Home / Browse projects / Nashik, Maharashtra / ARKK PUSHP PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

ARKK PUSHP PHASE II

By VIJAY LALJIBHAI CHHEDA

RG-MH-13820 · RERA P51600028565 · Last updated on MahaRERA portal: 22 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
10 of 55Construction stages doneacross 5 buildings; furthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

ARKK PUSHP PHASE II is a Residential / Group Housing project by VIJAY LALJIBHAI CHHEDA in Nashik, Maharashtra, registered with MahaRERA as P51600028565 on 19 Mar 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date.

At a glance

Project

  • NameARKK PUSHP PHASE II
  • TypeResidential / Group Housing
  • Location
    • VIJAY NAGAR
    • BHAGUR
    • Bhagur (M Cl)
    • Nashik
    • 422401
  • Pincode422401
  • RERA no.P51600028565
  • ReraGenie IDRG-MH-13820

Builder

  • NameVIJAY LALJIBHAI CHHEDA
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

4 months past promisethis monthRegisteredMar 2021PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Mar 2021
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings5 building records
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA40000
BUILDING BNA40000
BUILDING CNA40000
BUILDING DNA50000
BUILDING ENA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 22 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 90%.

BUILDING A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING C86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING D86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING E5%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered5
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
BUILDING A145
BUILDING B145
BUILDING C145
BUILDING D145
BUILDING E145

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,400 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1875.62
Proposed, not sanctioned1,876 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNASIK ROAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKESHAV ADKE
EngineerK V ADKE ENGINEERS
Chartered AccountantbHUSHAN gOSAR & aSSOCIATES
PartnerRole in project
VIJAY LALJIBHAI CHHEDA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Self Declaration March 24.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Self Declaration June 24.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Self Declaration Sept 24.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Self Declaration Dec 24.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Self Declaration March 24.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Self Declaration June 24.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Self Declaration Sept 24.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Self Declaration Dec 24.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Self Declaration March 24.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Self Declaration June 24.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Self Declaration Sept 24.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Self Declaration Dec 24.pdf22 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ARKK PUSHPII FORM 5.pdf22 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Arkk Pushp phase II Form 5 22-23.pdf12 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARKK PUSHP II_0001.pdf10 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ARKK PUSHP II_0001.pdf10 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 ARKK PUSHP II_0001.pdf10 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arkk Pushp Phase II Dec 22.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate ARKK PUSHP II.pdf4 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Arkk Pushp Phase II Dec 22.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Arkk Pushp Phase II Form 5 Mar 22.pdf28 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Arkk Pushp Phase II MAR 21.pdf28 Sep 2021
Declaration about Commencement CertificateFile: declaration of commencement Arkk Pushp Phase II.pdf15 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arkk Pushp Phase II.pdf15 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Arkk Pushp Phase II.pdf15 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Arkk Pushp Phase II.pdf15 Aug 2021
Disclosure of sold/ booked inventoryFile: disclosure of sold Arkk Pushp Phase II.pdf15 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Arkk Pushp Phase II.pdf15 Aug 2021
Layout approvalFile: Plan Part 1.pdf10 Mar 2021
Layout approvalFile: Plan Part 2.pdf10 Mar 2021
Layout approvalFile: Plan Part 3.pdf10 Mar 2021
Layout approvalFile: Stamp of Authority Cantonment.pdf10 Mar 2021
Building plan approvalFile: Plan Part 1.pdf10 Mar 2021
Building plan approvalFile: Plan Part 2.pdf10 Mar 2021
Building plan approvalFile: Plan Part 3.pdf10 Mar 2021
Building plan approvalFile: Stamp of Authority Cantonment.pdf10 Mar 2021
Building plan approvalFile: Commencement Arkk Pushp Phase II.pdf10 Mar 2021
PAN CardFile: Vijay Laljibhai Chheda.pdf10 Mar 2021
Copy of the legal title reportFile: Title Search Arkk Pushp Phase II.pdf10 Mar 2021
Details of encumbrancesFile: Letter of encurbrance Arkk Pushp Phase II.pdf10 Mar 2021
Copy of Layout Approval (in case of layout)File: Plan Part 1.pdf10 Mar 2021
Copy of Layout Approval (in case of layout)File: Plan Part 2.pdf10 Mar 2021
Copy of Layout Approval (in case of layout)File: Plan Part 3.pdf10 Mar 2021
Copy of Layout Approval (in case of layout)File: Stamp of Authority Cantonment.pdf10 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Part 1.pdf10 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Part 2.pdf10 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Part 3.pdf10 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Stamp of Authority Cantonment.pdf10 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Commencement Arkk Pushp Phase II.pdf10 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Arkk Pushp Phase II.pdf10 Mar 2021
Declaration in FORM BFile: Form B Arkk Pushp Phase II.pdf10 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Arkk Pushp Phase II.pdf10 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Arkk Pushp Phase II.pdf10 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 3 CA Certificate Arkk Pushp Phase II.pdf10 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Arkk Pushp Phase II.pdf10 Mar 2021
Proforma of Allotment letterFile: Draft Allotment Letter Arkk Pushp Phase II.pdf10 Mar 2021
Proforma of Allotment letterFile: Agreement To Sell Rera Draft pushp Phase II.pdf10 Mar 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARKK PUSHP PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHAGUR4,100+ in Nashik

Builder: VIJAY LALJIBHAI CHHEDA

VIJAY LALJIBHAI CHHEDA has 2 registrations on MahaRERA, including ASHTAPAD and ARKK PUSHP PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that ARKK PUSHP PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ARKK PUSHP PHASE II is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARKK PUSHP PHASE II?

The registered promoter entity is VIJAY LALJIBHAI CHHEDA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARKK PUSHP PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARKK PUSHP PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARKK PUSHP PHASE II?

The professionals named in the filing: Architect: KESHAV ADKE; Engineer: K V ADKE ENGINEERS; Chartered Accountant: bHUSHAN gOSAR & aSSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARKK PUSHP PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARKK PUSHP PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARKK PUSHP PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.