Home / Browse projects / Mumbai Suburban, Maharashtra / Arkade Prime
Arkade Prime
By M/s. Arkade Developers Pvt Ltd.
RG-MH-47072 · RERA P51800047081 · Last updated on MahaRERA portal: 4 Feb 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 8 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Arkade Prime is a Others project by M/s. Arkade Developers Pvt Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047081 on 29 Sep 2022. The registration is recorded completed; possession was promised by 31 Dec 2025.
At a glance
Project
- NameArkade Prime
- TypeOthers
- Location
- Andheri - Kurla Road
- Makwana Road
- Andheri East
- Andheri
- Mumbai Suburban
- 400059
- Pincode400059
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800047081
- ReraGenie IDRG-MH-47072
Builder
- NameM/s. Arkade Developers Pvt Ltd.
- Entity typeCompany
- CINU45200MH1986PLC039813
- GSTIN27AAACA3578Q1Z4
- DirectorsAmit Mangilal Jain, Sandeep Ummedmal Jain, Arpit Vikram Jain
- Declared earlier projects8 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Sep 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings2 building records
- Documents filed91 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 16 | 0 | 0 | 0 | 0 |
| Wing B | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 4 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.
Wing A81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 18% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 74% |
Wing B76%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 74% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 74% |
Progress on shared amenities18
As on 4 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | No | Not applicable |
| Swimming Pool | Yes | 50% |
| Fitness Center and Society Office | Yes | 80% |
| Car Parking System | Yes | 80% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kalakruti Architects & Planners |
| Engineer | Jignesh Mohan Patel |
| Engineer | Hiren M. Tanna |
| Chartered Accountant | Santosh B Morge & Co |
| Chartered Accountant | Amit T. Jain & Co |
| Partner | Role in project |
|---|---|
| M/s. Arkade Developers Pvt Ltd. | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Aug 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Feb 2025
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: ARK-PRIME- Form 4.pdf | 4 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2455920_OC_signed.pdf | 3 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prime Form 3 Dec 24_compressed.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Arkade Prime Dec 24.pdf | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Prime Dec 24.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Prime Inventory Declaration dec 24.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Prime Sep 24.pdf | 7 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prime Sep 24-Both sign_compressed.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prime form 3 Sep 24_compressed.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Prime Sep 24.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Arkade Prime - Form 5-FY 24.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Prime Sep 2024.pdf | 14 Oct 2024 |
| Layout approvalFile: Prime IOD _1.pdf | 5 Aug 2024 |
| Layout approvalFile: Prime -2.pdf | 5 Aug 2024 |
| Layout approvalFile: Prime -3.pdf | 5 Aug 2024 |
| Layout approvalFile: Prime -4.pdf | 5 Aug 2024 |
| Layout approvalFile: Prime IOD-5.pdf | 5 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Prime IOD _1.pdf | 5 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Prime -2.pdf | 5 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Prime -3.pdf | 5 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Prime -4.pdf | 5 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Prime IOD-5.pdf | 5 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Prime_Up to June 2024.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventories Prime-Jun 24 Final.pdf | 24 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 june prime jun 24_compressed.pdf | 24 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Prime Jun 24.pdf | 13 Jul 2024 |
| Declaration about Commencement CertificateFile: FurtherCC_signed_prime.pdf | 3 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold UnSold March 24 Arkade Prime_compressed.pdf | 25 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Untitled_20240424_110627_PRIME MAR 24_compressed.pdf | 24 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arkade Prime Form 2 March 2024.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Prime March 2024.pdf | 11 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Arkade Prime March 24.pdf | 10 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Arkade Prime Part OC signed.pdf | 4 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation 28082024.pdf | 16 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Prime Dec 23-1.pdf | 6 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Arkade Prime Dec 23.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Arkade Prime Dec 23.pdf | 31 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23 Prime.pdf | 22 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Arkade Prime - Mar 23.pdf | 6 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2 - Engg Certificate - Arkade Prime Sep 23_compressed.pdf | 3 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arkade Prime - Form 3 Sep 23 - Signed_compressed.pdf | 2 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Arkade Prime sold Unsold Delc Sept 23.pdf | 1 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arkade Prime_June 23.pdf | 9 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arkade Prime_Sep 23.pdf | 9 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 23 Arkade Prime.pdf | 9 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Arkade Prime March 23.pdf | 16 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Declaration June 23 - Arkade Prime.pdf | 16 Aug 2023 |
