Home / Browse projects / Thane, Maharashtra / ANANTA PRIDE PHASE I

Registration lapsed No litigation declared Residential / Group Housing project

ANANTA PRIDE PHASE I

By PATKAR REALTY

RG-MH-30162 · RERA P51700029977 · Last updated on MahaRERA portal: 21 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
19 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
37 of 70Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

ANANTA PRIDE PHASE I is a Residential / Group Housing project by PATKAR REALTY in Thane, Maharashtra, registered with MahaRERA as P51700029977 on 20 Jul 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 18 months from the original filing. 33 of the 70 units on this registration are recorded sold or booked, and 19 of 22 construction stages are filed complete.

At a glance

Project

  • NameANANTA PRIDE PHASE I
  • TypeResidential / Group Housing
  • Location
    • ERANJAD ROAD
    • AMBERNATH AMBESHIV VILLAGE
    • Ambeshiv Bk
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700029977
  • ReraGenie IDRG-MH-30162

Builder

  • NamePATKAR REALTY
  • Entity typePartnership
  • PartnersPARAG NANDKISHOR PATKAR, SUSHIL SUNDERDAS BAJAJ, RATI NANDKISHOR PATKAR
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredJul 2021First promiseJun 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Jul 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed95 files

Current status

47%33 of 70 units booked
92.1%Work done, per cost certificate

Figures as on 21 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER DNA9028028
TOWER ENA9042042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

TOWER D82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
TOWER D11
TOWER E11

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jun 2025
LandownerVillageDistrict
JANARDHAN SHANTARAM MEHERBadlapur (M Cl)Thane
KALPANA JANARDAN MEHERBadlapur (M Cl)Thane
NILESH JANARDAN MEHERBadlapur (M Cl)Thane
YUVRAJ JANARDAN MEHERBadlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Municipal Council
Permissible FSI2783.0
Proposed, not sanctioned2,783 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCANARA BANK ULHASNAGAR 2
Estimated costRs 6.10 cr
Cost incurredRs 5.62 cr
Work done92.12%
BuildingWingEstimatedIncurred
TOWER ENARs 3.48 crRs 3.41 cr
TOWER DNARs 2.26 crRs 2.21 cr
-NARs 36.62 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM SQUARE ARCHITECTS
ArchitectAcotech Consultants Pvt Ltd
EngineerATUL KUDTARKAR ASSOCIATES
Chartered AccountantRangani& co
Chartered AccountantKapure & Kapure
Chartered AccountantShripati Gandhi Choudhari & Co.
PartnerRole in project
PATKAR REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019615Jun 2024 → Jun 2025

Reason as filed by the promoterAs per Attached

EA10072502031Jun 2024 → Dec 2025

Reason as filed by the promoterThe main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. It is evident from Table C of Form 3 and sold booked inventory as on 31/03/2025 that only 29 units are sold out of total 70 units amounting to only 41% of total units being sold. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 30/06/2025 In addition to poor cash flows, cost overruns on projects, unexpected expenses, economic downturns are reasons that further contribu

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Phase I - Dec 25.pdf21 Feb 2026
Withdrawal Update Form 2File: Form 2 - Phase I - Dec 25.pdf21 Feb 2026
Withdrawal Update Form 3File: Form 3 - Phase I - Dec 25.pdf21 Feb 2026
Form 5 (FY 2022-2023)File: Form 5- 22-23.pdf24 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 - 23-24.pdf24 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf24 Dec 2025
Withdrawal Update Form 1File: Form 1 - Phase I - Sept 25.pdf10 Nov 2025
Withdrawal Update Form 2File: Form 2 - Phase I - Sept 25.pdf10 Nov 2025
Withdrawal Update Form 3File: Form 3 - Sept 25 - Phase I_compressed.pdf10 Nov 2025
Withdrawal Update Form 1File: Form -1 Phase-1 - June 25.pdf19 Aug 2025
Withdrawal Update Form 2File: Form 2 - I - June 25.pdf19 Aug 2025
Withdrawal Update Form 3File: Form-3 Phase-1 - June 25.pdf19 Aug 2025
Form 1File: Form-1 (Dec) Phase I.pdf9 Jul 2025
Form 2File: Form-2(Dec) Phase-1.pdf9 Jul 2025
Form 3File: Form-3 Phase-1 Promoters Acceptance.pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of flats Phase I.pdf9 Jul 2025
Form 1File: Form-1 March 24.pdf9 Jul 2025
Form 2File: form 2 - March 24.pdf9 Jul 2025
Form 3File: Signed Form 3 - Anant Pride Phase 1.pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory.pdf9 Jul 2025
Form 1File: Form-1 - Phase I.pdf9 Jul 2025
Form 2File: Form-2 Phase-I.pdf9 Jul 2025
Form 3File: Signed form 3 - Pro.pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Phase I.pdf9 Jul 2025
Form 1File: Form-1 Phase-1.pdf9 Jul 2025
Form 2File: Form-2 Phase-1.pdf9 Jul 2025
Form 3File: Signed Form 3 Phase 1.pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Phase-1.pdf9 Jul 2025
Form 1File: Form 1.pdf9 Jul 2025
Form 2File: Form-2.pdf9 Jul 2025
Form 3File: Form-3.pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf9 Jul 2025
Form 1File: Form-1.pdf14 Jun 2025
Form 2File: Form-2 Phase-1.pdf14 Jun 2025
Form 3File: Form-3 Phase-1_compressed.pdf14 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory Phase-1.pdf14 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Phase-1_compressed.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-1.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Phase-1.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Phase-1.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 Phase 1.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-1.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure Phase-1.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 - Phase I.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-I.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure Phase I.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed form 3 - Pro.pdf20 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 23-24.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA certificate.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 March 24.pdf13 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - March 24.pdf13 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf13 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 - Anant Pride Phase 1.pdf13 Apr 2024
Declaration in FORM BFile: Form B_compressed (1).pdf6 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Mar 2023.pdf6 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf23 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 (Dec) Phase I.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2(Dec) Phase-1.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of flats Phase I.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Phase-1 Promoters Acceptance.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 April.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 July.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 March.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 June.pdf10 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Promoters acceptance March 23.pdf26 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Promoters acceptance June 23.pdf26 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Promoters acceptance September 23.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf25 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf25 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 21-22.pdf25 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Patkar Realty - Form 2 dt 131022.pdf9 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Revised Letter (1).pdf9 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Patkar Realty Form 3 signed.pdf9 Jan 2023

How this compares with Thane

47%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 18 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANANTA PRIDE PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBERNATH AMBESHIV VILLAGE7,600+ in Thane

2 kmANANTA PRIDE PHASE ICompleted 46Lapsed / revoked 13Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 86 registered projects within 2 km.

Builder: PATKAR REALTY

PATKAR REALTY has 2 registrations on MahaRERA, including ANANTA PRIDE PHASE I and Ananta Pride Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that ANANTA PRIDE PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANANTA PRIDE PHASE I is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANTA PRIDE PHASE I?

The registered promoter entity is PATKAR REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANTA PRIDE PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANANTA PRIDE PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANTA PRIDE PHASE I?

The professionals named in the filing: Architect: M SQUARE ARCHITECTS; Architect: Acotech Consultants Pvt Ltd; Engineer: ATUL KUDTARKAR ASSOCIATES; Chartered Accountant: Rangani& co; Chartered Accountant: Kapure & Kapure; Chartered Accountant: Shripati Gandhi Choudhari & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANTA PRIDE PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANTA PRIDE PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANTA PRIDE PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.