ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Anandam Park

Completed No litigation declared Plotted project

Anandam Park

By Pankaj Chandrakant Waghmare

RG-MH-03516 · RERA P50500027394 · Last updated on MahaRERA portal: 8 Dec 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
0 of 28Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

Anandam Park is a Plotted project by Pankaj Chandrakant Waghmare in Nagpur, Maharashtra, registered with MahaRERA as P50500027394 on 8 Dec 2020. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 42 months from the original filing. 28 of the 28 units on this registration are recorded sold or booked.

At a glance

Project

  • NameAnandam Park
  • TypePlotted
  • Location
    • S. No. 91
    • Mouza Panjari Farm
    • P. H. no. 42
    • Nagpur
    • Panjari FArm
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • RERA no.P50500027394
  • ReraGenie IDRG-MH-03516

Builder

  • NamePankaj Chandrakant Waghmare
  • Entity typeIndividual
  • Other registrations11 more →
  • Completed8 of 12
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredDec 2020First promiseJun 2023Revised toDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Dec 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2023)
  • BuildingsNot stated in filing
  • Documents filed45 files

Current status

100%28 of 28 units booked

Figures as on 8 Dec 2023, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 8 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes25%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes25%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,592 sq m
Land owned byThe promoter
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCivil Lines Nagpur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEkveera Architects
EngineerParag Deshkar
Chartered AccountantRishi Lashkare
PartnerRole in project
Pankaj Chandrakant Waghmare-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500017336Jun 2023 → Dec 2026

Reason as filed by the promoterWith respect our residential plotted project named and styled as “ANANDAM PARK”, Kh. No. 91, PH No. 42, Village & Mouza - Panjari (Farm), Taluka - Nagpur (Rural), Distt. - Nagpur., vide Project Registration Number as - P50500027394; due to the slowdown in the real estate market in the region, we could not complete the few development works related to the completion of the project. We would require some more time to complete the development of the project. Hence, we hereby request your authority to kindly grant the requisite extension of the permission to complete the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Dec 2023

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 - Arch Completion Certificate - Anandam Park.pdf8 Dec 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Anandam Park.pdf7 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Arch Certificate - Anandam Park - Sept 2023.pdf16 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - Anandam Park - Sept 2023.pdf16 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory - Anandam Park - Sept 2023.pdf16 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate - Anandam Park - Sept 2023.pdf16 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Unique Park-5 - June 2023.pdf1 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Cerificate Unique Park-5 - June 2023.pdf1 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Inventory Unique Park-5 - June 2023.pdf1 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CA Certificate Of Unique Park-5 - June 2023n.pdf1 Oct 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Legal.pdf11 Sep 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Finance.pdf11 Sep 2023
Details of encumbrances concerned to LegalFile: Encumbrance Legal.pdf11 Sep 2023
Details of encumbrances concerned to LegalFile: Encumbrance Finance.pdf11 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate - March 2023 Qtr.pdf11 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - March 2023 Qtr.pdf11 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - 2019-20.pdf11 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - 2020-21.pdf11 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2021-22.pdf11 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2022-23.pdf11 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory - March 2023.pdf11 Sep 2023
CERSAI detailsFile: Self Declaration CERSAI.pdf11 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate - March 2023 Qtr.pdf11 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Format D Disclosure of Interest in Other Real Estate.pdf11 Sep 2023
Deviation Report with respect to Allotment letterFile: Deviation - Allotment Letter.pdf11 Sep 2023
Deviation Report with respect to model copy of AgreementFile: Deviation - Model Agreement.pdf11 Sep 2023
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate.pdf16 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate.pdf16 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf16 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate.pdf16 Sep 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf16 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf16 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21.pdf16 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 Pankja Waghmare.pdf4 Dec 2020
Copy of the legal title reportFile: Legal Title Report Pankaj Waghmare.pdf3 Dec 2020
Declaration in FORM BFile: Form B Pankaj Waghmare.pdf3 Dec 2020
OtherFile: CREDAI Pankaj Waghmare.pdf3 Dec 2020
Building plan approval or NA orderFile: NA Order.pdf26 Nov 2020
Layout approvalFile: Sanction Map_compressed.pdf26 Nov 2020
PAN CardFile: PAN.pdf26 Nov 2020
Details of encumbrancesFile: Encumbrance Letter.pdf26 Nov 2020
Copy of Layout Approval (in case of layout)File: Sanction Map_compressed.pdf26 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf26 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf26 Nov 2020
Proforma of Allotment letterFile: Allotment Letter.pdf26 Nov 2020

How this compares with Nagpur

100%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 42 months
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Anandam Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Panjari FArm2,800+ in Nagpur

Builder: Pankaj Chandrakant Waghmare

Pankaj Chandrakant Waghmare has 12 registrations on MahaRERA, including Gladstone and Anandam Park. Its filings disclose 8 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Anandam Park is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anandam Park?

The registered promoter entity is Pankaj Chandrakant Waghmare, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anandam Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Anandam Park?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Anandam Park?

The professionals named in the filing: Architect: Ekveera Architects; Engineer: Parag Deshkar; Chartered Accountant: Rishi Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anandam Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anandam Park. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anandam Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.