Anmol Nayantara Gold
By Bafna Builders and Land Developers
RG-MH-01000 · RERA P51600002894 · Last updated on MahaRERA portal: 15 Jun 2022
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Anmol Nayantara Gold is a Residential / Group Housing project by Bafna Builders and Land Developers in Nashik, Maharashtra, registered with MahaRERA as P51600002894 on 4 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameAnmol Nayantara Gold
- TypeResidential / Group Housing
- Location
- Nashik
- 422009
- Pincode422009
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600002894
- ReraGenie IDRG-MH-01000
Builder
- NameBafna Builders and Land Developers
- Entity typePartnership
- PartnersTaradevi Ratanlal Bafna, Siddharth Ratanlal Bafna, Sushil Kasturchand Bafna
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on4 Aug 2017
- Promised completion31 Dec 2019
- Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
- Buildings15 building records
- Documents filed59 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A - Aquamarine | NA | 12 | 0 | 0 | 0 | 0 |
| B- Amethyst | NA | 12 | 0 | 0 | 0 | 0 |
| C-Crystal | NA | 12 | 0 | 0 | 0 | 0 |
| D-Coral | NA | 12 | 0 | 0 | 0 | 0 |
| E- Diamond | NA | 13 | 0 | 0 | 0 | 0 |
| F-Embrald | NA | 13 | 0 | 0 | 0 | 0 |
| G - Moonstone | NA | 13 | 0 | 0 | 0 | 0 |
| H-Peral | NA | 13 | 0 | 0 | 0 | 0 |
| I - Ruby | NA | 12 | 0 | 0 | 0 | 0 |
| J-Sapphire | NA | 12 | 0 | 0 | 0 | 0 |
| L- Quartz | NA | 12 | 0 | 0 | 0 | 0 |
| N- Jasper | NA | 12 | 0 | 0 | 0 | 0 |
| O -Amber | NA | 12 | 0 | 0 | 0 | 0 |
| M -Lapis | NA | 12 | 0 | 0 | 0 | 0 |
| K - Topaz | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 15 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
88 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.
A - Aquamarine72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B- Amethyst72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
C-Crystal72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
D-Coral72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
E- Diamond81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
F-Embrald81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
G - Moonstone81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
H-Peral81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
I - Ruby72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
J-Sapphire72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
L- Quartz72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
N- Jasper72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
O -Amber71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
M -Lapis71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
K - Topaz71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 15 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed617
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A - Aquamarine | 10 | 20 | 30 |
| B- Amethyst | 13 | 20 | 33 |
| C-Crystal | 14 | 20 | 34 |
| D-Coral | 11 | 20 | 31 |
| E- Diamond | 43 | 27 | 70 |
| F-Embrald | 35 | 26 | 61 |
| G - Moonstone | 35 | 27 | 62 |
| H-Peral | 42 | 27 | 69 |
| I - Ruby | 10 | 20 | 30 |
| J-Sapphire | 13 | 20 | 33 |
| L- Quartz | 9 | 20 | 29 |
| N- Jasper | 12 | 20 | 32 |
| O -Amber | 12 | 20 | 32 |
| M -Lapis | 17 | 20 | 37 |
| K - Topaz | 14 | 20 | 34 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Nakshtra Infrastructures Pvt Ltd | Aurangabad (CB) | Aurangabad |
| Santosh Muthian | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Homework |
| Partner | Role in project |
|---|---|
| Bafna Builders and Land Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter• The Project Anmol Nayantara Gold comprising 15 buildings, Clubhouse and Multi-purpose Hall along with basic infrastructure is virtually completed. • Total Handover are 384 / 620 as of December 2018. • Total owners Occupying Residing 277 as of December 2018 • Nashik Municipal Corporation has granted appropriate water supply Connection based on occupied number of premises. • MSEDCL has also provided residential meter to common areas and individual. • All other basic infrastructure is in place and being augmented on the basis of physical occupation of the customer. • The apartment declaration d
Litigation declared4
| Case | Court | Status |
|---|---|---|
| SPCS 101/2009 | Nashik Civil Senior court | pending |
| CMA 189/2010 | Nashik Civil Senior court | pending |
| SPCS 488/2010 | Nashik Civil Senior court | pending |
| SPCS 39/2016 | Nashik Civil Senior court | pending |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12503257 | Tejaswini Anant Athani | Bafna Builders and Land Developers | 13/09/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Jun 2022
Documents filed59
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Gold Completion.pdf | 15 Jun 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Gold.pdf | 6 Aug 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form-4-Gold.pdf | 30 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5 Gold.pdf | 26 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold AC part 1_compressed.pdf | 6 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold AC part 2_compressed.pdf | 6 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold EC part1_compressed.pdf | 6 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold EC part2.pdf | 6 Nov 2019 |
| Certificates of CA (Form 3)File: gold CA certificate part 1_compressed.pdf | 6 Nov 2019 |
| Certificates of CA (Form 3)File: gold CA certificate part2_compressed.pdf | 6 Nov 2019 |
| Certificates of CA (Form 3)File: gold CA certificate part 3.pdf | 6 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold architect_17.pdf | 24 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold architect.pdf | 24 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold architect (1).pdf | 24 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold architect (2).pdf | 24 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: gold architect (3).pdf | 24 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold eng.pdf | 24 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold eng (1).pdf | 24 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold eng (2).pdf | 24 Dec 2018 |
| Certificates of CA (Form 3)File: ca gold (1).pdf | 24 Dec 2018 |
| Certificates of CA (Form 3)File: ca gold (2).pdf | 24 Dec 2018 |
| Certificates of CA (Form 3)File: ca gold (3).pdf | 24 Dec 2018 |
| Certificates of CA (Form 3)File: ca gold_13.pdf | 24 Dec 2018 |
| Certificates of CA (Form 5)File: gold form 5_1.pdf | 30 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 3 part 1 gold_20180302153926.pdf | 2 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Gold Part 1.pdf | 2 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Gold Part 2.pdf | 2 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Gold Part 3.pdf | 2 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Gold Part 4.pdf | 2 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Gold Part 5.pdf | 2 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Gold Part 6.pdf | 2 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold eng certificate_20180302154025.pdf | 2 Mar 2018 |
| Certificates of CA (Form 3)File: form 3 part 2 gold_20180302153912.pdf | 2 Mar 2018 |
| Certificates of CA (Form 3)File: form 3 part 3 gold_20180302153859.pdf | 2 Mar 2018 |
| Certificates of CA (Form 5)File: form 5 gold_20180302153945.pdf | 2 Mar 2018 |
| Building plan approvalFile: New Doc 2017-07-24.pdf | 24 Jul 2017 |
| Layout approvalFile: scan329.pdf | 24 Jul 2017 |
| Layout approvalFile: New Doc 2017-07-24.pdf | 24 Jul 2017 |
| Details of encumbrancesFile: New Doc 2017-07-24 (1).pdf | 24 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: scan329.pdf | 24 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: New Doc 2017-07-24.pdf | 24 Jul 2017 |
| Building Plan Approval (IOD)File: New Doc 2017-07-24.pdf | 24 Jul 2017 |
| Declaration in FORM BFile: bbld form b.pdf | 24 Jul 2017 |
| Proforma of Allotment letterFile: GOLD - RERA - MASTER AGREEMENT -.pdf | 24 Jul 2017 |
| Building plan approvalFile: scan299.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: New Doc 2017-07-22 (1).pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: scan299.pdf | 22 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: New Doc 2017-07-22(1)(1).pdf | 22 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: archi Gold p1_20170722171731.pdf | 22 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: archi Gold p1_20170722171731.pdf | 22 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: archi Gold p3_20170722172403.pdf | 22 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold engineers part 1_20170722120802.pdf | 22 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gold engineers part 2_20170722121033.pdf | 22 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: gold engineers part 3_20170722121303.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: CA certificate Gold p1_20170722165301.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: CA certificate Gold p2_20170722165624.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: CA certificate gold p3_20170722165850.pdf | 22 Jul 2017 |
| Certificates of CA (Form 5)File: Form5(2).pdf | 22 Jul 2017 |
| PAN CardFile: bbld pan card.pdf | 20 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 59 filed documents as one ZIP, foldered, with a manifest
Keep Anmol Nayantara Gold on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nashik4,100+ in Nashik
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
STAR WORLD
DEEPAK KALYANJI CHANDE
VRAJ CENTRAL VISTA
DHAIRYA DEVELOPERS
ROONGTA TECHONE APARTMENT
SHREE TIRUMALA BUILDCON
VRAJ CAPITAL
KAPILAVASTU CREATORS
MAA BHAGWATI RESIDENCY APARTMENT
ROONGTA LANDMARKS LLP
THREE LEAVES PHASE ONE
DEEPAK INFRA AND HOMES PRIVATE LIMITED
See every Nashik project, with the district possession charts
Builder: Bafna Builders and Land Developers
Bafna Builders and Land Developers has 2 registrations on MahaRERA, including Anmol Nayantara Empire and Anmol Nayantara Gold. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Anmol Nayantara Gold is delayed beyond 31 Dec 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Anmol Nayantara Gold?
The registered promoter entity is Bafna Builders and Land Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Anmol Nayantara Gold?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Anmol Nayantara Gold?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Anmol Nayantara Gold?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Anmol Nayantara Gold?
The professionals named in the filing: Architect: Homework. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Anmol Nayantara Gold?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback