Home / Browse projects / Thane, Maharashtra / Archit Jewel
Archit Jewel
RG-MH-37402 · RERA P51700009850 · Last updated on MahaRERA portal: 11 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 43 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Archit Jewel is a Others project by Archit Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700009850 on 22 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 43 months from the original filing.
At a glance
Project
- NameArchit Jewel
- TypeOthers
- Location
- Mumbra Road
- Mumbra
- Thane (M Corp.)
- Thane
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700009850
- ReraGenie IDRG-MH-37402
Builder
- NameArchit Enterprises
- Entity typePartnership
- PartnerGanesh Ramchandra Kine
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 May 2022)
- Buildings4 building records
- Documents filed73 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building No 1A | NA | 2 | 0 | 0 | 0 | 0 |
| building No 2 | NA | 16 | 0 | 0 | 0 | 0 |
| Building No 3 | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 11 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
34 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 85%.
Building No 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 1A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
building No 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 365%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 45% |
Progress on shared amenities15
As on 11 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building No 1 | 6 | 1 | 7 |
| Building No 1A | 0 | 1 | 1 |
| building No 2 | 13 | 1 | 14 |
| Building No 3 | 17 | 1 | 18 |
Land and ownership8
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Vijay Ramchandra Kine | Thane (M Corp.) | Thane |
| Shobha Nandakumar Patil | Thane (M Corp.) | Thane |
| Prabhakar Ramchandra Kine | Thane (M Corp.) | Thane |
| Nanda Datta Tare | Kalyan | Thane |
| Ganesh Ramchandra Kine | Thane (M Corp.) | Thane |
| Babybai Kesarinath Bhandari | Borivali | Mumbai Suburban |
| Ashok Ramchandra Kine | Thane (M Corp.) | Thane |
| Anjani Balu Kharkar | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Buildform Architect |
| Engineer | ShravaniConsultant |
| Partner | Role in project |
|---|---|
| Archit Enterprises | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. 3. Customers are also facing financial problems There are huge receivable from the customers but we are unable to receive the same, which in turn has affected our financial position as well. Customers and we both are highly affected in last 1 and half year. 4. Since last 3 years market slow-do
Reason as filed by the promoterThis application is for additional 4 Floors in Building no.3. As per earlier CC, we completed work of Building no.1A, 1, 2 and 3 and Form 4 Submitted for the same. In Earlier CC, sanction was up to 3 Floors only. We received extended / Revised CC on 07/03/2024 for additional floors from 4th to 7th in Building no.3. Meanwhile our uncle was hospitalised and we could not apply for extention. We hereby Request you, to grant extention for our Project- Archit Jewel till 31/12/2025. Thank you.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Sep 2023
Documents filed73
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Form B.pdf | 11 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Revised Sold Unsold Details.pdf | 11 Dec 2024 |
| Other - TechnicalFile: Reply to Maharera Mail.pdf | 11 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about Separate Bank Account for real estate projects.pdf | 6 Dec 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with Respect to Allotment Letter.pdf | 6 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with Respect to Agreement for Sale.pdf | 6 Dec 2024 |
| Proforma of Agreement for saleFile: AGreement for Sales.pdf | 6 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in Other Real Estate Organization-Ganesh Kine.pdf | 6 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Declaration with respect to Security Interest and Finance Charges.pdf | 6 Dec 2024 |
| Layout approvalFile: Plan And CC of Third Building.pdf | 3 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: Plan And CC of Third Building.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 30-09-24.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 30-06-24.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 20-03-24.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 31-12-23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificae 30-09-23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 30-06-23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 31-03-23.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 31-12-22.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 30-09-22.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate 30-06-2024.pdf | 3 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate 30-09-2024.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate 31-12-23.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30-09-24.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30-06-24.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 20-03-24.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 23-09-23.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GetUserDocumentFileContent.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31-03-23.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31-12-22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30-09-22.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30-06-23.pdf | 3 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate 31-09-22.pdf | 3 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Quality Certificate 31-12-22.pdf | 3 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Quality Certificate 30-09-24.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Annual Report 2022-23.pdf | 3 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Quality Certificate 31-03-24.pdf | 3 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Quality Certificate 30-06-24.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Annual Report 2023-24.pdf | 3 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form4 1.pdf | 30 Nov 2024 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 30 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Rera Competition Certificate - Form 4.pdf | 19 Nov 2024 |
| Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf | 12 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Competition Certificate From Architect - Form 4.pdf | 15 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Sanction Letter - Extention 3rd Floor to 7th Floor.pdf | 15 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf | 27 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_compressed.pdf | 4 Sep 2022 |
| Certificates of CA (Form 3)File: FORM 3 JAN 22 TO MAR 22_compressed.pdf | 2 Sep 2022 |
| Certificates of CA (Form 3)File: FORM 3 APR 22 TO JUN 22_compressed.pdf | 2 Sep 2022 |
| Proforma of Allotment letterFile: Revised New Allotment Letter format.pdf | 2 Sep 2022 |
| Details of encumbrances concerned to LegalFile: Legal Encrumbances.pdf | 30 Aug 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 30 Aug 2022 |
| Declaration about Commencement CertificateFile: Declaration about Comm Certificate.pdf | 30 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate 30-06-22.pdf | 30 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate 31-03-22_compressed.pdf | 30 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Quality Assurance 30-6-22_compressed.pdf | 30 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Quality Assurance 31-03-22_compressed.pdf | 30 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Sold unsold details.pdf | 30 Aug 2022 |
| CERSAI detailsFile: Cersai Report.pdf | 30 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5_compressed.pdf | 30 Aug 2022 |
| Layout approvalFile: 4-Layout.pdf | 31 Jul 2017 |
| Building plan approvalFile: 13-IOD.pdf | 31 Jul 2017 |
| PAN CardFile: 1-PAN.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: 2-Legal Titel.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: 3-Letter Of Encuberance.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 4-Layout.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 13-IOD.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Form B Archit.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certi_opt.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: 5-AFS - ARCHIT ENTERPRISES - ARCHIT JEWEL - RERA DOC.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: 5-allotment letters.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 73 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Archit Jewel on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mumbra7,600+ in Thane
Filed coordinates, straight-line distance. 87 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: Archit Enterprises
Archit Enterprises has 1 registration on MahaRERA, including Archit Jewel. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Archit Jewel shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Archit Jewel is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Archit Jewel?
The registered promoter entity is Archit Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Archit Jewel?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Archit Jewel?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Archit Jewel?
The professionals named in the filing: Architect: Buildform Architect; Engineer: ShravaniConsultant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Archit Jewel?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.