ARIHANT ASPIRE PHASE I
RG-MH-77984 · RERA P52000014107 · Last updated on MahaRERA portal: 4 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 10 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
- Rs 150.00 crore secured on the land, in favour of TATA Capital Housing Finance Limited
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARIHANT ASPIRE PHASE I is a Residential / Group Housing project by ARIHANT ABODE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000014107 on 7 Nov 2017. Possession is promised by 30 Dec 2027. The completion date has moved by 12 months from the original filing. 1,113 of the 1,210 units on this registration are recorded sold or booked, and 17 of 33 construction stages are filed complete. 10 complaints are on record with the regulator.
At a glance
Project
- NameARIHANT ASPIRE PHASE I
- TypeResidential / Group Housing
- Location
- Palaspe
- Panvel
- Raigarh
- 410221
- Pincode410221
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000014107
- ReraGenie IDRG-MH-77984
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Nov 2017
- Promised completion30 Dec 2027
- Revised completionRevised to 30 Dec 2027 (originally 30 Dec 2026)
- Buildings6 building records
- Documents filed171 files
Current status
Figures as on 4 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ILIANA | NA | 46 | 43 | 319 | 9 | 328 |
| HORTENSIA | NA | 46 | 43 | 319 | 10 | 329 |
| DELLA | NA | 47 | 43 | 494 | 15 | 509 |
| WING B | NA | 40 | 40 | 0 | 17 | 17 |
| WING C | HORTENSIA | 49 | 43 | 0 | 12 | 12 |
| Wing F | Wing F | 47 | 42 | 0 | 15 | 15 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 33 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 90%.
ILIANA77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63% |
| Sanitary Fittings within the flats / premises | 48% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
HORTENSIA77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63% |
| Sanitary Fittings within the flats / premises | 48% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
DELLA58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 83% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 7% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 37% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING BNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
WING C · wing HORTENSIANot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Wing F · wing Wing FNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 30% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 55% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed907
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| ILIANA | 311 | 311 |
| HORTENSIA | 311 | 311 |
| DELLA | 285 | 285 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGITA BHANDARKAR |
| Engineer | KALEEM SAYYAD |
| Engineer | YOGESH RAO |
| Chartered Accountant | ANJANI KUMAR GOYAL |
| Chartered Accountant | Ummed Jain & Co. |
| Partner | Role in project |
|---|---|
| ARIHANT ABODE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe hereby state and declare that there has been a delay in the completion of the project as well as in the submission of the present request due to circumstances beyond our control. The delay has occurred due to unforeseen factors, including disruption in the supply chain of construction materials arising out of the prevailing war situation. The shipment and availability of essential construction materials were adversely affected for a significant period, which further resulted in financial constraints and impacted the overall progress of the project. Further, considering the adverse impact of
Complaints filed with MahaRERA10
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000195236 | Preeti Singh | Arihant Abode Ltd. | 14/12/2020 |
| CC006000000195238 | Preeti Singh | Arihant Abode Ltd. | 14/12/2020 |
| CC006000000199305 | surekha sanbhuiena | Arihant Abode LTD | 04/12/2021 |
| CC12400363 | Anil Kashinath Varande | ARIHANT ABODE LIMITED | 07/10/2024 |
| CC12400709 | Prakash kashinath Varande | ARIHANT ABODE LIMITED | 08/11/2024 |
| CC12401276 | kavita sunil sadarangani | ARIHANT ABODE LIMITED | 29/12/2024 |
| CC12401277 | sunil shamsunder sadarangani | ARIHANT ABODE LIMITED | 29/12/2024 |
| CC12504687 | ARIHANT ABODE LIMITED | Raja Narayan Naidu | 30/12/2025 |
| CC12601320 | VAISHALI MAHESH DAMUHSHTE | ARIHANT ABODE LIMITED | 10/03/2026 |
| SM12600278 | Bhakti Achrekar | ARIHANT ABODE LIMITED | 27/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2027
Documents filed171
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 171 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1_Aspire Phase I_31122025.pdf | 4 May 2026 |
| Form 2File: Form 2_Aspire Ph I_31122025.pdf | 4 May 2026 |
| Form 3File: Form 3_Aspire Phase I_ Final V1_revised_stamp.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Aspire Ph I_Disclosure of sold unsold units_31122025_signed.pdf | 4 May 2026 |
| Form 1File: Form 1_Aspire Ph I_310326.pdf | 4 May 2026 |
| Form 2File: Form 2_Aspire Ph I_250326.pdf | 4 May 2026 |
| Form 3File: Form 3_Aspire Ph I_250326.pdf | 4 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Aspire Ph I_Disclosure of sold unsold units_25032026_signed.pdf | 4 May 2026 |
| Form 1File: Form 1_ASPIRE PHASE I_30092025_comp.pdf | 27 Oct 2025 |
| Form 2File: Form 2_Aspire Ph I_30092025.pdf | 27 Oct 2025 |
| Form 3File: Form 3_Aspire Ph I_30092025.pdf | 27 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Aspire Ph I_Disclosure of sold unsold units_30092025.pdf | 27 Oct 2025 |
| Form 5 (FY 2024-2025)File: Aspire Phase I.pdf | 16 Oct 2025 |
| Form 2A (FY 2024-2025)File: Aspire Phase I.pdf | 30 Sep 2025 |
| Form 1File: Form 1_Aspire Ph I_30062025.pdf | 18 Jul 2025 |
| Form 2File: Form 2_Aspire Ph I_30062025.pdf | 18 Jul 2025 |
