Home / Browse projects / Thane, Maharashtra / Anthony Annex
Anthony Annex
RG-MH-22860 · RERA P51700024182 · Last updated on MahaRERA portal: 27 Feb 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 26 months past the filed date
- Completion date moved by 20 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Anthony Annex is a Residential / Group Housing project by Magnum Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700024182 on 24 Jan 2020. Possession was promised by 21 Aug 2024 and is now 26 months past that date. The completion date has moved by 20 months from the original filing.
At a glance
Project
- NameAnthony Annex
- TypeResidential / Group Housing
- Location
- Kolbad Road
- Khopat
- Thane (M Corp.)
- Thane
- 400602
- Pincode400602
- RERA no.P51700024182
- ReraGenie IDRG-MH-22860
Builder
- NameMagnum Enterprises
- Entity typePartnership
- PartnersRavish karim Makani, Anwar Shamsuddin Kasam, Rajendra Suresh Bhagat, Mukesh Prabhudayal Mangla, Santosh Ramavtar Agrawal, Suresh Shankar Bhagat, Yash Vivek Bhagat, Vinod Parshuram Bhagat
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Jan 2020
- Promised completion21 Aug 2024
- Revised completionRevised to 21 Aug 2024 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed125 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Anthony Annex | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 25%.
Anthony Annex: 39% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Vivienne D'souza | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shraddha Paranjpe |
| Engineer | Ajay Mahale |
| Chartered Accountant | Kewal Sanghvi |
| Partner | Role in project |
|---|---|
| Magnum Enterprises | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. 3. Customers are also facing financial problems There are huge receivable from the customers but we are unable to receive the same, which in turn has affected our financial position as well. Customers and we both are highly affected in last 1 and half year. 4. Since last 3 years market slow-do
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed125
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architec Certificate - Anthony Anex - Sept 23.pdf | 27 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 Form 1 Architect Certificate -Anthony Anex Dec 23.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 Eng Certificate for Anthony Annexe Dec 23.pdf | 27 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate - Anthony Anex - Sept 23.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Anthny Anex - Spet23.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3 CA Certificate - Anthony Annex Dec 23.pdf | 27 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES CONCERNED TO FINANCE.pdf | 3 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf | 3 Sep 2023 |
| Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES CONCERNED TO FINANCE.pdf | 3 Sep 2023 |
| Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf | 3 Sep 2023 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE_compressed.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 21 Form 1 - Architect Cert - Mar 20.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 22 Form 1 - Architect Cert- Dec 20.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 23 Form 1 - Architect Cert - Mar 21.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 24 form 1 - Architect Cert - Jun 21.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 25 Form 1 - Archtect Cert - Sept 21.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 26 Form 1 - Architect Cert - Dec 21.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 27 Form 1 - Architect Cert - Mar 22 .pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 28 Form 1 - Architect Cert - June 22.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 29 Form 1 - Architect Cert - Sept 22.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 form 1 - Architect Cert - Dec 22.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 form 1 - Architect Cert - Mar 23.pdf | 3 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 form 1 - Architect Cert - June 23.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2 - RERA- Mar 20.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 - RERA-Jun 20.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 FORM 2 - RERA-Sept20.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 FORM 2 - RERA-Dec 20.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2 - RERA-Mar 21.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2 - RERA-Jun 21.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 FORM 2 - RERA-Sept 21.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 FORM 2 - RERA-Dec 21.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 FORM 2 - RERA-Mar 22.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 FORM 2 - RERA-Jun 22.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 FORM 2 - RERA-Sept 22.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 FORM 2 - RERA-Dec 22.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 FORM 2 - RERA-Mar 23.pdf | 3 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 FORM 2 - RERA-Jun 23.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSURANCE CERTIFICATE 31-03-2020_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE 30-06-2020_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: DISCLOSURE OF SOLD -30-09-2020.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE 31-12-2020_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: DISCLOSURE OF SOLD -31-03-2021.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE CERTIFICATE 30-06-2021_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE CERTIFICATE 30-09-2021_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: DISCLOSURE OF SOLD -31-12-2021.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE CERTIFICATE 31-03-2022_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 30-06-2022_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 30-09-2022_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 31-12-2022_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 31-03-2023_compressed.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: DISCLOSURE OF SOLD -31-03-2023.pdf | 3 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE 30-06-2023_compressed.pdf | 3 Sep 2023 |
| CERSAI detailsFile: UNDERTAKING WITH RESPECT TO CERSAI REPORT.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-03-2020.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-06-2020.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-09-2020.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-12-2020.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-03-2021.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-06-2021.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-09-2021.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-12-2021.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-03-2022.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-06-2022.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-09-2022.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-12-2022.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -31-03-2023.pdf | 3 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -30-06-2023.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 01-CA Form 3-MAR-2020_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 02-CA Form 3-JUN-2020_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03-CA Form 3-SEP-2020_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 04-CA Form3 -DEC-2020_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 05-CA Form 3-MAR-2021_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 06-CA Form 3-JUN-2021_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 07-CA Form 3-SEP-2021_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 08-CA Form 3-DEC-2021_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 09-CA Form 3-MAR-2022_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10-CA Form 3-JUNE-2022_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11-CA form 3-SEP-2022_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12-CA Form 3-DEC-2022_compressed.pdf | 3 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13-CA Form 3-MAR-2023_compressed.pdf | 3 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 125 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Anthony Annex on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khopat7,600+ in Thane
Stellar
Trimity Realty LLP
SAMRIN HERITAGE
SAMRIN INFRA PRIVATE LIMITED
L&T Realty Vayam Tower 3
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
L&T Realty Vayam Tower 4
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
Codename LIT Tower A
Camrose Realtors Private Limited
Codename LIT Tower B
Camrose Realtors Private Limited
See every Thane project, with the district possession charts
Builder: Magnum Enterprises
Magnum Enterprises has 1 registration on MahaRERA, including Anthony Annex. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Anthony Annex shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Anthony Annex is delayed beyond 21 Aug 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Anthony Annex?
The registered promoter entity is Magnum Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Anthony Annex?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Anthony Annex?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Anthony Annex?
The professionals named in the filing: Architect: Shraddha Paranjpe; Engineer: Ajay Mahale; Chartered Accountant: Kewal Sanghvi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Anthony Annex?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback