ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ARSH COMPLAX

Registered No litigation declared Residential / Group Housing project

ARSH COMPLAX

By MILAN DEVELOPERS

RG-MH-21424 · RERA P52100029490 · Last updated on MahaRERA portal: 23 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 59 months, 4 of them under MahaRERA's automatic 4-month extension
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2028Possession promisedmoved 59 months from the original
1 of 11Construction stages donefurthest along: Slabs of Super Structure, 40%
26 of 27Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 116 documents Report an error

ARSH COMPLAX is a Residential / Group Housing project by MILAN DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100029490 on 4 Jun 2021. Possession is promised by 30 Apr 2028. The completion date has moved by 59 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 1 of the 27 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameARSH COMPLAX
  • TypeResidential / Group Housing
  • Location
    • Pune
    • Peth
    • Haveli
    • 411002
  • Pincode411002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029490
  • ReraGenie IDRG-MH-21424

Builder

  • NameMILAN DEVELOPERS
  • Entity typePartnership
  • PartnersMUJASSIM TAWAKKAL KAMBLE, WASIM AYUB KAMBLE
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJun 2021First promiseMay 2023Revised toApr 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Jun 2021
  • Promised completion30 Apr 2028
  • Revised completionRevised to 30 Apr 2028 (originally 31 May 2023)
  • Buildings1 building record
  • Documents filed116 files

Current status

4%1 of 27 units booked
72.6%Work done, per cost certificate

Figures as on 23 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARSH COMPLAXNA7624327

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 40%.

ARSH COMPLAX: 19% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)30%
Podiums (if any)0%
Plinth30%
Stilt Floor0%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Open Space1

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area613 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Sep 2026
LandownerVillageDistrict
WASIM AYUB KAMBLEPune (M Corp.)Pune
MUJASSIM TAWAKKAL KAMBLEPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPOONA MUNICIPAL CORPORATION
Permissible FSI833.52
Proposed, not sanctioned834 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch648, SRI ASSOCIATES KUMTEKAR ROAD, PUNE
Estimated costRs 7.58 cr
Cost incurredRs 5.50 cr
Work done72.56%
BuildingWingEstimatedIncurred
ARSH COMPLAXNARs 6.50 crRs 4.50 cr
-NARs 1.08 crRs 1.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHIL SHAIKH
EngineerFAROOK MULLA
EngineerSHIVAJI MANE
Chartered AccountantDHEERAJ DHARMAWAT
Chartered AccountantSAGAR SHARAD DHARMAVAT
PartnerRole in project
MILAN DEVELOPERS-

Extensions2

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Dec 2027 → Apr 2028

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EXT52100019761May 2023 → Dec 2027

Reason as filed by the promoterThe project has experienced delays due to circumstances beyond our control. The progress of construction was adversely affected by force majeure conditions including disruptions caused by the COVID-19 pandemic, migration and shortage of skilled labour, and interruptions in the supply chain of essential construction materials. Additionally, delays in obtaining statutory approvals and services from concerned authorities, unforeseen site-related challenges, and extended periods of adverse weather further impacted the construction schedule. These factors collectively slowed the pace of execution d

