Pankaj Chandrakant Waghmare: RERA track record

Individual ยท attribution by exact filing name, entity resolution in progress

Pankaj Chandrakant Waghmare has 12 registrations on MahaRERA, including Gladstone and Anandam Park. Its filings disclose 8 earlier MahaRERA projects: declares 4 of 4 past projects completed on time.

12RERA registrations
8Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation
Follow this developer. An email when Pankaj Chandrakant Waghmare registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 12 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
MAULI TOWN 25P50500077995Mouza - Mohagaon, Nagpur, 4411109977%19 Nov 2024Registered
Anandam Elite Phase - 4P50500053050Wardha Road, Shankarpur, Nagpur, Nagpur, 4411087695%12 Oct 2023Completed
UNIQUE PARK - 5P50500046998Dongargaon, Nagpur, 4411086444%26 Sep 2022Completed
Anandam Elite Phase VIIIPP1190002502455welahari, Nagpur, 4411085910%23 Feb 2026Registered
ANANDAM ELITE PHASE IIIP50500048478MOUZA SHANKARPUR, Nagpur, 4411085064%3 Jan 2023Registration lapsed
Anandam Elite Phase VP50500080788Waroda Nagpur Gramin Nagpur, Nagpur, 4415014233%7 Jul 2025Completed
GladstoneP50500023032Gotadpanjiri, Nagpur, 4400183494%14 Nov 2019Completed
UNIQUE PARK - 2P50500030307Wardha Road, Nagpur, 44110834100%15 Aug 2021Completed
UNIQUE PARK - 1P50500030299Wardha Road, Nagpur, 4411083385%15 Aug 2021Completed
Anandam ParkP50500027394Panjari FArm, Nagpur, 44110828100%8 Dec 2020Completed
ANANDAM ELITE PHASE IP50500031969SHANKARPUR,NAGPUR, Nagpur, 4411081894%29 Nov 2021Completed
MAULI TOWN 26P50500077758Mouza - Mohagaon, Nagpur, 4411101100%29 Oct 2024Registered

What this promoter declares as its own experience

Pankaj Chandrakant Waghmare declares experience on 8 earlier projects. 8 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

8 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Gladstone
P50500023032
30 Dec 202130 Dec 2021On time
ANANDAM ELITE PHASE I
P50500031969
31 Dec 202331 Dec 2023On time
ANANDAM ELITE PHASE III
P50500048478
31 Dec 202431 Dec 2024On time
Anandam Elite Phase - 4
P50500053050
31 Dec 2026Not completed yetOngoing
UNIQUE PARK - 5
P50500046998
31 Dec 202630 Nov 2025On time
MAULI TOWN 25
P50500077995
31 Dec 2027Not completed yetOngoing
MAULI TOWN 26
P50500077758
31 Dec 2027Not completed yetOngoing
Anandam Elite Phase V
P50500080788
31 Dec 2028Not completed yetOngoing

Frequently asked questions

How do I verify Pankaj Chandrakant Waghmare as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Pankaj Chandrakant Waghmare?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.