ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Apostrophe Hinjawadi Tower A

Registered No litigation declared Residential / Group Housing project

Apostrophe Hinjawadi Tower A

By HINJAWADI INFRADEVELOPMENT PVT LTD

RG-MH-33275 · RERA P52100080628 · Last updated on MahaRERA portal: 10 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 completed earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 13 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 15%
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

Apostrophe Hinjawadi Tower A is a Residential / Group Housing project by HINJAWADI INFRADEVELOPMENT PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100080628 on 23 Jun 2025. Possession is promised by 31 Dec 2028.

At a glance

Project

  • NameApostrophe Hinjawadi Tower A
  • TypeResidential / Group Housing
  • Location
    • Rajiv Gandhi Infotech Park
    • Maan Road
    • Maan
    • Hinjawadi
    • Man
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • RERA no.P52100080628
  • ReraGenie IDRG-MH-33275

Builder

  • NameHINJAWADI INFRADEVELOPMENT PVT LTD
  • Entity typeCompany
  • CINU45202MH2009PTC195028
  • DirectorsCHETAN PREMRAJ CHORDIA, Bhushan Jain
  • Other registrations13 more →
  • Completed4 of 14
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredJun 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jun 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Apostrophe Hinjawadi Tower ANA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 15%.

Apostrophe Hinjawadi Tower A: 29% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes5%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes15%
Open ParkingYes0%

Parking filed135

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots135
Open Space135

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area666 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9619.81
Proposed, not sanctioned9,620 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 12 13 and 14 opposite to Aditya Birla Hospital Pimpri Chinchwad Pune 411033

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMs Sudhir Patil and Associates
EngineerManmath Kumar Behera
EngineerAchyut Watave
Chartered AccountantMANTRI MARU & CO
PartnerRole in project
HINJAWADI INFRADEVELOPMENT PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Apostrophe Hinjawadi Tower A.PDF10 Apr 2026
Form 2File: APOH A01Jan-Mar 26.PDF10 Apr 2026
Form 3File: Apos Tower A Form 3.PDF10 Apr 2026
Disclosure of Sold and Booked InventoryFile: Apos.PDF10 Apr 2026
Form 1File: Arch Certificate Apos A.PDF19 Jan 2026
Form 2File: APOS ENGG CERTIFICATE.PDF19 Jan 2026
Form 3File: Apos Tower A form 3.PDF19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Apos A RERA inventory.PDF19 Jan 2026
Form 1File: Building A FORM 1 ARCHITECTS CERTIFICATE.PDF14 Oct 2025
Form 2File: APOS-A.PDF14 Oct 2025
Form 3File: Ahipl Tower A form 3.PDF14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Tower A Sold Unsold.PDF14 Oct 2025
Building plan approvalFile: TOWER A SANCTION PLAN_compressed.pdf16 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: TOWER A SANCTION PLAN_compressed.pdf16 Jun 2025
Building plan approvalFile: Apos A Tower Floor Plan.pdf14 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Apos A Tower Floor Plan.pdf14 Jun 2025
Other - LegalFile: Maharera Apos Tower A (1).PDF11 Jun 2025
CERSAI detailsFile: CERSAI REPORT.pdf11 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Apostrophe Hinjawadi - Tower A FORM 3.pdf10 Jun 2025
Other - LegalFile: Tower B Completion Certificate (2).pdf10 Jun 2025
Other - TechnicalFile: letter.pdf29 May 2025
Other - LegalFile: 1 Other - Technical (4).pdf21 May 2025
Other - TechnicalFile: MIDC.PDF2 May 2025
Other - TechnicalFile: Aposdeclaration cum undertaking.PDF2 May 2025
Proforma of Allotment letterFile: Allotment Letter revised.pdf29 Apr 2025
Proforma of Agreement for saleFile: Model Draft of Agreement For Sale revised.pdf29 Apr 2025
Other - LegalFile: SIROYA FM WTIH MIDC LEASE DEED NO 35 to 77_compressed.pdf25 Apr 2025
Other - LegalFile: SIROYA FM WTIH MIDC LEASE DEED 1 to 35_compressed.pdf25 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Annexure A Apos A.PDF25 Apr 2025
Other - TechnicalFile: Certificate of Incorporation.pdf25 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B of Bank Declaration revised.pdf22 Apr 2025
Declaration in FORM BFile: Form B.PDF18 Apr 2025
Declaration about Commencement CertificateFile: Declaration about CC.PDF18 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure in other organisation Brajesh Gupta pdf.pdf18 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure in other organisation.pdf18 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured unsecured finanace.PDF18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 for Apostrophe Hinjawadi Tower A.PDF15 Apr 2025
Layout approvalFile: TOWER A HIGHLIGHTED IN LAYOUT (3)_compressed.pdf11 Apr 2025
Details of encumbrances concerned to FinanceFile: Encumbrance Finanace.pdf11 Apr 2025
Details of encumbrances concerned to FinanceFile: Encumbrance legal.pdf11 Apr 2025
Copy of Layout Approval (in case of layout)File: TOWER A HIGHLIGHTED IN LAYOUT (3)_compressed.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Tower A.pdf11 Apr 2025
CERSAI detailsFile: CERSAI Declaration.pdf11 Apr 2025
Deviation Report with respect to Allotment letterFile: Deviation Allotment Apos A.pdf11 Apr 2025
Details of encumbrances concerned to LegalFile: Encumbrance Finanace.pdf11 Apr 2025
Details of encumbrances concerned to LegalFile: Encumbrance legal.pdf11 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Agreement Apos A.pdf11 Apr 2025
Copy of the legal title reportFile: STR-APO A-9-6-25 (1).PDF2 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Apos A.pdf2 Apr 2025
PAN CardFile: PAN.pdf15 Feb 2025

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Apostrophe Hinjawadi Tower BP52100048177Hinjawadi IT park Man, Pune-Dec 2022OngoingDec 2027Not due yet
Building A2 Eon homesPlot R3 1 Part Hinjawadi Phase III Man Pune 411057160-CompletedJun 2020Feb 2020
Building D3 Eon homesPlot R3 1 Part Hinjawadi Phase III Man Pune 41105780-CompletedDec 2019Mar 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Apostrophe Hinjawadi Tower A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Maan, Hinjawadi13,700+ in Pune

Builder: HINJAWADI INFRADEVELOPMENT PVT LTD

Hinjawadi Infradevelopment Pvt Ltd has 14 registrations on MahaRERA, including Building A2 Eon Homes and Building D3 Eon Homes. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Apostrophe Hinjawadi Tower A is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Apostrophe Hinjawadi Tower A?

The registered promoter entity is HINJAWADI INFRADEVELOPMENT PVT LTD, a company as per the filing. Its CIN U45202MH2009PTC195028 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Apostrophe Hinjawadi Tower A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Apostrophe Hinjawadi Tower A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Apostrophe Hinjawadi Tower A?

The professionals named in the filing: Architect: Ms Sudhir Patil and Associates; Engineer: Manmath Kumar Behera; Engineer: Achyut Watave; Chartered Accountant: MANTRI MARU & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Apostrophe Hinjawadi Tower A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Apostrophe Hinjawadi Tower A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Apostrophe Hinjawadi Tower A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.