| Form 3File: Form 3_Aspire Ph I_30062025.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclsoure_Signed.pdf | 18 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 - Aspire Ph I_310325_Revised.pdf | 8 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Aspire Ph I_310325.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aspire Ph I_310325_signed.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Aspire Ph I_310325.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - Aspire Ph I_310325.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aspire Phase I_SIGNED.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 - Aspire-1 - SIGNED.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ASPIRE PH I.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 20 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Aspir Phase I_signed.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - ASPIRE PHASE I_SIGNED.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aspire Ph I.pdf | 21 Oct 2024 |
| Certificates of CA (Form 3)File: Aspire 1_SIGNED.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A ASPIRE I FY 22-23.pdf | 23 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ASPIRE I FY 23-24.pdf | 23 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aspire I.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arihant Aspire Phase I.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure SIGNED.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3 30062024 Aspire 1 SIGNED.pdf | 20 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Aspire Phase 1_FY 22-23.pdf | 7 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Aspire I - Dec 23 SIGNED.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: Aspire I - Mar 24 SIGNED.pdf | 28 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aspire Phase 1 31122023.PDF | 4 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aspire Phase 1 31032024.PDF | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aspire Phase 1 31032024.pdf | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 ASPIRE PH1 DEC2023.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: Form 3 Aspire Phase 1 Dec 23 SIGN.pdf | 2 May 2024 |
| Certificates of CA (Form 3)File: 31032024 Aspire Phase 1 SIGN.pdf | 2 May 2024 |
| Disclosure of sold/ booked inventoryFile: Arihant Aspire Phase I.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I ASPIRE PHASE I -30 SEPTEMBER 2023.PDF | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 RERA Aspire Ph I Sept 2023.pdf | 19 Oct 2023 |
| Certificates of CA (Form 3)File: Aspire Phase-1.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ASPIRE PH1 JUNE2023.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARIHANT ASPIRE PHASE I - FORM 1 - ARCHITECT CERTIFICATE 30TH JUNE 2023.PDF | 19 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I ARIHANT ASPIRE PHASE I 31 MARCH 2023.PDF | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: aspire phase 1_31032023.PDF | 21 Apr 2023 |
| Certificates of CA (Form 3)File: Aspire I_11zon (1).pdf | 21 Apr 2023 |
| Certificates of CA (Form 3)File: AspireI300322.pdf | 18 Feb 2023 |
| Certificates of CA (Form 3)File: AspireI300322.pdf | 18 Feb 2023 |
| Certificates of CA (Form 3)File: AspireI300622.pdf | 18 Feb 2023 |
| Certificates of CA (Form 3)File: AspireI300922.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE12020.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE12018.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE12019.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE12020.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE1MARCH2021.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE1MARCH2022.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE1MARCH2021.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE1JUNE2022.PDF | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1RERAASPIRE1DEC2022.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE1DEC22.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE1JUNE22.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE1MARCH22.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE1SEP22.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE12018.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE12019.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE12020.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE12021.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE1311221.PDF | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2RERAASPIRE1211221.PDF | 16 Feb 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Arihant Aspire Phase IIIP52000056197 | Panvel, Raigarh | 319 | May 2024 | Ongoing | Dec 2031 | Not due yet |
| ARIHANT ASPIRE PHASE IIP52000050712 | Panvel, Raigarh | 360 | Apr 2023 | Ongoing | Dec 2030 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 171 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARIHANT ASPIRE PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Panvel5,900+ in Raigarh
Filed coordinates, straight-line distance. 60 registered projects within 2 km.
Green Terraces, Godrej City, Panvel
CAROA PROPERTIES LLP
Nexspace, Godrej City, Panvel
CAROA PROPERTIES LLP
The Highlands, Godrej City, Panvel
CAROA PROPERTIES LLP
LA MER ONE
La Mer Homes LLP
Emperia Hill Crest
Emperia Builtcon
Yogakshema Residency Phase-II
Superb Maa Infra and Housing LLP
See every Raigarh project, with the district possession charts
Builder: ARIHANT ABODE LIMITED
ARIHANT ABODE LIMITED has 4 registrations on MahaRERA, including ARIHANT ASPIRE PHASE I and ARIHANT ASPIRE PHASE II. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if ARIHANT ASPIRE PHASE I is delayed beyond 30 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARIHANT ASPIRE PHASE I?
The registered promoter entity is ARIHANT ABODE LIMITED, a company as per the filing. Its CIN U70102MH2009PLC197090 and GSTIN 27AAICA0612R1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARIHANT ASPIRE PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ARIHANT ASPIRE PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ARIHANT ASPIRE PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARIHANT ASPIRE PHASE I?
The professionals named in the filing: Architect: YOGITA BHANDARKAR; Engineer: KALEEM SAYYAD; Engineer: YOGESH RAO; Chartered Accountant: ANJANI KUMAR GOYAL; Chartered Accountant: Ummed Jain & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARIHANT ASPIRE PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.