| Proforma of Agreement for saleFile: Agreemen-Prime-.pdf | 16 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Arkade Prime_Up to June 2023.pdf | 4 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arkade Prime Form 3_compressed.pdf | 4 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - June 23.pdf | 10 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 2380991_FurtherCC_signed.pdf | 30 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Arkade Prime March 23.pdf | 30 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arkade Prime Form 3 31032023.pdf | 17 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arkade Prime.pdf | 9 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Arkade Prime Dec 2022_compressed_11zon.pdf | 19 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arkade Prime.pdf | 16 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Arkade Prime Dec 2022.pdf | 16 Jan 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance Letter - Prime.pdf | 16 Sep 2022 |
| Proforma of Allotment letterFile: Draft Allotment Letter - Prime_11zon.pdf | 16 Sep 2022 |
| Proforma of Allotment letterFile: Draft Agreement for Sale - Prime Part 1_11zon.pdf | 16 Sep 2022 |
| Proforma of Allotment letterFile: Draft Agreement for Sale - Prime Part 2_11zon.pdf | 16 Sep 2022 |
| Deviation Report with respect to Allotment letterFile: AL Deviation report - Prime.pdf | 16 Sep 2022 |
| Deviation Report with respect to model copy of AgreementFile: AFS Deviation Letter - Prime.pdf | 16 Sep 2022 |
| Layout approvalFile: Drawing-1.pdf | 14 Sep 2022 |
| Layout approvalFile: Drawing-2.pdf | 14 Sep 2022 |
| Layout approvalFile: Drawing-3.pdf | 14 Sep 2022 |
| Layout approvalFile: Drawing-4.pdf | 14 Sep 2022 |
| Layout approvalFile: Drawing-5.pdf | 14 Sep 2022 |
| Building plan approvalFile: Drawing-1.pdf | 14 Sep 2022 |
| Building plan approvalFile: Drawing-2.pdf | 14 Sep 2022 |
| Building plan approvalFile: Drawing-3.pdf | 14 Sep 2022 |
| Building plan approvalFile: Drawing-4.pdf | 14 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: Drawing-1.pdf | 14 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: Drawing-2.pdf | 14 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: Drawing-3.pdf | 14 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: Drawing-4.pdf | 14 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: Drawing-5.pdf | 14 Sep 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing-1.pdf | 14 Sep 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing-2.pdf | 14 Sep 2022 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Arkade Earth - Carnation | Arkade Earth Kanjurmarg East Mumbai 400063 | 86 | Completed | Dec 2023 | Apr 2021 |
| Arkade Earth - Bluebell | Arkade Earth Kanjurmarg East Mumbai 400063 | 86 | Completed | Dec 2023 | Apr 2021 |
| Arkade Earth - Aspen | Arkade Earth Kanjurmarg East Mumbai 400063 | 86 | Completed | Dec 2023 | Apr 2021 |
| Arkade Earth - Hazel | Arkade Earth Kanjurmarg East Mumbai 400063 | 90 | Completed | Dec 2022 | Apr 2022 |
| Arkade Earth - Gardenia | Arkade Earth Kanjurmarg East Mumbai 400063 | 86 | Completed | Dec 2022 | Feb 2020 |
| Arkade Earth - Fern | Arkade Earth Kanjurmarg East Mumbai 63 | 86 | Completed | Dec 2022 | Feb 2020 |
| Arkade Earth - Ebony | Arkade Earth Kanjurmarg East Mumbai 400063 | 86 | Completed | Dec 2022 | Feb 2020 |
| Arkade Earth - Daffodil | Arkade Earth Kanjurmarg East Mumbai 400063 | 86 | Completed | Dec 2022 | Feb 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
Keep Arkade Prime on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri East6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 217 registered projects within 2 km.
SKYLINE BUSINESS WORLD WING C
Skyline Prashasti
NAMAN PREMIER
SHREE NAMAN DEVELOPERS PVT LTD
I STAY TOWER K (STUDIO)
I-STAY HOUSING PRIVATE LIMITED
CHANDAK SARVAM
CHANDAK REALTORS PRIVATE LIMITED
TRILIVE MAROL TOWER B
I-STAY HOUSING PRIVATE LIMITED
TBC Marol Phase 1
AGATE REALTORS AND DEVELOPERS
See every Mumbai Suburban project, with the district possession charts
Builder: M/s. Arkade Developers Pvt Ltd.
M/s. Arkade Developers Pvt Ltd. has 1 registration on MahaRERA, including Arkade Prime. Its filings disclose 8 earlier MahaRERA projects: declares 8 of 8 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Arkade Prime is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Arkade Prime?
The registered promoter entity is M/s. Arkade Developers Pvt Ltd., a company as per the filing. Its CIN U45200MH1986PLC039813 and GSTIN 27AAACA3578Q1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Arkade Prime?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Arkade Prime?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Arkade Prime?
The professionals named in the filing: Architect: Kalakruti Architects & Planners; Engineer: Jignesh Mohan Patel; Engineer: Hiren M. Tanna; Chartered Accountant: Santosh B Morge & Co; Chartered Accountant: Amit T. Jain & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Arkade Prime?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback