Home / Browse projects / Thane, Maharashtra / Apna Ghar Phase III
Apna Ghar Phase III
By Seven Eleven Construction Private Limited
RG-MH-97861 · RERA P51700016020 · Last updated on MahaRERA portal: 14 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- 3 complaints at MahaRERA
- Completion date moved by 27 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Apna Ghar Phase III is a Others project by Seven Eleven Construction Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700016020 on 12 Apr 2018. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 27 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameApna Ghar Phase III
- TypeOthers
- Location
- Behind Jhankar Company
- Near Vinay Nagar
- Village Ghodbunder
- MIra Bhayandar road
- MIra ROad East
- Mira-Bhayandar (M Corp.)
- Thane
- 401107
- Pincode401107
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700016020
- ReraGenie IDRG-MH-97861
Builder
- NameSeven Eleven Construction Private Limited
- Entity typeCompany
- Managing DirectorSanjay Sakharam Surve
- Other registrations4 more →
- Completed3 of 5
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Apr 2018
- Promised completion31 Mar 2025
- Revised completionRevised to 31 Mar 2025 (originally 30 Dec 2022)
- Buildings13 building records
- Documents filed147 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | NA | 23 | 0 | 0 | 0 | 0 |
| A2 | NA | 23 | 0 | 0 | 0 | 0 |
| A3 | NA | 23 | 0 | 0 | 0 | 0 |
| A4 | NA | 23 | 0 | 0 | 0 | 0 |
| B1 | NA | 23 | 0 | 0 | 0 | 0 |
| B2 | NA | 23 | 0 | 0 | 0 | 0 |
| B3 | NA | 23 | 0 | 0 | 0 | 0 |
| C3 | NA | 23 | 0 | 0 | 0 | 0 |
| C4 | NA | 23 | 0 | 0 | 0 | 0 |
| Shopping Complex | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow 1 | NA | 3 | 0 | 0 | 0 | 0 |
| Bunglow 2 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow 3 | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building13
As on 14 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
72 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
A190%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
A290%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
A390%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
A490%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
B190%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
B290%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
B390%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
C390%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
C490%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Shopping Complex0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Bunglow 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Bunglow 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Bunglow 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 14 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed121
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A1 | 10 | 10 |
| A2 | 10 | 10 |
| A3 | 14 | 14 |
| A4 | 10 | 10 |
| B1 | 14 | 14 |
| B2 | 14 | 14 |
| B3 | 11 | 11 |
| C3 | 17 | 17 |
| C4 | 15 | 15 |
| Bunglow 1 | 2 | 2 |
| Bunglow 2 | 2 | 2 |
| Bunglow 3 | 2 | 2 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tej |
| Engineer | Adarsh Consultant |
| Chartered Accountant | RASHMI AGRAWAL |
| Partner | Role in project |
|---|---|
| Seven Eleven Construction Private Limited | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO NON AVAILABILITY OF CEMENT AND DUE TO DELAY IN SOME PERMISSION, WE WERE NOT ABLE TO COMPLETE THE PROJECT IN TIME, THEREFORE WE WOULD REQUEST YOU TO PLEASE GRANT US THE CERTIFICATE TILL 20.12.2023
Reason as filed by the promoterThe Applicant has submitted to the planning Authority all the documents and papers for obtaining occupation certificate. The said planning authority till date has not issued the occupation certificate to the applicant for want of compliances of applicant project.
Reason as filed by the promoterWE WOULD LIKE TO INFORM YOU THAT WE HAVE ALREADY APPLIED FOR OCCUPATION CERTIFICATE. THE PLANNING AUTHORITY I.E. MIRA BHAYANDAR MUNICIPAL CORPORATION HAS RAISED CERTAIN QUERIES PRIOR TO GRANT OF OCCUPATION CERTIFICATE TO THE AFORESAID PROJECT. HENCE WE REQUIRE EXTENSION UPTO 31.03.2025 TO COMPLY WITH QUERIES OF PLANNING AUTHORITY I.E. MBMC AND OBTAIN OCCUPATION CERTIFICATE FOR AFORESAID PROJECT.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000429096 | Jayram sharma | Seven Eleven Construction Pvt. Ltd. | 23/02/2024 |
| CC12500867 | Sonal Ravindra Tambe | Seven Eleven Construction Private Limited | 12/03/2025 |
| CC12500954 | Sham Himmatsingh Kowor | Seven Eleven Construction Private Limited | 18/03/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Apr 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Mar 2025
Documents filed147
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 4 (2).pdf | 14 Feb 2026 |
| Form 3File: Form 5.pdf | 14 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Form 5.pdf | 14 Feb 2026 |
| Form 2File: Form 4 (2).pdf | 14 Feb 2026 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate Apna Ghar Phase-III.pdf | 10 Mar 2025 |
| Layout approvalFile: PHASE-3_OLD BUILDING HIGHLITED (1) (1).pdf | 25 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: PHASE-3_OLD BUILDING HIGHLITED (1) (1).pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: A_1.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: A_2.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: A_3.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: A_4.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: B_1.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: B_2.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: B_3.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: C_3.pdf | 25 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: C_4.pdf | 25 Jul 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_1.pdf | 25 Jul 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_2.pdf | 25 Jul 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_3.pdf | 25 Jul 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_4.pdf | 25 Jul 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_5.pdf | 25 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23.pdf | 25 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24.pdf | 25 Jul 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION OF SEPARATE BANK.pdf | 25 Jul 2024 |
| Declaration in FORM BFile: FORM B.pdf | 24 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ARCHITECT-compressed-merged-compressed.pdf | 24 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ENGINEER CERTIFICATE.pdf | 24 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 22-23.pdf | 24 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY ASSURANCE CERTIFICATE 23-24.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD _ BOOKED INVENTORY_III.pdf | 24 Jul 2024 |
| CERSAI detailsFile: CERSAI REPORT AND UNDERTAKING.pdf | 24 Jul 2024 |
| Certificates of CA (Form 3)File: FORM_3.pdf | 24 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANISATION.pdf | 24 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23.pdf | 24 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24.pdf | 24 Jul 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION OF SEPARATE BANK.pdf | 24 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: 8 NO ENCRUMBRANCE CONCERNED TOO LEGALL.pdf | 12 Dec 2022 |
| Details of encumbrances concerned to LegalFile: 8 NO ENCRUMBRANCE CONCERNED TOO LEGALL.pdf | 12 Dec 2022 |
| Declaration about Commencement CertificateFile: 11 DECLARATION OF CC.pdf | 12 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE (1).pdf | 12 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 12 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QAC_31032020.pdf | 12 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAC_31032021.pdf | 12 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QAC_31032022.pdf | 12 Dec 2022 |
| CERSAI detailsFile: Cersai.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: A_1.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: A_2.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: A_3.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: A_4.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: B_1.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: B_2.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: B_3.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: C_3.pdf | 12 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: C_4.pdf | 12 Dec 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE (1).pdf | 12 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.pdf | 12 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021-22.pdf | 12 Dec 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK LETTER.pdf | 12 Dec 2022 |
| Layout approvalFile: LAYOUT.pdf | 11 May 2022 |
| Layout approvalFile: Parking AND Refugee Calculation.pdf | 11 May 2022 |
| Building plan approvalFile: A_1_3_11zon.pdf | 11 May 2022 |
| Building plan approvalFile: A_2_4_11zon.pdf | 11 May 2022 |
| Building plan approvalFile: A_3_5_11zon.pdf | 11 May 2022 |
| Building plan approvalFile: A_4 AND B_3_11zon.pdf | 11 May 2022 |
| Building plan approvalFile: B_1_6_11zon.pdf | 11 May 2022 |
| Building plan approvalFile: B_2_7_11zon.pdf | 11 May 2022 |
| Layout approvalFile: C_3_11zon.pdf | 11 May 2022 |
| Building plan approvalFile: C_4_11zon_11zon.pdf | 11 May 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 11 May 2022 |
| Copy of Layout Approval (in case of layout)File: Parking AND Refugee Calculation.pdf | 11 May 2022 |
| Copy of Layout Approval (in case of layout)File: C_3_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: A_1_3_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: A_2_4_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: A_3_5_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: A_4 AND B_3_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: B_1_6_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: B_2_7_11zon.pdf | 11 May 2022 |
| Building Plan Approval (IOD)File: C_4_11zon_11zon.pdf | 11 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: PHASE III CC.pdf | 2 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: TEJ CONSULTANTS.pdf | 18 Jan 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 147 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Apna Ghar Phase III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Village Ghodbunder, MIra Bhayandar road , MIra ROad East7,600+ in Thane
Filed coordinates, straight-line distance. 223 registered projects within 2 km.
Codename StarLife
JP Infra Realty Private Limited
Prestige Garden Trails
PRESTIGE ESTATES PROJECTS LIMITED
TIARA HILLS PHASE I BLDG NO 3, 5 AND 2
PNK SPACE DEVELOPMENT PVT LTD
The Palace Tower B
JP Infra Realty Private Limited
Sector 2A - Wings JKL
Eversmile Properties Private Limited
CRESCENT WTC - WESTERN TRADE CENTER - PHASE -
CRESCENT SHELTERS
See every Thane project, with the district possession charts
Builder: Seven Eleven Construction Private Limited
Seven Eleven Construction Private Limited has 5 registrations on MahaRERA, including Apna Ghar Phase-II Plot-A and Apna Ghar Phase-II Plot-B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Apna Ghar Phase III shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Apna Ghar Phase III is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Apna Ghar Phase III?
The registered promoter entity is Seven Eleven Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Apna Ghar Phase III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Apna Ghar Phase III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Apna Ghar Phase III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Apna Ghar Phase III?
The professionals named in the filing: Architect: Tej; Engineer: Adarsh Consultant; Chartered Accountant: RASHMI AGRAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Apna Ghar Phase III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.