Home / Browse projects / Thane, Maharashtra / ARIHANT AARADHYA PHASE I
ARIHANT AARADHYA PHASE I
By ARIHANT SUPERSTRUCTURES LIMITED
RG-MH-49374 · RERA P51700045430 · Last updated on MahaRERA portal: 16 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Rs 45.00 crore secured on the land, in favour of India Real Estate Investment fund Series
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARIHANT AARADHYA PHASE I is a Residential / Group Housing project by ARIHANT SUPERSTRUCTURES LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700045430 on 18 May 2022. Possession is promised by 31 Mar 2029. 299 of the 440 units on this registration are recorded sold or booked, and 20 of 44 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameARIHANT AARADHYA PHASE I
- TypeResidential / Group Housing
- Location
- SURVEY NO 14
- BHIWANDI
- Bapgaon
- Thane
- 421302
- Pincode421302
- RERA no.P51700045430
- ReraGenie IDRG-MH-49374
Builder
- NameARIHANT SUPERSTRUCTURES LIMITED
- Entity typeCompany
- CINL51900MH1983PLC029643
- GSTIN27AABCS1848L1Z2
- CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- DirectorsASHOKKUMAR BHANWARLAL CHHAJER, PARTH ASHOKKUMAR CHHAJER
- Other registrations13 more →
- Completed5 of 14
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 May 2022
- Promised completion31 Mar 2029
- Revised completionNone
- Buildings4 building records
- Documents filed105 files
Current status
Figures as on 16 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LAURA | NA | 15 | 14 | 110 | 0 | 110 |
| MABEL | NA | 15 | 14 | 110 | 0 | 110 |
| VALENTIA | NA | 15 | 14 | 110 | 0 | 110 |
| WESLEY | NA | 14 | 14 | 110 | 0 | 110 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 16 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 80%.
LAURA59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 66% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MABEL60%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 52% |
| Sanitary Fittings within the flats / premises | 32% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 72% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
VALENTIA62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 38% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WESLEY63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| LAURA | 1 | 1 |
| MABEL | 1 | 1 |
| VALENTIA | 1 | 1 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| LAURA | NA | Rs 16.35 cr | Rs 16.09 cr |
| MABEL | NA | Rs 16.35 cr | Rs 16.09 cr |
| VALENTIA | NA | Rs 16.35 cr | Rs 16.09 cr |
| WESLEY | NA | Rs 16.35 cr | Rs 16.09 cr |
| - | NA | Rs 3.48 cr | Rs 2.63 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGITA SHIVCHARAN BHANDARKAR |
| Engineer | KALEEM SAYYAD |
| Chartered Accountant | Anjani Goyal & Co |
| Partner | Role in project |
|---|---|
| ARIHANT SUPERSTRUCTURES LIMITED | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000397359 | Vishal D K | Arihant Superstructures Limited | 05/09/2023 |
| SM12600283 | Bhakti Achrekar | ARIHANT SUPERSTRUCTURES LIMITED | 27/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2029
Documents filed105
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: 1 Form 1_AARADHYA PHASE I_310326.pdf | 16 Apr 2026 |
| Form 2File: Form 2_Aaradhya Ph I_250326.pdf | 16 Apr 2026 |
| Form 3File: 1 Form 3_Aaradhya Ph I_250326.pdf | 16 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Aaradhya Ph I_250326_signed.pdf | 16 Apr 2026 |
| Form 1File: Form 1_Aaradhya Ph I_31122025.pdf | 3 Apr 2026 |
| Form 2File: Form 2_Aaradhya Ph I_31122025.pdf | 3 Apr 2026 |
| Form 3File: Form 3_Aaradhya Ph I_31122025.pdf | 3 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_Aaradhya Ph I_31122025.pdf | 3 Apr 2026 |
| Form 1File: Form 1_AARADHYA PHASE I_30092025.pdf | 27 Oct 2025 |
| Form 2File: Form 2_Aaradhya Ph I_30092025.pdf | 27 Oct 2025 |
| Form 3File: Form 3_Aaradhya Ph I_30092025.pdf | 27 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Aaradhya Ph II_Disclosure of sold unsold units_30092025.pdf | 27 Oct 2025 |
| Form 1File: Form 1_Aaradhya Ph 1_30062025.pdf | 18 Jul 2025 |
| Form 2File: Form 2_Aradhya Ph I_30062025.pdf | 18 Jul 2025 |
| Form 3File: Form 3_Aaradhya Ph I_30062025.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure_signed.pdf | 18 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Aaradhya Ph I_31032025.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aaradhya Ph-I_310325.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Aaradhya Phase I_310325.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Aloki Phase VI.pdf | 19 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Aaradhya Phase 1.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Aaradhya Ph I_Signed.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aaradhya Ph I.pdf | 19 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 19 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 Aaradhya Phase 1_Signed.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - AARADHYA PHASE I_SIGNED.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aaradhya Ph I.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaradhya 1_SIGNED.pdf | 19 Oct 2024 |
| Details of encumbrancesFile: Aaradhya Ph I - Finance Encumbrance Cert with Index II.pdf | 17 Oct 2024 |
| Declaration in FORM BFile: Aaradhya Ph I - Form B.pdf | 17 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A AARADHYA I FY 23-24.pdf | 23 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aaradhya I.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arihant Aaradhya Phase I.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Aaradhya Ph I SIGNED.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30-06-2024 Aaradhya I - Revised SIGNED.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Aaradhya I - Dec 23 SIGNED.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: Aaradhya I - Mar 24 SIGNED.pdf | 28 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AARADHYA PH1 DEC 2023.pdf | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aaradhya Phase I 31032024.pdf | 4 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AARADHYA PHASE I 31032024.PDF | 29 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Aaradhya Ph 1 FY 22-23.pdf | 29 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31122023 Aaradhya Phase 1 SIGN.pdf | 23 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032024 Aaradhya 1 SIGN.pdf | 23 Apr 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_Security_Interest_Id_Based_Search_17_04_2024_11_01_00_142.pdf | 17 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARIHANT AARADHYA PHASE 1 31ST DEC 2023.PDF | 22 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I ARIHANT AARADHYA PHASE I - 30 SEPTEMBER 2023.PDF | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 RERA Aaradhya Ph I Sept 2023.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Arihant Aaradhya Phase 1-ASL.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arihant Aaradhya Phase -1.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Arihant Aaradhya Phase I.pdf | 9 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaradhya 1.pdf | 24 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA AARADHYA PH1 JUNE 2023.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARIHANT AARADHYA PHASE I- FORM 1 - ARCHITECT CERTIFICATE 30TH JUNE 2023 .PDF | 19 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AARADHYA PHASE I 31MARCH 2023.PDF | 19 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA AARADHYA 1 MARCH2023.pdf | 19 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM2 RERA AARADHYA 1 MARCH2023.pdf | 19 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaradhya I_11zon.pdf | 18 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: revised CC for road condition-13-2-2023-1_11zon.pdf | 17 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaradhya June 22_11zon_F3.pdf | 8 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaradhya Sep 22_11zon_F3.pdf | 8 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaradhya Dec 22_11zon_F3.pdf | 8 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA AARADHYA1 JUNE 2022.pdf | 7 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA AARADHYA1 SEP2022.pdf | 7 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA AARADHYA1 DEC2022.pdf | 7 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AARADHYA PROJECT- FORM 1 - 30 JUNE 2022.PDF | 6 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AARADHYA PROJECT- FORM 1 - 30 SEPTEMBER 2022.PDF | 6 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AARADHYA PROJECT- FORM 1 - 31 DECEMBER 2022.PDF | 6 Mar 2023 |
| Copy of the legal title reportFile: Title Certificate_Arihant Aaradhya_RERA.pdf | 9 May 2022 |
| Details of encumbrancesFile: Declaration for Encumberance_Arihant Aaradhya Phase I_RERA.pdf | 9 May 2022 |
| Declaration about Commencement CertificateFile: Declaration for Commemcememt Certificate_Arihant Aardhya Phase I.pdf | 9 May 2022 |
| Declaration in FORM BFile: Form B_Arihant Aaradhya Phase I_RERA.pdf | 9 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Arihant Aaradhya Phase I_RERA.pdf | 9 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Arihant Aaradhya Phase I_RERA.pdf | 9 May 2022 |
| CERSAI detailsFile: Declaration for CERSAI_Arihant Aaradhya Phase I.pdf | 9 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Arihant Aaradhya Phase I_RERA.pdf | 9 May 2022 |
| Proforma of Allotment letterFile: Arihant Aradhya Draft of Agreement for Sale.pdf | 9 May 2022 |
| Proforma of Allotment letterFile: Performa of the allotement letter_Arihant Aaradhya Phase I.pdf | 9 May 2022 |
| Layout approvalFile: Layout Plan_Arihant Aaradhya.pdf | 8 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 13 other registrations, which the RERA portal never shows together
- All 105 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARIHANT AARADHYA PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHIWANDI7,600+ in Thane
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
DGT - Sector 3A - Cluster 2 - Phase 1
ADRIKA DEVELOPERS PRIVATE LIMITED
DOSTI GREATER THANE - PHASE 1
ADRIKA DEVELOPERS PRIVATE LIMITED
Dosti Greater Thane - Sector 3A - Cluster 1B -
ADRIKA DEVELOPERS PRIVATE LIMITED
USHA RESIDENCY
SHREE BUDHDEV INFRA
NARAYANI DHAM BUILDING NO 2A AND 2B
MAYA DEVELOPER
See every Thane project, with the district possession charts
Builder: ARIHANT SUPERSTRUCTURES LIMITED
ARIHANT SUPERSTRUCTURES LIMITED has 14 registrations on MahaRERA, including ARIHANT ARSHIYA PHASE II and ARIHANT ARSHIYA PHASE III. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if ARIHANT AARADHYA PHASE I is delayed beyond 31 Mar 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARIHANT AARADHYA PHASE I?
The registered promoter entity is ARIHANT SUPERSTRUCTURES LIMITED, a company as per the filing. Its CIN L51900MH1983PLC029643 and GSTIN 27AABCS1848L1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARIHANT AARADHYA PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ARIHANT AARADHYA PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ARIHANT AARADHYA PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARIHANT AARADHYA PHASE I?
The professionals named in the filing: Architect: YOGITA SHIVCHARAN BHANDARKAR; Engineer: KALEEM SAYYAD; Chartered Accountant: Anjani Goyal & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARIHANT AARADHYA PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback