ANANTA PRIDE PHASE I
RG-MH-30162 · RERA P51700029977 · Last updated on MahaRERA portal: 21 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 18 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANANTA PRIDE PHASE I is a Residential / Group Housing project by PATKAR REALTY in Thane, Maharashtra, registered with MahaRERA as P51700029977 on 20 Jul 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 18 months from the original filing. 33 of the 70 units on this registration are recorded sold or booked, and 19 of 22 construction stages are filed complete.
At a glance
Project
- NameANANTA PRIDE PHASE I
- TypeResidential / Group Housing
- Location
- ERANJAD ROAD
- AMBERNATH AMBESHIV VILLAGE
- Ambeshiv Bk
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700029977
- ReraGenie IDRG-MH-30162
Builder
- NamePATKAR REALTY
- Entity typePartnership
- PartnersPARAG NANDKISHOR PATKAR, SUSHIL SUNDERDAS BAJAJ, RATI NANDKISHOR PATKAR
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Jul 2021
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2024)
- Buildings2 building records
- Documents filed95 files
Current status
Figures as on 21 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER D | NA | 9 | 0 | 28 | 0 | 28 |
| TOWER E | NA | 9 | 0 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 21 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
TOWER D82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
TOWER E91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 21 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| TOWER D | 1 | 1 |
| TOWER E | 1 | 1 |
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| JANARDHAN SHANTARAM MEHER | Badlapur (M Cl) | Thane |
| KALPANA JANARDAN MEHER | Badlapur (M Cl) | Thane |
| NILESH JANARDAN MEHER | Badlapur (M Cl) | Thane |
| YUVRAJ JANARDAN MEHER | Badlapur (M Cl) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER E | NA | Rs 3.48 cr | Rs 3.41 cr |
| TOWER D | NA | Rs 2.26 cr | Rs 2.21 cr |
| - | NA | Rs 36.62 lakh | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | M SQUARE ARCHITECTS |
| Architect | Acotech Consultants Pvt Ltd |
| Engineer | ATUL KUDTARKAR ASSOCIATES |
| Chartered Accountant | Rangani& co |
| Chartered Accountant | Kapure & Kapure |
| Chartered Accountant | Shripati Gandhi Choudhari & Co. |
| Partner | Role in project |
|---|---|
| PATKAR REALTY | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per Attached
Reason as filed by the promoterThe main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. It is evident from Table C of Form 3 and sold booked inventory as on 31/03/2025 that only 29 units are sold out of total 70 units amounting to only 41% of total units being sold. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 30/06/2025 In addition to poor cash flows, cost overruns on projects, unexpected expenses, economic downturns are reasons that further contribu
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Phase I - Dec 25.pdf | 21 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Phase I - Dec 25.pdf | 21 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Phase I - Dec 25.pdf | 21 Feb 2026 |
| Form 5 (FY 2022-2023)File: Form 5- 22-23.pdf | 24 Dec 2025 |
| Form 5 (FY 2023-2024)File: Form 5 - 23-24.pdf | 24 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 24-25.pdf | 24 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Phase I - Sept 25.pdf | 10 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Phase I - Sept 25.pdf | 10 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - Sept 25 - Phase I_compressed.pdf | 10 Nov 2025 |
| Withdrawal Update Form 1File: Form -1 Phase-1 - June 25.pdf | 19 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 - I - June 25.pdf | 19 Aug 2025 |
| Withdrawal Update Form 3File: Form-3 Phase-1 - June 25.pdf | 19 Aug 2025 |
| Form 1File: Form-1 (Dec) Phase I.pdf | 9 Jul 2025 |
| Form 2File: Form-2(Dec) Phase-1.pdf | 9 Jul 2025 |
| Form 3File: Form-3 Phase-1 Promoters Acceptance.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of flats Phase I.pdf | 9 Jul 2025 |
| Form 1File: Form-1 March 24.pdf | 9 Jul 2025 |
| Form 2File: form 2 - March 24.pdf | 9 Jul 2025 |
| Form 3File: Signed Form 3 - Anant Pride Phase 1.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory.pdf | 9 Jul 2025 |
| Form 1File: Form-1 - Phase I.pdf | 9 Jul 2025 |
| Form 2File: Form-2 Phase-I.pdf | 9 Jul 2025 |
| Form 3File: Signed form 3 - Pro.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Phase I.pdf | 9 Jul 2025 |
| Form 1File: Form-1 Phase-1.pdf | 9 Jul 2025 |
| Form 2File: Form-2 Phase-1.pdf | 9 Jul 2025 |
| Form 3File: Signed Form 3 Phase 1.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Phase-1.pdf | 9 Jul 2025 |
| Form 1File: Form 1.pdf | 9 Jul 2025 |
| Form 2File: Form-2.pdf | 9 Jul 2025 |
| Form 3File: Form-3.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 9 Jul 2025 |
| Form 1File: Form-1.pdf | 14 Jun 2025 |
| Form 2File: Form-2 Phase-1.pdf | 14 Jun 2025 |
| Form 3File: Form-3 Phase-1_compressed.pdf | 14 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory Phase-1.pdf | 14 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Phase-1_compressed.pdf | 25 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-1.pdf | 25 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Phase-1.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf | 29 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 29 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 24 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Phase-1.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 Phase 1.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-1.pdf | 23 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Phase-1.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 - Phase I.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-I.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Phase I.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed form 3 - Pro.pdf | 20 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 23-24.pdf | 28 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA certificate.pdf | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 March 24.pdf | 13 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - March 24.pdf | 13 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf | 13 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 - Anant Pride Phase 1.pdf | 13 Apr 2024 |
| Declaration in FORM BFile: Form B_compressed (1).pdf | 6 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Mar 2023.pdf | 6 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 23 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 23 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 (Dec) Phase I.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2(Dec) Phase-1.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of flats Phase I.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Phase-1 Promoters Acceptance.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 April.pdf | 10 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 July.pdf | 10 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 March.pdf | 10 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 June.pdf | 10 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Promoters acceptance March 23.pdf | 26 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Promoters acceptance June 23.pdf | 26 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Promoters acceptance September 23.pdf | 26 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf | 25 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf | 25 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 21-22.pdf | 25 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Patkar Realty - Form 2 dt 131022.pdf | 9 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Revised Letter (1).pdf | 9 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Patkar Realty Form 3 signed.pdf | 9 Jan 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ANANTA PRIDE PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AMBERNATH AMBESHIV VILLAGE7,600+ in Thane
Filed coordinates, straight-line distance. 86 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: PATKAR REALTY
PATKAR REALTY has 2 registrations on MahaRERA, including ANANTA PRIDE PHASE I and Ananta Pride Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that ANANTA PRIDE PHASE I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ANANTA PRIDE PHASE I is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANANTA PRIDE PHASE I?
The registered promoter entity is PATKAR REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANANTA PRIDE PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ANANTA PRIDE PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANANTA PRIDE PHASE I?
The professionals named in the filing: Architect: M SQUARE ARCHITECTS; Architect: Acotech Consultants Pvt Ltd; Engineer: ATUL KUDTARKAR ASSOCIATES; Chartered Accountant: Rangani& co; Chartered Accountant: Kapure & Kapure; Chartered Accountant: Shripati Gandhi Choudhari & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANANTA PRIDE PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback