4 Jan 2022 |
| Certificates of CA (Form 3)File: ARVIND ELAN q1 202122.pdf | 3 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_compressed.pdf | 29 Dec 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q1 2020-21.pdf | 29 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1 2021-22.pdf | 29 Dec 2021 |
| Layout approvalFile: arvind elan.pdf | 12 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: arvind elan.pdf | 12 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate DMS No 42103.pdf | 31 Jul 2021 |
| Declaration about Commencement CertificateFile: ELAN declartion - RERA.pdf | 31 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Inventory Details RERA.pdf | 31 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE THE YOGITA.pdf | 26 Jun 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE THE YOGITA.pdf | 26 Jun 2021 |
| Certificates of CA (Form 3)File: Elan Form 3.pdf | 26 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT 01072020.pdf | 26 Feb 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT 01102020.pdf | 26 Feb 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT 01012021.pdf | 26 Feb 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE FORM 2 q1 2021.pdf | 16 Feb 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 107 filed documents as one ZIP, foldered, with a manifest
Keep Arvind Elan on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kothrud13,700+ in Pune
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: Yogita Shelters LLP
Yogita Shelters LLP has 1 registration on MahaRERA, including Arvind Elan. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Arvind Elan is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Arvind Elan?
The registered promoter entity is Yogita Shelters LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Arvind Elan?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Arvind Elan?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Arvind Elan?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Arvind Elan?
The professionals named in the filing: Architect: Arch. Vikas Achalkar, A & T Consultants; Engineer: M/s JW Consultants LLP; Engineer: SANGRAM LAIGUDE; Chartered Accountant: RAVI SHAH; Chartered Accountant: MEET DIPAKBHAI SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Arvind Elan?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.