RG-MH-28676 · RERA P52000026790 · Last updated on MahaRERA portal: 19 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Litigation declared, 2 cases
- 6 complaints at MahaRERA
- Completion date moved by 5 months
- 1 extension taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Highlands, Godrej City, Panvel is a Residential / Group Housing project by CAROA PROPERTIES LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000026790 on 25 Oct 2020. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 5 months from the original filing. 831 of the 877 units on this registration are recorded sold or booked, and 33 of 33 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameThe Highlands, Godrej City, Panvel
- TypeResidential / Group Housing
- Location
- Old Mumbai Pune Highway
- Talegaon
- Khalapur
- Raigarh
- 410221
- Pincode410221
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000026790
- ReraGenie IDRG-MH-28676
Builder
- NameCAROA PROPERTIES LLP
- Entity typeOthers
- GSTIN27AADCC3425D1Z4
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerRAJIB DAS
- Named personsRavi Gulab Khubchandani, Uraaz Santosh Bahl, Avtejinder Harbans Mann, Swaroop Agencies Pvt. Ltd
- Other registrations11 more →
- Completed2 of 12
- Past their filed date1
- Declared earlier projects11 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Oct 2020
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 30 Apr 2026)
- Buildings3 building records
- Documents filed127 files
Current status
Figures as on 19 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | NA | 43 | 39 | 301 | 0 | 301 |
| Tower 3 | NA | 43 | 36 | 284 | 0 | 284 |
| Tower 2 | NA | 43 | 39 | 292 | 0 | 292 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
33 of 33 construction stages are filed complete across 3 buildings.
Tower 1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower 3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower 2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 45% |
| Landscaping & Tree Planting | Yes | 35% |
| Street Lighting | Yes | 20% |
| Community Buildings | Yes | 40% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 40% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 35% |
| Open Parking | Yes | 70% |
Parking filed524
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Tower 1 | 171 | 171 |
| Tower 3 | 172 | 172 |
| Tower 2 | 181 | 181 |
Land and ownership7
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Ravi Khubchandani | Kurla | Mumbai Suburban |
| Uraaz Bahl | Kurla | Mumbai Suburban |
| Avtejinder Mann | Kurla | Mumbai Suburban |
| Riaz Batlivala | Kurla | Mumbai Suburban |
| Zahan Batlivala | Kurla | Mumbai Suburban |
| Amarjit Singh | Kurla | Mumbai Suburban |
| Swaroop Agencies | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower 2 | NA | Rs 108.32 cr | Rs 92.39 cr |
| Tower 3 | NA | Rs 107.24 cr | Rs 91.47 cr |
| Tower 1 | NA | Rs 107.10 cr | Rs 91.35 cr |
| - | NA | Rs 56.45 cr | Rs 20.49 cr |
Certifying professionals and partners13
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kapadia Associates Design LLP |
| Architect | R Design Architects |
| Engineer | Whitby Wood Pritamdasani Consulting Engineers Pvt Ltd |
| Engineer | vinyasa consultants |
| Engineer | Vinayasa Consultants |
| Engineer | Rajendra V Joshi |
| Engineer | Shrishail Sharanappa Gaikwad |
| Chartered Accountant | Bafna Jain & Co |
| Chartered Accountant | AKPJ & Associates |
| Chartered Accountant | BSR and Co. LLP ( 101248W/W-100022) |
| Chartered Accountant | Bafna Jain @ Co |
| Chartered Accountant | B S R & Co. LLP |
| Partner | Role in project |
|---|---|
| CAROA PROPERTIES LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO THE COVID 19, WE HAVE FACED A LOT OF SHORTAGE OF LABOUR AND RAW MATERIAL AVAILABILITY. DUE TO THE PANDEMIC, WE REQUEST EXTENSION OF 5 MONTHS FOR THE PROJECT COMPLETION FROM APRIL 30TH 2026 TO SEPTEMBER 30, 2026.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 366/2023 | District Court Panvel | Ongoing |
| 366/2023 | CIVIL JUDGE S.D.PANVEL | Ongoing |
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000197704 | Mrunal Milind Phansalkar | Godrej Properties | 28/07/2021 |
| CC006000000197795 | SACHINKUMAR MAHENDRAKUMAR CHAUHAN | Godrej Properties | 28/07/2021 |
| CC006000000198880 | MANOJ AGIWAL | Caroa Properties LLP | 30/10/2021 |
| CC006000000209849 | Bharat Babu Ishwar Peta | COROA PROPERTIES LLP | 28/01/2022 |
| CC12501207 | Arif Ayyub Baig | CAROA PROPERTIES LLP | 11/04/2025 |
