Home / Browse projects / Pune, Maharashtra / ANANTSRISHTI PHASE I
ANANTSRISHTI PHASE I
RG-MH-12579 · RERA P52100006401 · Last updated on MahaRERA portal: 8 Apr 2023
Source: official MahaRERA filing
Red flags
- 10 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANANTSRISHTI PHASE I is a Mixed project by LANDSCAPE REALITY in Pune, Maharashtra, registered with MahaRERA as P52100006401 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2020. The completion date has moved by 18 months from the original filing. 122 of the 123 units on this registration are recorded sold or booked, and 88 of 88 construction stages are filed complete. 10 complaints are on record with the regulator.
At a glance
Project
- NameANANTSRISHTI PHASE I
- TypeMixed
- Location
- TAKVE ROAD
- JAMBHUL
- Mawal
- Pune
- 412106
- Pincode412106
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100006401
- ReraGenie IDRG-MH-12579
Builder
- NameLANDSCAPE REALITY
- Entity typeCompany
- DirectorPALLAVI AMIT VAIDYA
- Other registrations2 more →
- Completed1 of 3
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on14 Aug 2017
- Promised completion30 Sep 2020
- Revised completionRevised to 30 Sep 2020 (originally 31 Mar 2019)
- Buildings8 building records
- Documents filed37 files
Current status
Figures as on 8 Apr 2023, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| H WING | NA | 7 | 0 | 0 | 0 | 0 |
| I WING | NA | 7 | 0 | 0 | 0 | 0 |
| J WING | NA | 7 | 0 | 0 | 0 | 0 |
| Q WING | NA | 7 | 0 | 0 | 0 | 0 |
| K WING | NA | 9 | 0 | 0 | 0 | 0 |
| P WING | NA | 9 | 0 | 0 | 0 | 0 |
| C TYPE ROW HOUSE | NA | 1 | 0 | 0 | 0 | 0 |
| D TYPE ROW HOUSE | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 8 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
88 of 88 construction stages are filed complete across 9 buildings.
H WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
J WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Q WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
K WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
P WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C TYPE ROW HOUSE100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D TYPE ROW HOUSE100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA Plot Without StructureNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 8 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 88% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 88% |
| Storm Water Drains | Yes | 88% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 75% |
| Solid Waste Management And Disposal | Yes | 75% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | No | Not applicable |
Parking filed240
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| H WING | 22 | 25 | 47 |
| I WING | 24 | 39 | 63 |
| J WING | 23 | 5 | 28 |
| Q WING | 23 | 4 | 27 |
| K WING | 23 | 7 | 30 |
| P WING | 23 | 6 | 29 |
| C TYPE ROW HOUSE | 8 | 0 | 8 |
| D TYPE ROW HOUSE | 8 | 0 | 8 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Milind Pokharkar & Associates |
| Engineer | SUNIL MUTALIK |
| Partner | Role in project |
|---|---|
| LANDSCAPE REALITY | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir / Madam, We, landscape Realty are developing residential and commercial project, Anantsrishti at village Jambhul, Gat no. 404 and 387, Taluka Maval, District Pune, PMRDA, Pune 412106 and we were due to complete the project on 31st March 2019. We hereby submit that since last 4-5 months we were not getting adequate labour on our site mentioned above. Due to shortage of required labour we were not able to attain expected construction within time as a result of which our project was delayed. We hereby state that we are now overcoming the difficulty and have resumed construction activity
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 515/2017 | Honarable civil judge senior division wadgaon maval | Injuction application rejected |
| CC005000000022472/2019 | The Maharashtra Real Estate Regulatory Authority Office at Bandra East | Posted for reply of Respondent |
| CC005000000022150/2019 | The Maharashtra Real Estate Regulatory Authority Office at Bandra East | Posted for reply of Respondent |
Complaints filed with MahaRERA10
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000022150 | RAMESHWAR RADHESHYAM MANIYAR | Landscape Realty | 11/12/2018 |
| CC005000000022472 | Ramchandra Dhondiba Gawade | Landscape Realty | 20/01/2019 |
| CC005000000064835 | Vidyadhar Jayant Joshi | Landscap Realty | 15/11/2020 |
| CC005000000064836 | RAHUL KAMALAKANT VAIDYA | Landscap Realty | 15/11/2020 |
| CC005000000064837 | RAHUL KAMALAKANT VAIDYA | Landscap Realty | 15/11/2020 |
| CC005000000064839 | ANAND V CHANDEKAR | Landscap Realty | 16/11/2020 |
| CC005000000095785 | Mr. Shantaram Sudhakar Arvindekar | Landscape Realty | 17/07/2021 |
| CC005000000023124 | Shashikant Shridhar Gawade | Landscape Realty | 11/06/2019 |
| CC005000000033475 | DWARKADHISH DESHPANDE AND APARNA DESHPANDE | LANDSCAPE REALTY THROUGH AMOL DILIP TAVILDAR | 29/09/2019 |
| CC005000000043797 | MAYURESH SHASHIKANT BHAVE | LANDSCAPE REALTY | 20/12/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Dec 2020
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: ilovepdf_merged (1).pdf | 8 Apr 2023 |
| Other - TechnicalFile: Quality assurance certificate.pdf | 8 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Row House D - March 2023.pdf | 31 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society - Certificate - Plot and Row House -July 19.pdf | 3 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society - Certificate - Plot and Row House -July 19.pdf | 3 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Anantsrishti-H,I,J,Q- Society Certificate - Aug 2020 (1).pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure_merged (1).pdf | 10 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: ilovepdf_merged (1).pdf | 21 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01_Form I _ Phase I (1)_compressed.pdf | 16 Jul 2022 |
| OtherFile: Anantsrishti-rera-complaync-may 2021-ajinkya-compressed.pdf | 3 Jun 2021 |
| Certificates of CA (Form 5)File: FORM 5 AS.pdf | 23 Dec 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: P and K OC.pdf | 3 Dec 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: 201008 - RERA Certificate - Form 4(Signed).pdf | 23 Nov 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC H and I.pdf | 5 Oct 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC J and Q.pdf | 5 Oct 2020 |
| Certificates of CA (Form 5)File: AS-Form 5 2019.pdf | 14 Oct 2019 |
| Certificates of CA (Form 5)File: LR_Form 5.pdf | 20 Feb 2019 |
| Certificates of CA (Form 5)File: FORM 5 AS.pdf | 23 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch CertIFICATE PH-i.pdf | 29 Mar 2018 |
| Layout approvalFile: compressed_Approved Layout.pdf | 23 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: compressed_Approved Layout.pdf | 23 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: compressed_180322-CC.pdf | 23 Mar 2018 |
| Building plan approval or NA orderFile: IOD PLAN.pdf | 29 Jul 2017 |
| Layout approvalFile: SANCTION PLAN LAYOUT.pdf | 29 Jul 2017 |
| PAN CardFile: LANDSCAPE PAN CARD.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: Anantsrishti Title Certificate.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: details of encumbrances-1.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: SANCTION PLAN LAYOUT.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: IOD PLAN.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Anantsrishti Commencment certificate.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: B Form.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE PART 1.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE PART 2.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Anantsrishti Engineer's Certificate.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE ANANTSRISHTI.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: LR Allotement Letter.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Anantsrishti draft.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 37 filed documents as one ZIP, foldered, with a manifest
Keep ANANTSRISHTI PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JAMBHUL13,700+ in Pune
Filed coordinates, straight-line distance. 30 registered projects within 2 km.
Residential Building on CTS No 107/1P -GIRIVAR
SHRIVAR BUILDERS LLP
Aranya
Naiknavare Township LLP.
Land of Dreams
Krisala Buildscape LLP
Mount Vista
Tirupati Lands and Building Constructions
Osian LifeLands 2
Planet-i Realty
RKL INDRAYANI CITY
R K LUNKAD HOUSING COMPANY
Builder: LANDSCAPE REALITY
LANDSCAPE REALITY has 3 registrations on MahaRERA, including ANANTSRISHTI PHASE I and ANANTSRISHTI PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ANANTSRISHTI PHASE I is delayed beyond 30 Sep 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANANTSRISHTI PHASE I?
The registered promoter entity is LANDSCAPE REALITY, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANANTSRISHTI PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ANANTSRISHTI PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ANANTSRISHTI PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANANTSRISHTI PHASE I?
The professionals named in the filing: Architect: Milind Pokharkar & Associates; Engineer: SUNIL MUTALIK. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANANTSRISHTI PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.