ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Apna Ghar Phase III

Registration lapsed No litigation declared Others project

Apna Ghar Phase III

By Seven Eleven Construction Private Limited

RG-MH-97861 · RERA P51700016020 · Last updated on MahaRERA portal: 14 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 27 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
72 of 143Construction stages doneacross 13 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
3Complaints at MahaRERAon this registration
Jump to the 147 documents Report an error

Apna Ghar Phase III is a Others project by Seven Eleven Construction Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700016020 on 12 Apr 2018. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 27 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameApna Ghar Phase III
  • TypeOthers
  • Location
    • Behind Jhankar Company
    • Near Vinay Nagar
    • Village Ghodbunder
    • MIra Bhayandar road
    • MIra ROad East
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700016020
  • ReraGenie IDRG-MH-97861

Builder

  • NameSeven Eleven Construction Private Limited
  • Entity typeCompany
  • Managing DirectorSanjay Sakharam Surve
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live2 lapsed, de-registered or revoked

Key dates

19 months past promisethis monthRegisteredApr 2018First promiseDec 2022Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Apr 2018
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Dec 2022)
  • Buildings13 building records
  • Documents filed147 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA230000
A2NA230000
A3NA230000
A4NA230000
B1NA230000
B2NA230000
B3NA230000
C3NA230000
C4NA230000
Shopping ComplexNA20000
Bunglow 1NA30000
Bunglow 2NA20000
Bunglow 3NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building13

As on 14 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

72 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

A190%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
A290%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
A390%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
A490%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B190%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B290%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B390%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
C390%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
C490%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Shopping Complex0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bunglow 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bunglow 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bunglow 30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed121

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots121
Closed/Covered121
BuildingClosed/CoveredTotal
A11010
A21010
A31414
A41010
B11414
B21414
B31111
C31717
C41515
Bunglow 122
Bunglow 222
Bunglow 322

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMira Bhayandar Municipal Corporation
Permissible FSI26809.64
Proposed, not sanctioned13,025 sq m
Buildings approved13
Buildings sanctioned13

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDivine Sheraton Plaza, Jesal Park, Bhayander East, Thane 401105

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTej
EngineerAdarsh Consultant
Chartered AccountantRASHMI AGRAWAL
PartnerRole in project
Seven Eleven Construction Private Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700013108Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO NON AVAILABILITY OF CEMENT AND DUE TO DELAY IN SOME PERMISSION, WE WERE NOT ABLE TO COMPLETE THE PROJECT IN TIME, THEREFORE WE WOULD REQUEST YOU TO PLEASE GRANT US THE CERTIFICATE TILL 20.12.2023

EXT51700018172Dec 2022 → Aug 2024

Reason as filed by the promoterThe Applicant has submitted to the planning Authority all the documents and papers for obtaining occupation certificate. The said planning authority till date has not issued the occupation certificate to the applicant for want of compliances of applicant project.

EXT51700024342Dec 2022 → Mar 2025

Reason as filed by the promoterWE WOULD LIKE TO INFORM YOU THAT WE HAVE ALREADY APPLIED FOR OCCUPATION CERTIFICATE. THE PLANNING AUTHORITY I.E. MIRA BHAYANDAR MUNICIPAL CORPORATION HAS RAISED CERTAIN QUERIES PRIOR TO GRANT OF OCCUPATION CERTIFICATE TO THE AFORESAID PROJECT. HENCE WE REQUIRE EXTENSION UPTO 31.03.2025 TO COMPLY WITH QUERIES OF PLANNING AUTHORITY I.E. MBMC AND OBTAIN OCCUPATION CERTIFICATE FOR AFORESAID PROJECT.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000429096Jayram sharmaSeven Eleven Construction Pvt. Ltd.23/02/2024
CC12500867Sonal Ravindra TambeSeven Eleven Construction Private Limited12/03/2025
CC12500954Sham Himmatsingh KoworSeven Eleven Construction Private Limited18/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Mar 2025

Documents filed147

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 4 (2).pdf14 Feb 2026
Form 3File: Form 5.pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: Form 5.pdf14 Feb 2026
Form 2File: Form 4 (2).pdf14 Feb 2026
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate Apna Ghar Phase-III.pdf10 Mar 2025
Layout approvalFile: PHASE-3_OLD BUILDING HIGHLITED (1) (1).pdf25 Jul 2024
Copy of Layout Approval (in case of layout)File: PHASE-3_OLD BUILDING HIGHLITED (1) (1).pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: A_1.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: A_2.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: A_3.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: A_4.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: B_1.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: B_2.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: B_3.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: C_3.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: C_4.pdf25 Jul 2024
Certificates of CA (Form 3)File: CA CERTIFICATE_1.pdf25 Jul 2024
Certificates of CA (Form 3)File: CA CERTIFICATE_2.pdf25 Jul 2024
Certificates of CA (Form 3)File: CA CERTIFICATE_3.pdf25 Jul 2024
Certificates of CA (Form 3)File: CA CERTIFICATE_4.pdf25 Jul 2024
Certificates of CA (Form 3)File: CA CERTIFICATE_5.pdf25 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23.pdf25 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24.pdf25 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION OF SEPARATE BANK.pdf25 Jul 2024
Declaration in FORM BFile: FORM B.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ARCHITECT-compressed-merged-compressed.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ENGINEER CERTIFICATE.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 22-23.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY ASSURANCE CERTIFICATE 23-24.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD _ BOOKED INVENTORY_III.pdf24 Jul 2024
CERSAI detailsFile: CERSAI REPORT AND UNDERTAKING.pdf24 Jul 2024
Certificates of CA (Form 3)File: FORM_3.pdf24 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANISATION.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24.pdf24 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION OF SEPARATE BANK.pdf24 Jul 2024
Details of encumbrances concerned to FinanceFile: 8 NO ENCRUMBRANCE CONCERNED TOO LEGALL.pdf12 Dec 2022
Details of encumbrances concerned to LegalFile: 8 NO ENCRUMBRANCE CONCERNED TOO LEGALL.pdf12 Dec 2022
Declaration about Commencement CertificateFile: 11 DECLARATION OF CC.pdf12 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE (1).pdf12 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf12 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QAC_31032020.pdf12 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAC_31032021.pdf12 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QAC_31032022.pdf12 Dec 2022
CERSAI detailsFile: Cersai.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: A_1.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: A_2.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: A_3.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: A_4.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: B_1.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: B_2.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: B_3.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: C_3.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: C_4.pdf12 Dec 2022
Certificates of CA (Form 3)File: CA CERTIFICATE (1).pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021-22.pdf12 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK LETTER.pdf12 Dec 2022
Layout approvalFile: LAYOUT.pdf11 May 2022
Layout approvalFile: Parking AND Refugee Calculation.pdf11 May 2022
Building plan approvalFile: A_1_3_11zon.pdf11 May 2022
Building plan approvalFile: A_2_4_11zon.pdf11 May 2022
Building plan approvalFile: A_3_5_11zon.pdf11 May 2022
Building plan approvalFile: A_4 AND B_3_11zon.pdf11 May 2022
Building plan approvalFile: B_1_6_11zon.pdf11 May 2022
Building plan approvalFile: B_2_7_11zon.pdf11 May 2022
Layout approvalFile: C_3_11zon.pdf11 May 2022
Building plan approvalFile: C_4_11zon_11zon.pdf11 May 2022
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf11 May 2022
Copy of Layout Approval (in case of layout)File: Parking AND Refugee Calculation.pdf11 May 2022
Copy of Layout Approval (in case of layout)File: C_3_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: A_1_3_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: A_2_4_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: A_3_5_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: A_4 AND B_3_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: B_1_6_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: B_2_7_11zon.pdf11 May 2022
Building Plan Approval (IOD)File: C_4_11zon_11zon.pdf11 May 2022
Commencement Certificates / NA Order for plotted developmentFile: PHASE III CC.pdf2 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: TEJ CONSULTANTS.pdf18 Jan 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 27 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Apna Ghar Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Ghodbunder, MIra Bhayandar road , MIra ROad East7,600+ in Thane

2 kmApna Ghar Phase IIICompleted 84Lapsed / revoked 65Other 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 223 registered projects within 2 km.

Builder: Seven Eleven Construction Private Limited

Seven Eleven Construction Private Limited has 5 registrations on MahaRERA, including Apna Ghar Phase-II Plot-A and Apna Ghar Phase-II Plot-B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Apna Ghar Phase III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Apna Ghar Phase III is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Apna Ghar Phase III?

The registered promoter entity is Seven Eleven Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Apna Ghar Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Apna Ghar Phase III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Apna Ghar Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Apna Ghar Phase III?

The professionals named in the filing: Architect: Tej; Engineer: Adarsh Consultant; Chartered Accountant: RASHMI AGRAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Apna Ghar Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Apna Ghar Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Apna Ghar Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.