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2028

Documents filed116

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Q1 2627.pdf23 Sep 2026
Withdrawal Update Form 2File: FORM 2 Q1 2627.pdf23 Sep 2026
Withdrawal Update Form 3File: FORM 3 Q1 2627.pdf23 Sep 2026
Withdrawal Update Form 1File: Architects Certificate 1 Q3 25-26.pdf22 Sep 2026
Withdrawal Update Form 1File: FORM 1 Q4 26.pdf22 Sep 2026
Withdrawal Update Form 1File: FORM 1 Q1 2627.pdf22 Sep 2026
Withdrawal Update Form 2File: Eng Certificate Q3 25-26.pdf22 Sep 2026
Withdrawal Update Form 2File: FORM 2 Q4 26.pdf22 Sep 2026
Withdrawal Update Form 2File: FORM 2 Q1 2627.pdf22 Sep 2026
Withdrawal Update Form 3File: FORM 3 Q4 25-26.pdf22 Sep 2026
Withdrawal Update Form 3File: FORM 3 Q4 25-26.pdf22 Sep 2026
Withdrawal Update Form 3File: FORM 3 Q1 2627.pdf22 Sep 2026
Withdrawal Update Form 1File: Architects Certificate Final Q2 25-26.pdf18 Sep 2026
Withdrawal Update Form 1File: Architects Certificate Final Q1.pdf18 Sep 2026
Withdrawal Update Form 1File: Architects Certificate 1 Q3 25-26.pdf18 Sep 2026
Withdrawal Update Form 2File: Eng Certificate Q2 25-26.pdf18 Sep 2026
Withdrawal Update Form 2File: Eng Certificate Q2 25-26.pdf18 Sep 2026
Withdrawal Update Form 2File: Eng Certificate Q3 25-26.pdf18 Sep 2026
Withdrawal Update Form 3File: CA Certificate ForM 3 - Q2 Signed.pdf18 Sep 2026
Withdrawal Update Form 3File: CA Certificate ForM 3 - Q1 Signed.pdf18 Sep 2026
Withdrawal Update Form 3File: CA Certificate ForM 3 - Q3.pdf18 Sep 2026
Form 2A (FY 2024-2025)File: Quality Assurance Certificate 2024-25.pdf18 Sep 2026
Form 2A (FY 2025-2026)File: Quality Assurance Certificate 2025-26.pdf18 Sep 2026
Form 5 (FY 2023-2024)File: FORM 5 2024 Signed.pdf7 Sep 2026
Form 5 (FY 2024-2025)File: FORM 5 2025 Signed.pdf7 Sep 2026
Form 1File: Architects Certificate 1 Q4 2526.pdf3 Sep 2026
Form 2File: Eng Certificate Q4 2526.pdf3 Sep 2026
Form 3File: form 3 q4 25-26.pdf3 Sep 2026
Disclosure of Sold and Booked InventoryFile: CamScanner.pdf3 Sep 2026
Disclosure of Sold and Booked InventoryFile: CamScanner 3.pdf3 Sep 2026
Form 1File: Architects Certificate 1 Q12627.pdf3 Sep 2026
Form 2File: Eng Certificate Updated (1).pdf3 Sep 2026
Form 3File: form 3 q1 26-27.pdf3 Sep 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30062022.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30092022.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032022.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31122022.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30062023.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30092023.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032023.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31122023.pdf30 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07012022.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07012023.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07012024.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07042022.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07042023.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07042024.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07072022.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07072023.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07102022.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 07102023.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q1.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q3.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q4.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_compressed.pdf3 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_compressed.pdf3 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 MILAN.pdf3 Jun 2024
Declaration in FORM BFile: Affidavit_compressed (1).pdf23 May 2024
Layout approvalFile: rera plan1.pdf8 May 2024
Layout approvalFile: rera plan2.pdf8 May 2024
Building plan approvalFile: rera plan1.pdf8 May 2024
Building plan approvalFile: rera plan2.pdf8 May 2024
Details of encumbrancesFile: ENCUMBRANCES.pdf8 May 2024
Copy of Layout Approval (in case of layout)File: rera plan1.pdf8 May 2024
Copy of Layout Approval (in case of layout)File: rera plan2.pdf8 May 2024
Building Plan Approval / NA Order for plotted developmentFile: rera plan1.pdf8 May 2024
Building Plan Approval / NA Order for plotted developmentFile: rera plan2.pdf8 May 2024
Declaration about Commencement CertificateFile: Commencment Certificate.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_compressed.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Eng certificate_compressed.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: Sold and Unsold_compressed.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASS.pdf12 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASS.pdf12 Dec 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DETAILS.pdf12 Dec 2023
CERSAI detailsFile: LEGAL ENCUBRANCES.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Milan Enterprises Form 5 22-23.pdf12 Dec 2023
Proforma of Agreement for saleFile: AGREEMENT TO SALE.pdf12 Dec 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUBRANCES.pdf5 Dec 2023
Details of encumbrances concerned to LegalFile: LEGAL ENCUBRANCES.pdf5 Dec 2023
Declaration about Commencement CertificateFile: Commencment Certificate.pdf5 Dec 2023

How this compares with Pune

4%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 59 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARSH COMPLAX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune14,000+ in Pune

2 kmARSH COMPLAXCompleted 185Lapsed / revoked 134Other 181Dot size: filed unitsN

Filed coordinates, straight-line distance. 500 registered projects within 2 km.

Builder: MILAN DEVELOPERS

MILAN DEVELOPERS has 2 registrations on MahaRERA, including MILAN HOMES and ARSH COMPLAX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ARSH COMPLAX is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARSH COMPLAX?

The registered promoter entity is MILAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARSH COMPLAX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARSH COMPLAX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARSH COMPLAX?

The professionals named in the filing: Architect: RAHIL SHAIKH; Engineer: FAROOK MULLA; Engineer: SHIVAJI MANE; Chartered Accountant: DHEERAJ DHARMAWAT; Chartered Accountant: SAGAR SHARAD DHARMAVAT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARSH COMPLAX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARSH COMPLAX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARSH COMPLAX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.