| CC12600505 | MREENAL KANT NAGENDRA NATH HALDAR | CAROA PROPERTIES LLP | 29/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Oct 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Oct 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Oct 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: The HighlandsGodrej CityPanvel.pdf | 19 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_Highlands T123.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: RERA-Withdrawal Application Form2_Highlands T123.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Highlands T123.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_Ph5T123.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: RERA-Revised Form2_Ph5 T123.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: P5 T123_compressed.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: New Form1_Ph5 T123.pdf | 19 Oct 2025 |
| Withdrawal Update Form 1File: New Form1_Ph5 T123.pdf | 19 Oct 2025 |
| Withdrawal Update Form 2File: RERA-GODREJ PANVEL_CAROA Phase5-T1 TO T3_SEPTu002725 - Final.pdf | 19 Oct 2025 |
| Withdrawal Update Form 2File: RERA-GODREJ PANVEL_CAROA Phase5-T1 TO T3_SEPTu002725 - Final.pdf | 19 Oct 2025 |
| Withdrawal Update Form 3File: New Form3_Ph5 T123_11zon.pdf | 19 Oct 2025 |
| Withdrawal Update Form 3File: New Form3_Ph5 T123_11zon.pdf | 19 Oct 2025 |
| Form 5 (FY 2024-2025)File: freecompress-Form 5 The Higlands T1-T3.pdf | 28 Aug 2025 |
| Form 1File: Form 1 P5 T123.pdf | 19 Jul 2025 |
| Form 2File: Form 2 P5 T123.pdf | 19 Jul 2025 |
| Form 3File: Form 3 P5 T123.pdf | 19 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold P5 T123.pdf | 19 Jul 2025 |
| Form 2A (FY 2024-2025)File: The Highlands_ Quality Assurance Certificate FY 25.pdf | 20 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 250402_RERA certificate phase 5_ Towers 1,2,3.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Highlands T- 1-3 Mar 25.pdf | 16 Apr 2025 |
| OtherFile: Declaration Highlands.pdf | 27 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Tower 123 The Highlands.pdf | 22 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 250108_RERA certificate phase 5_ Towers 1,2,3.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower 1-3 Dec 24_compressed.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1 TO T3_DEC'24 - Final.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate Phase 5 Tower 1_3 Sep 24.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_T1-3 1_compressed.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Tower 123 The Highlands.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GODREJ PANVEL_CAROA Phase5-T1toT3_JUNE'24 - Final.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: The Highlands, Godrej City Panvel Form 5 FY 23 24.pdf | 8 Oct 2024 |
| Form 5 (FY 2023-2024)File: Caroa The Highlands Tower 1 to 3.pdf | 2 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE T1-3 signed 1.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Tower 123 The Highlands.pdf | 17 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate T1-3 2.pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240702_RERA certificate phase 5_ Tower 3_signed.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_JUNE'24 - Final.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_JUNE'24 - Final.pdf | 16 Jul 2024 |
| Proforma of Agreement for saleFile: Draft AFS - Highland T123 - 4-6-2024.pdf | 26 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Highlands T1-T3 Mar 24_compressed (1).pdf | 19 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240405_RERA certificate phase 5_ Tower 1-3.pdf | 15 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_MAR'24 - Final.pdf | 15 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A -Godrej City - PH5 - T1- T3 -end 31-03-24.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Tower 123 The Highlands.pdf | 15 Apr 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Highland Name Reservation Certificate Tower 1 to 3.pdf | 15 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A -Godrej City - PH5 - T1 to T3 -end 31-03-23.pdf | 27 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A -Godrej City - PH5 - T1 to T3 -end 31-03-23.pdf | 26 Mar 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Highland Name Reservation Certificate Tower 1 to 3.pdf | 22 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: The Highlands - T1 T2 T3.pdf | 20 Mar 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Highland.pdf | 20 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: The Highlands - T1 T2 T3.pdf | 29 Feb 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Home Buyer Allottee Grievance Redressal Cell The Highlands, Godrej City, Panvel.pdf | 29 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Panvel PH 5_ T 1-3 Dec 2023.pdf | 19 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_DEC23 - Final.