Home / Browse projects / Thane, Maharashtra / Arihant Anmol Phase V
Arihant Anmol Phase V
By ARIHANT VATIKA REALTY PRIVATE LIMITED
RG-MH-50526 · RERA P51700049294 · Last updated on MahaRERA portal: 15 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Arihant Anmol Phase V is a Residential / Group Housing project by ARIHANT VATIKA REALTY PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700049294 on 7 Feb 2023. Possession is promised by 30 Dec 2028. 0 of the 134 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.
At a glance
Project
- NameArihant Anmol Phase V
- TypeResidential / Group Housing
- Location
- Jouveli
- Ambarnath
- Badlapur (M Cl)
- Thane
- 421503
- Pincode421503
- RERA no.P51700049294
- ReraGenie IDRG-MH-50526
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Feb 2023
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed77 files
Current status
Figures as on 15 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Arihant Anmol Phase V F | NA | 10 | 0 | 134 | 0 | 134 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
Arihant Anmol Phase V F: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed35
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Arihant Anmol Phase V F | NA | Rs 20.37 cr | Rs 1.84 cr |
| - | NA | Rs 1.17 cr | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGITA BHANDARKAR |
| Engineer | NARESH KASHINATH BHOIR |
| Engineer | KALEEM SAYYAD |
| Chartered Accountant | Ummed Jain & Co. |
| Chartered Accountant | ANJANI KUMAR GOYAL |
| Chartered Accountant | CA ANJANI GOYAL & CO |
| Partner | Role in project |
|---|---|
| ARIHANT VATIKA REALTY PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Dec 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Dec 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2028
Documents filed77
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 15 Form 1 ANMOL PH V 310326.pdf | 15 Apr 2026 |
| Withdrawal Update Form 1File: 15 Form 1 ANMOL PH V 310326.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2_Anmol Ph V_250326.pdf | 15 Apr 2026 |
| Withdrawal Update Form 2File: Form 2_Anmol Ph V_250326.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: 15 Form 3_Anmol Ph V_250326.pdf | 15 Apr 2026 |
| Withdrawal Update Form 3File: 15 Form 3_Anmol Ph V_250326.pdf | 15 Apr 2026 |
| Withdrawal Update Form 1File: Form 1_Anmol Ph V_31122025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Anmol Ph V_31122025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_Anmol Ph V_31122025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 1File: Form 1_ANMOL PHASE V_30092025.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_Anmol Ph V_30092025.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Anmol Phase V_30092025.pdf | 27 Oct 2025 |
| Form 5 (FY 2024-2025)File: Anmol Phase V.pdf | 17 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Anmol Phase V_signed.pdf | 4 Oct 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Anmol Ph V_310325.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anmol Ph-V_310325.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anmol Ph V_310325_SIGNED.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anmol Phase V.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anmol Phase V.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anmol Phase V.pdf | 19 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 19 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Anmol Phase V_signed.pdf | 12 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anmol Ph V.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - ANMOL PHASE V_SIGNED.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anmol Phase -5_SIGNED.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A ANMOL V FY 22-23.pdf | 23 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ANMOL V FY 23-24.pdf | 23 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anmol V.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ANMOL PHASE V.PDF | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure SIGNED.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30062024 Anmol 5 SIGNED.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Anmol V - Dec 23 SIGNED.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: Anmol V - Mar 24 SIGNED.pdf | 28 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Anmol Phase V 31122023.PDF | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anmol Phase V 31122023.pdf | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anmol Phase V 31122023.pdf | 4 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032024 Anmol 5 SIGN.pdf | 23 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1 (14).pdf | 3 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anmol Phase _5.pdf | 31 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE - ARIHANT ANMOL PHASE V 30TH DECEMBER 2023.PDF | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I ARIHANT ANMOL PHASE V.PDF | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 RERA Anmol Ph 5 Sept 2023.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Arihant Anmol Phase 5.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arihant Anmol Phase-V.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory-Anmol Phase V_March 2023.pdf | 28 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory_Anmol Phase V_June 2023.pdf | 28 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anmol V.pdf | 21 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA Anmol 5 June 2023.pdf | 19 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARIHANT ANMOL PHASE V- 30 JUNE 2023.PDF | 17 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anmol V_11zon.pdf | 25 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ANMOL PHASE V 31 MARCH 23.PDF | 24 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANMOL 5 MARCH2023.pdf | 19 Apr 2023 |
| Proforma of Agreement for saleFile: Agreement.pdf | 4 Feb 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation.pdf | 4 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest.pdf | 1 Feb 2023 |
| Building plan approvalFile: Building Plan3-5A.pdf | 10 Dec 2022 |
| Copy of the legal title reportFile: Anmol V Title Report Title flow.pdf | 10 Dec 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan3-5A.pdf | 10 Dec 2022 |
| Other - LegalFile: anmol v form b.pdf | 10 Dec 2022 |
| Declaration about Commencement CertificateFile: FORMAT D.pdf | 24 Nov 2022 |
| CERSAI detailsFile: Anmol V cersai.pdf | 24 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: Declaration Encumbrance of Anmol 17-11-2022.PDF | 21 Nov 2022 |
| Details of encumbrances concerned to LegalFile: Declaration Encumbrance of Anmol 17-11-2022.PDF | 21 Nov 2022 |
| Proforma of Allotment letterFile: Allotment Letter Anmol V- RERA.pdf | 21 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate1.pdf | 17 Nov 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: anmol bank DECL.pdf | 17 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: V encumbrance decl.pdf | 5 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: no Deviation in Allotment.pdf | 5 Nov 2022 |
| Layout approvalFile: 1-2.pdf | 17 Oct 2022 |
| PAN CardFile: PAN Card.pdf | 17 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: 1-2.pdf | 17 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 17 Oct 2022 |
| Declaration in FORM BFile: V form b .pdf | 17 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ANMOL PHASE 5 - F WING.PDF | 17 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ARIHANT ANMOL - PHASE 5.PDF | 17 Oct 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ARIHANT ANMOL PHASE I | JOUVELI BADLAPUR EAST | 434 | Completed | Oct 2016 | Oct 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 8 other registrations, which the RERA portal never shows together
- All 77 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Arihant Anmol Phase V on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambarnath7,600+ in Thane
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: ARIHANT VATIKA REALTY PRIVATE LIMITED
ARIHANT VATIKA REALTY PRIVATE LIMITED has 9 registrations on MahaRERA, including ARIHANT ANAIKA PHASE I and ARIHANT ANMOL PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Arihant Anmol Phase V is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Arihant Anmol Phase V?
The registered promoter entity is ARIHANT VATIKA REALTY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Arihant Anmol Phase V?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Arihant Anmol Phase V?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Arihant Anmol Phase V?
The professionals named in the filing: Architect: YOGITA BHANDARKAR; Engineer: NARESH KASHINATH BHOIR; Engineer: KALEEM SAYYAD; Chartered Accountant: Ummed Jain & Co.; Chartered Accountant: ANJANI KUMAR GOYAL; Chartered Accountant: CA ANJANI GOYAL & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Arihant Anmol Phase V?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback