Red flags

  • Completion date moved by 5 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
14 of 18Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 75%
96 of 280Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 135 documents Report an error

Anjani Pride is a Residential / Group Housing project by Geeta Developers in Thane, Maharashtra, registered with MahaRERA as P51700024335 on 5 Feb 2020. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 5 months from the original filing. 184 of the 280 units on this registration are recorded sold or booked, and 14 of 18 construction stages are filed complete.

At a glance

Project

  • NameAnjani Pride
  • TypeResidential / Group Housing
  • Location
    • Kanungo Estate
    • Mira Road (East)
    • BHAYANDAR
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700024335
  • ReraGenie IDRG-MH-21720

Builder

  • NameGeeta Developers
  • Entity typePartnership
  • GSTIN27AACFG3654J1ZB
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersNANDLAL Gulabchand Bhutra, Madanlal Gulabchand Bhutra, Rameshchandra Gulabchand Bhutra, Ramautar Gulabchand Bhutra, Maheshchandra Gulabchand Bhutra
  • Other registrations6 more →
  • Completed6 of 7
  • Declared earlier projects7 →

Key dates

this monthRegisteredFeb 2020First promiseJul 2025Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Feb 2020
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 1 Jul 2025)
  • Buildings2 building records
  • Documents filed135 files

Current status

66%184 of 280 units booked
90.6%Work done, per cost certificate

Figures as on 24 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Anjani PrideA25251400140
Anjani PrideB25251400140

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 75%.

Anjani Pride · wing A86%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
Anjani Pride · wing B86%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 24 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed206

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots206
Closed/Covered206

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,776 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2025

Approvals and building plan

Sanctioning authorityMira Bhayandar Municipal Corporation
Permissible FSI18200.0
Proposed, not sanctioned17,753 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhayandar West
Estimated costRs 55.20 cr
Cost incurredRs 50.00 cr
Work done90.58%
BuildingWingEstimatedIncurred
Anjani PrideARs 55.20 crRs 50.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANISH & ASSOCIATES
ArchitectHemant Talaty talaty
EngineerRajesh Dubey
Chartered AccountantPurshottam Bajaj
Chartered AccountantShivratan Agarwal
PartnerRole in project
Geeta Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA05062501447Jul 2025 → Dec 2025

Reason as filed by the promoter1. We have completed 95% work of the Project. 2. We are in the process of completing the remaining project work and procuring the Occupancy Certificate & Form 4 - Architect’s Certificate on Completion of Project. 3. We have also taken consent for extension from more than 51% of allottees. 4. The remaining project work & process of procuring the Occupancy Certificate will be completed by 31/12/2025.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed135

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 135 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: OC Certificate.pdf24 Aug 2025
Withdrawal Update Form 1File: FORM -1.pdf14 Jun 2025
Withdrawal Update Form 2File: FORM 2.pdf14 Jun 2025
Withdrawal Update Form 3File: Form 3.pdf14 Jun 2025
Form 1File: FORM -1.pdf9 Jun 2025
Form 2File: FORM 2.pdf9 Jun 2025
Form 3File: FORM 3.pdf9 Jun 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD.pdf9 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaratlon for Ouarterly Progress.pdf9 Jun 2025
Form 1File: FORM 1.pdf9 Jun 2025
Form 2File: Form 2.pdf9 Jun 2025
Form 3File: Form 3.pdf9 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory.pdf9 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaratlon for Ouarterly Progress.pdf9 Jun 2025
Form 1File: Form 1.pdf9 Jun 2025
Form 2File: Form 2.pdf9 Jun 2025
Form 3File: Form 3.pdf9 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory Pride.pdf9 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaratlon for Ouarterly Progress.pdf9 Jun 2025
Form 1File: Form 1 Annexure A.pdf9 Jun 2025
Form 2File: Form 2.pdf9 Jun 2025
Form 3File: Form 3 Pride.pdf9 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory -.pdf9 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaratlon for Ouarterly Progress.pdf9 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 .pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory Pride_compressed.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pride.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anjani Pride.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Annexure A.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Inventory - 1.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anjani Pride.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD Inventory of Anjani Pride.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 anjani pride_compressed.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold -Inventoery Anandam.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Discloure of Inventory Anjani pride.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 pride.pdf30 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form -2A Engineer 's Certificate for Quality Assurance.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclouser of sold or Booked Inventory.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf20 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Form 3.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold - Booked Inventory Anjani Pride_001.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jan 2023
Disclosure of sold/ booked inventoryFile: Diclosure Of Sold Booked Inventory - Anjani Pride_001.pdf18 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Anjani Pride.pdf26 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf26 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory.pdf20 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Oct 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
Anandam-BP51700017941Bhayandar West, ThaneSep 2018CompletedJun 2024Late, Sep 2024
Anjani EnclaveP51700014453Mira Road East, ThaneDec 2017CompletedMar 2022Mar 2022
Anjani RegencyP51700004541Mira Road (East), ThaneAug 2017CompletedDec 2020Dec 2018

How this compares with Thane

66%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 5 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Anjani Pride on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira Road (East)7,600+ in Thane

2 kmAnjani PrideCompleted 95Lapsed / revoked 76Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 276 registered projects within 2 km.

Builder: Geeta Developers

GEETA DEVELOPERS has 7 registrations on MahaRERA, including GEETA HEIGHTS and Anjani Regency. Its filings disclose 7 earlier MahaRERA projects: declares 5 of 7 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Anjani Pride is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anjani Pride?

The registered promoter entity is Geeta Developers, a partnership as per the filing. Its GSTIN 27AACFG3654J1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anjani Pride?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Anjani Pride?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Anjani Pride?

The professionals named in the filing: Architect: ANISH & ASSOCIATES; Architect: Hemant Talaty talaty; Engineer: Rajesh Dubey; Chartered Accountant: Purshottam Bajaj; Chartered Accountant: Shivratan Agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anjani Pride?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anjani Pride. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anjani Pride to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.