ANUGRAHA

By AVADHOOT CONSTRUCTIONS

RG-MH-22456 · RERA P52100031495 · Last updated on MahaRERA portal: 19 Dec 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 11 months past the filed date
  • Completion date moved by 25 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2025Possession promised11 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 60%
0Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

ANUGRAHA is a Others project by AVADHOOT CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100031495 on 25 Oct 2021. Possession was promised by 21 Nov 2025 and is now 11 months past that date. The completion date has moved by 25 months from the original filing.

At a glance

Project

  • NameANUGRAHA
  • TypeOthers
  • Location
    • BHOPATKAR ROAD
    • SADASHIV PETH
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411030
  • Pincode411030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100031495
  • ReraGenie IDRG-MH-22456

Builder

  • NameAVADHOOT CONSTRUCTIONS
  • Entity typePartnership
  • PartnersSHAILESH SHRIKANT TILAK, VRUSHALI SACHIN DESHPANDE
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

11 months past promisethis monthRegisteredOct 2021First promiseOct 2023Revised toNov 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Oct 2021
  • Promised completion21 Nov 2025
  • Revised completionRevised to 21 Nov 2025 (originally 31 Oct 2023)
  • Buildings1 building record
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANUGRAHANA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

ANUGRAHA: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 19 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Multipurpose CourtNoNot applicable
Compound wallNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area401 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI901.93
Proposed, not sanctioned902 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDECCAN GYMKHANA

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShailesh Salehittal
EngineerPARAG S. SURA
Chartered AccountantMahesh Ankush Ghare
PartnerRole in project
AVADHOOT CONSTRUCTIONS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017885Oct 2023 → Oct 2024

Reason as filed by the promoterSince we received revised plan late we could not complete the project in given time. So request to grant us the extension.

EXT52100027392Oct 2023 → Nov 2025

Reason as filed by the promoterWe already had completed our project in full. We had also got Occupancy Certificate for our project and we also had submitted it to RERA. However RERA is yet to scrutinize it. We require some time to complete Handover Process , society formation and conveyance process

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: 03 1257 Sadashiv peth Declaration B new.pdf19 Dec 2023
Disclosure of sold/ booked inventoryFile: 05_Avadhoot_Sold_Unsold_information.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Anugraha_Form_05_2022_2023__compressed.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 02_Anugraha_Engineers Certificate_Form 2A_July to Sept_.pdf7 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Anugraha_Engineers Certificate_Form 2A_ March 22.pdf7 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 06_Anugraha_Eng Cert_2A March_2023.pdf7 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 ANUGRAH FY 21-22.pdf21 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anugraha Form 02 Engineers Certificate Dec 21.pdf12 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineers' Certificate_Anugraha_2A_Oct to Dec_2021.pdf12 Mar 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold or booked inventory.pdf12 Mar 2022
Copy of the legal title reportFile: 1257_Legal Tital Report Form A_1.pdf23 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 AC Anugraha 30092021.pdf4 Oct 2021
Layout approvalFile: 06_Anughraha_IOD Certificate.PDF1 Oct 2021
Building plan approvalFile: Plan 1.PDF1 Oct 2021
Building plan approvalFile: Plan 2.PDF1 Oct 2021
Building plan approvalFile: plan 3.PDF1 Oct 2021
PAN CardFile: 00_Pan Card_Avadhoot Construction.pdf1 Oct 2021
Details of encumbrancesFile: 10_Anughraha_Encombrances Self Declaration format.pdf1 Oct 2021
Copy of Layout Approval (in case of layout)File: 06_Anughraha_IOD Certificate.PDF1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan 1.PDF1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.PDF1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: plan 3.PDF1 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: 11_Anughraha_Commencement Certificate.pdf1 Oct 2021
Declaration about Commencement CertificateFile: Anugraha_Format D.pdf1 Oct 2021
Declaration in FORM BFile: 13_Anughraha_Declaration B.pdf1 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15_Anughraha_Architects Certificate_Form_01.pdf1 Oct 2021
Proforma of Allotment letterFile: 07_Anughraha_ ALLOTMENT LETTER.pdf1 Oct 2021
Proforma of Allotment letterFile: _Anugraha_Flat_ Agreement.pdf1 Oct 2021
OtherFile: 01_1257_Abhijit Limiaye_Sale Deed_01_12.pdf1 Oct 2021
OtherFile: 02_1257_Abhijit Limiaye_Sale Deed_13_21.pdf1 Oct 2021
OtherFile: 03_1257_Abhijit Limiaye_Sale Deed_22_29.PDf1 Oct 2021
OtherFile: 01_POA Limaye_01_11.pdf1 Oct 2021
OtherFile: 02_POA Limaye_12_22.pdf1 Oct 2021
OtherFile: Shirish Limaye_01_10.pdf1 Oct 2021
OtherFile: Shirish Limaye_11_21.pdf1 Oct 2021
OtherFile: Shirish Limaye_22_36.pdf1 Oct 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KAPIL SANKALPCTS 1228 SADASHIV PETH NEAR PERUGATE POLICE STATION PUNE47CompletedMar 2019Late, Sep 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 25 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANUGRAHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SADASHIV PETH13,700+ in Pune

2 kmANUGRAHACompleted 184Lapsed / revoked 131Other 170Dot size: filed unitsN

Filed coordinates, straight-line distance. 485 registered projects within 2 km.

Builder: AVADHOOT CONSTRUCTIONS

AVADHOOT CONSTRUCTIONS has 3 registrations on MahaRERA, including KAPIL SANKALP and ANITAKUNJ HSG SOC LTD. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that ANUGRAHA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANUGRAHA is delayed beyond 21 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANUGRAHA?

The registered promoter entity is AVADHOOT CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANUGRAHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANUGRAHA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANUGRAHA?

The professionals named in the filing: Architect: Shailesh Salehittal; Engineer: PARAG S. SURA; Chartered Accountant: Mahesh Ankush Ghare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANUGRAHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANUGRAHA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANUGRAHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.