ReraGenieLog inGet a buyer report

Home / Browse projects / ANANTA HEIGHTS

Registration lapsed Litigation declared Residential / Group Housing project

ANANTA HEIGHTS

By JDJ-VISHAL

RG-MH-35920 · RERA P51900019919 · Last updated on MahaRERA portal: 25 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 3 cases
  • Completion date moved by 39 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jun 2026Possession promised4 months past this date
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
80 of 104Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

ANANTA HEIGHTS is a Residential / Group Housing project by JDJ-VISHAL in DADISETH AGIARY LANE, 400002, registered with MahaRERA as P51900019919 on 13 Mar 2019. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 39 months from the original filing. 24 of the 104 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameANANTA HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • NAVI WADI
    • DADISETH AGIARY LANE
    • 400002
  • Pincode400002
  • RERA no.P51900019919
  • ReraGenie IDRG-MH-35920

Builder

  • NameJDJ-VISHAL
  • Entity typeOthers
  • GSTIN27AADAJ5394C1ZN
  • Named personsVISHAL MEGA DEVELOPERS, JDJ DEVELOPERS PRIVATE LIMITED

Key dates

4 months past promisethis monthRegisteredMar 2019First promiseMar 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Mar 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Mar 2023)
  • Buildings1 building record
  • Documents filed51 files

Current status

23%24 of 104 units booked

Figures as on 25 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AVIGHNA HEIGHTSNA2323995104

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

AVIGHNA HEIGHTS: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area585 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jul 2026
LandownerVillageDistrict
JDJ DEVELOPERS PVT LTDABCD-400001Mumbai City
VISHAL MEGA DEVELOPERS-Mumbai City

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI4623.26
Proposed, not sanctioned4,135 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch380/82 JSS ROAD MUMBAI

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPR DHARIA AND ASSOCIATES
EngineerVJ JOSHI AND ASSOCIATES
Chartered AccountantHITESH GADA
Chartered AccountantJAY KUMAR SHAH
PartnerRole in project
JDJ-VISHAL-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900015314Mar 2023 → Jun 2026

Reason as filed by the promoterThe Extension is sought on the basis of consent terms filed in the Honorable Bombay High Court by the Members of the the Building in which the extension is sought till 30th June 2026. The copy of Consent Term is also attached to the COnsent of Sold unit holders

Litigation declared3

CaseCourtStatus
107 of 2018/2018bombay high courtconsent terms
685 of 2018/2018bombay high courtconsent terms
26 of 2022/2022Bombay High CourtConsent Term Filled

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form3-31_compressed (1).pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf25 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold.pdf25 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: certificate (1).pdf8 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 (1).pdf8 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 19-20.pdf20 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 20-21.pdf20 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf20 Feb 2024
Other - LegalFile: resolution consent for extension.pdf20 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf19 Jan 2024
Other - LegalFile: FormatB.pdf19 Jan 2024
Declaration in FORM BFile: Form B.pdf16 Jan 2024
Layout approvalFile: Approved Plan 1.pdf9 Jan 2024
Layout approvalFile: Approved Plan 2.pdf9 Jan 2024
Layout approvalFile: Approved Plan 3.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: Approved Plan 1.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: Approved Plan 2.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: Approved Plan 3.pdf9 Jan 2024
Declaration about Commencement CertificateFile: Format D- Declaration about CC.pdf9 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf9 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final Form 2.pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Final 2A.pdf9 Jan 2024
CERSAI detailsFile: CERSAI Report.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: Final List of Sold-Booked Inventory.pdf9 Jan 2024
Certificates of CA (Form 3)File: Final Form 3.pdf9 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Real Estate Organisation.pdf9 Jan 2024
Proforma of Agreement for saleFile: Proforma of AFS.pdf9 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A- Declaration of Seperate Bank Account.pdf9 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report of AFS.pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A RERA.pdf14 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- JDJ Vishal_compressed.pdf6 Dec 2019
Building plan approvalFile: IODcompressed.pdf6 Mar 2019
Layout approvalFile: Approved Plans 1.pdf6 Mar 2019
Layout approvalFile: Approved Plans2.pdf6 Mar 2019
Layout approvalFile: Approved Plans3.pdf6 Mar 2019
PAN CardFile: PAN JDJ-VISHAL_converted.pdf6 Mar 2019
Copy of the legal title reportFile: Title Certificate CS No1978.pdf6 Mar 2019
Copy of the legal title reportFile: Title Certificate CS No1979.pdf6 Mar 2019
Details of encumbrancesFile: Encumbrances Certificate.PDF6 Mar 2019
Copy of Layout Approval (in case of layout)File: Approved Plans 1.pdf6 Mar 2019
Copy of Layout Approval (in case of layout)File: Approved Plans2.pdf6 Mar 2019
Copy of Layout Approval (in case of layout)File: Approved Plans3.pdf6 Mar 2019
Building Plan Approval (IOD)File: IODcompressed.pdf6 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: PLINTH CC.pdf6 Mar 2019
Declaration in FORM BFile: FORM B Affidavit cum Undertaking_compressed.pdf6 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf6 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf6 Mar 2019
Certificates of CA (Form 3)File: form 3.pdf6 Mar 2019
Proforma of Allotment letterFile: Agreement for SaleRERADraft.pdf6 Mar 2019

Keep ANANTA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DADISETH AGIARY LANE

Builder: JDJ-VISHAL

JDJ-VISHAL has 1 registration on MahaRERA, including ANANTA HEIGHTS. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that ANANTA HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANANTA HEIGHTS is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANTA HEIGHTS?

The registered promoter entity is JDJ-VISHAL, an others as per the filing. Its GSTIN 27AADAJ5394C1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANTA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANANTA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANTA HEIGHTS?

The professionals named in the filing: Architect: PR DHARIA AND ASSOCIATES; Engineer: VJ JOSHI AND ASSOCIATES; Chartered Accountant: HITESH GADA; Chartered Accountant: JAY KUMAR SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANTA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANTA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANTA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.