Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
19 of 77Construction stages doneacross 7 buildings; furthest along: Staircases, 90%
2 of 7Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

Anant Serene Villas is a Residential / Group Housing project by Anant Builders in Raigarh, Maharashtra, registered with MahaRERA as P52000079647 on 18 Mar 2025. Possession is promised by 31 Dec 2027. The completion date has moved by 12 months from the original filing. 5 of the 7 units on this registration are recorded sold or booked, and 19 of 77 construction stages are filed complete.

At a glance

Project

  • NameAnant Serene Villas
  • TypeResidential / Group Housing
  • Location
    • Survey No. 139/1
    • Wardoli
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000079647
  • ReraGenie IDRG-MH-31313

Builder

  • NameAnant Builders
  • Entity typePartnership
  • GSTIN27ABKFA6285G1Z5
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersPramod Ramnarayan Agrawal, Jitesh Pramod Agrawal
  • Other registrations4 more →
  • Completed3 of 5
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2025First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Mar 2025
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2026)
  • Buildings7 building records
  • Documents filed50 files

Current status

71%5 of 7 units booked
94.8%Work done, per cost certificate

Figures as on 15 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bungalow - 1NA22101
Bungalow - 2NA22101
Bungalow - 3NA22101
Bungalow - 4NA22101
Bungalow - 5NA22101
Bungalow - 6NA22101
Bungalow - 7NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Staircases, at 90%.

Bungalow - 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow - 29%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow - 39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow - 49%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow - 59%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow - 673%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow - 772%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25
BuildingClosed/CoveredTotal
Bungalow - 122
Bungalow - 222
Bungalow - 322
Bungalow - 422
Bungalow - 522
Bungalow - 622
Bungalow - 71313

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,070 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Hello Homes RealtyWardoliRaigarh

Approvals and building plan

Sanctioning authorityNAVI MUMBAI AIRPORT INFLUENCE NOTIFIED AREA
Permissible FSI1656.0
Proposed, not sanctioned1,471 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRUPAM CENTRECINE PLANET, SION CIRCLESION EAST MUMBAI MAHARASHTRA 400022
Estimated costRs 4.00 cr
Cost incurredRs 3.79 cr
Work done94.85%
BuildingWingEstimatedIncurred
Bungalow - 1NARs 54.29 lakhRs 54.20 lakh
Bungalow - 2NARs 54.29 lakhRs 54.20 lakh
Bungalow - 3NARs 54.29 lakhRs 54.20 lakh
Bungalow - 4NARs 54.29 lakhRs 54.20 lakh
Bungalow - 5NARs 54.29 lakhRs 54.20 lakh
Bungalow - 6NARs 54.29 lakhRs 54.20 lakh
Bungalow - 7NARs 54.29 lakhRs 54.20 lakh
-NARs 20.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSwapnil Kalyankar
EngineerSK Consultants & Engineers
Chartered AccountantNB Sayed & Associates
Chartered AccountantPranav Bhaskaran & Associates
PartnerRole in project
Anant Builders-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30032620466Dec 2026 → Dec 2027

Reason as filed by the promoterWe hereby apply for extension under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The primary reason for the delay in completion of the project has arisen on account of the time required for completion of the balance construction work and for undertaking the statutory compliances necessary for obtaining the Occupation Certificate. The project is presently at an advanced stage of construction, with certain balance works still in progress. However, due to unforeseen circumstances, including procurement issues, financial constraints, and site-related challenges, the comp

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Feb 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1-Anant Serene Villlas as on June 2026.pdf15 Jul 2026
Withdrawal Update Form 2File: Anant_Serene_Villas_Form2_Q1_2026-27_15-07-2026_06-53.pdf15 Jul 2026
Withdrawal Update Form 3File: Anant_Serene_Villas_Form3_Q1_2026-27_15-07-2026_06-31_doc1.pdf15 Jul 2026
Withdrawal Update Form 1File: Form 1 - Anant Serene Villas as on March 2026.pdf20 May 2026
Withdrawal Update Form 2File: Form 2 - Anant Serene Villas as on March 2026.pdf20 May 2026
Withdrawal Update Form 3File: Form 3 - Anant Serene Villas as on March 2026.pdf20 May 2026
Withdrawal Update Form 1File: Form 1 - Anant Serene Villas as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 2File: Form 2 - Anant Serene Villas as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3 - Anant Serene Villas as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 1File: Form 1 - Anant Serene Villas as on Sep 2025.pdf20 Oct 2025
Withdrawal Update Form 2File: Form 2 - Anant Serene Villas as on Sep 2025.pdf20 Oct 2025
Withdrawal Update Form 3File: Form 3 - Anant Serene Villas as on Sep 2025.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - Anant Serene vIllas for FY 24-25.pdf11 Oct 2025
Form 1File: Form 1 - Anant Serene Villas as on June 2025.pdf19 Jul 2025
Form 2File: Form 2 - Anant Serene Villas as on June 2025.pdf19 Jul 2025
Form 3File: Form 3 - Anant Serene Villas as on June 2025.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Anant Serene Villas as on June 2025.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anant Serene Villas as on March 2025.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anant Serene Villas as on March 2025.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anant Serene Villas as on March 2025.pdf15 Apr 2025
Other - TechnicalFile: 1 Other - Technical (5).pdf8 Mar 2025
Other - TechnicalFile: 2 Other - Technical.pdf8 Mar 2025
Building plan approvalFile: Plan - Anant Serene Villas_Part2.pdf5 Mar 2025
Building plan approvalFile: Plan - Anant Serene Villas_Part3.pdf5 Mar 2025
Building plan approvalFile: Plan - Anant Serene Villas_Part4.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan - Anant Serene Villas_Part4.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan - Anant Serene Villas_Part3.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan - Anant Serene Villas_Part2.pdf5 Mar 2025
Layout approvalFile: Plan - Anant Serene Villas_Part1.pdf4 Mar 2025
Copy of Layout Approval (in case of layout)File: Plan - Anant Serene Villas_Part1.pdf4 Mar 2025
Proforma of Allotment letterFile: AL_Anant Serene Villa_Ms Anant Builders_24022025.pdf4 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: First Form 3 - Anant Serene Villa's (2).pdf4 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - All RERA Designated Bank Accounts -Area Sharing.pdf4 Mar 2025
Proforma of Agreement for saleFile: AFS_Anant Serene Villa_Ms Anant Builders_08032025.pdf4 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B -Declaration from the bank (1) (1).pdf4 Mar 2025
PAN CardFile: 1 PAN Card (1).pdf27 Feb 2025
Copy of the legal title reportFile: Title Final.pdf27 Feb 2025
Details of encumbrances concerned to FinanceFile: No ENCUMBRANCE LETTER -Dues.pdf27 Feb 2025
Details of encumbrances concerned to FinanceFile: No ENCUMBRANCE LETTER Litigations.pdf27 Feb 2025
Declaration in FORM BFile: FORM -B (Promoter) (1).pdf27 Feb 2025
Declaration about Commencement CertificateFile: Format D - Bungalow.pdf27 Feb 2025
CERSAI detailsFile: Cersai Declaration.pdf27 Feb 2025
Deviation Report with respect to Allotment letterFile: AL_Deviation_Anant Serene Villa_Ms Anant Builders_24022025.pdf27 Feb 2025
Details of encumbrances concerned to LegalFile: No ENCUMBRANCE LETTER -Dues.pdf27 Feb 2025
Details of encumbrances concerned to LegalFile: No ENCUMBRANCE LETTER Litigations.pdf27 Feb 2025
Other - FinanceFile: Final draft-Declaration regarding not selling units (2) (1).pdf27 Feb 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report Villas.pdf27 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Anant Builders.pdf27 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured and unsecured finance availed for the project (1).pdf27 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf22 Feb 2025

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
ANANT RESIDENCYP52000028314Vihighar, RaigarhFeb 2021CompletedSep 2024Jun 2024
Anant SakshiP52000019773Sakshi Nagar, RaigarhMar 2019CompletedDec 2022Aug 2021
Anant NiwasP52000020849Pushpak New, RaigarhMay 2019CompletedDec 2022Dec 2021

How this compares with Raigarh

71%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 12 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Anant Serene Villas on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wardoli5,900+ in Raigarh

2 kmAnant Serene VillasCompleted 5Lapsed / revoked 3Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 28 registered projects within 2 km.

Builder: Anant Builders

Anant Builders has 5 registrations on MahaRERA, including Anant Sakshi and Anant Niwas. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Anant Serene Villas is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anant Serene Villas?

The registered promoter entity is Anant Builders, a partnership as per the filing. Its GSTIN 27ABKFA6285G1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anant Serene Villas?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Anant Serene Villas?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Anant Serene Villas?

The professionals named in the filing: Architect: Swapnil Kalyankar; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anant Serene Villas?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anant Serene Villas. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anant Serene Villas to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.