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Highlands T1-3 Dec 23 (4).pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase 5 T1-3_compressed.pdf | 16 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate phase 5_ Tower 1-3_SEPT 2023.pdf | 12 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GODREJ PANVEL_CAROA Phase5-T1toT3_SEPT'23 - Final.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_SEPT'23 - Final.pdf | 11 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase 5 Tower 1 to 3 Form 5 FY - 23_compressed.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R1_RERA_ PH5 _T 1-3 Jun 23.pdf | 25 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA_ PH5 _T 1-3 Jun 23.pdf | 24 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_JULY'23 - Final.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Phase 5 T1-3 Jun 23_Upload.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase 5 T1 to 3_compressed.pdf | 21 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PH 5A_Mar 23.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ PANVEL_CAROA Phase5-T1toT3_MAR'23 - Final.pdf | 20 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2020-DEC- 5A.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Panvel The Highlands (Phase 5A) architectural Certificate (April 2021)- Tower 1 to 3. | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Panvel The Highlands (Phase 5A) architectural Certificate (Sep 2021) -Tower 1 to 3.pd | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate phase 5A_Dec 2021.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate phase 5A_Mar 2022.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate phase 5A_ july 2022.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate phase 5A_ sEP 2022.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA certificate phase 5A_T1-3 Dec 2022.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Panvel The Highlands (Phase 5A) architectural Certificate (June 2021) -Tower 1 to 3.p | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej CityPanvel - Phase 05 A Dec 2020.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej CityPanvel - Phase 05A (T1 to T3) March 2021.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvel Phase 05A (T1 to T3) RERA Engg - June,2021.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej CityPanvel - Phase 05 A(T1 to T3) Sept 2021.pdf | 7 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 11 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep The Highlands, Godrej City, Panvel on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Talegaon5,900+ in Raigarh
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
ARIHANT ASPIRE PHASE I
ARIHANT ABODE LIMITED
Green Terraces, Godrej City, Panvel
CAROA PROPERTIES LLP
Nexspace, Godrej City, Panvel
CAROA PROPERTIES LLP
LA MER ONE
La Mer Homes LLP
Emperia Hill Crest
Emperia Builtcon
Yogakshema Residency Phase-II
Superb Maa Infra and Housing LLP
See every Raigarh project, with the district possession charts
Builder: CAROA PROPERTIES LLP
CAROA PROPERTIES LLP has 12 registrations on MahaRERA, including GODREJ CITY PANVEL PH.1 and Golf Meadows Godrej City, Panvel. Its filings disclose 11 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if The Highlands, Godrej City, Panvel is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Highlands, Godrej City, Panvel?
The registered promoter entity is CAROA PROPERTIES LLP, an others as per the filing. Its GSTIN 27AADCC3425D1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Highlands, Godrej City, Panvel?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against The Highlands, Godrej City, Panvel?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for The Highlands, Godrej City, Panvel?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Highlands, Godrej City, Panvel?
The professionals named in the filing: Architect: Kapadia Associates Design LLP; Architect: R Design Architects; Engineer: Whitby Wood Pritamdasani Consulting Engineers Pvt Ltd; Engineer: vinyasa consultants; Engineer: Vinayasa Consultants; Engineer: Rajendra V Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Highlands, Godrej City, Panvel?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback