Home / Browse projects / Pune, Maharashtra / ANAND

Registration lapsed No litigation declared Residential / Group Housing project

ANAND

By ARCHWAY PROPERTIES

RG-MH-44907 · RERA P52100050190 · Last updated on MahaRERA portal: 25 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 14 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 98%
17 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

ANAND is a Residential / Group Housing project by ARCHWAY PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100050190 on 21 Mar 2023. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 14 months from the original filing. 7 of the 24 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameANAND
  • TypeResidential / Group Housing
  • Location
    • ERANDWANA
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411038
  • Pincode411038
  • RERA no.P52100050190
  • ReraGenie IDRG-MH-44907

Builder

  • NameARCHWAY PROPERTIES
  • Entity typePartnership
  • GSTIN27ABGFA2219J1ZK
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersDILIP BALKRISHNA DESHPANDE, SAMEER DEEPAK JOSHI
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredMar 2023First promiseOct 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Mar 2023
  • Promised completion30 Dec 2025
  • Revised completionRevised to 30 Dec 2025 (originally 31 Oct 2024)
  • Buildings1 building record
  • Documents filed74 files

Current status

29%7 of 24 units booked
96.6%Work done, per cost certificate

Figures as on 25 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANANDNA7624024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.

ANAND: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 25 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered78

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Declared on31 May 2025
LandownerVillageDistrict
Shubhangi S KhadilkarPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI2324.22
Proposed, not sanctioned1,035 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOKMANYA NAGAR
Estimated costRs 8.59 cr
Cost incurredRs 8.29 cr
Work done96.57%
BuildingWingEstimatedIncurred
ANANDNARs 8.29 crRs 8.05 cr
-NARs 29.50 lakhRs 24.50 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectChitale Jog Associates
EngineerKalpak Constructions
EngineerMakardhwaj Kamble
Chartered AccountantChandorkar and Limaye Chartered Accountants
Chartered AccountantAshish Awati
PartnerRole in project
ARCHWAY PROPERTIES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024264Oct 2024 → Jun 2025

Reason as filed by the promoterAt the inception of the project, we had estimated that the project would be completed by October 31, 2024. However, after starting the excavation, we encountered substantial hard rock beneath the plot. This discovery significantly slowed the excavation process and necessitated the use of advanced machinery and additional resources. As a result, while we are now nearing the completion stage of the excavation, we need to revise our estimated completion date for the entire project. We request you to consider the new estimated completion date as June 30, 2025. Also Revised Sanction Plan as well as

EA30062501864Oct 2024 → Dec 2025

Reason as filed by the promoterElectrical installation and fittings along with sanitary work are pending. Also painting and tiling work need to be completed which require the extension period.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ANAND ARCHITECT FORM 1.pdf25 Mar 2026
Withdrawal Update Form 2File: ANAND ENGINEER FORM 2.pdf25 Mar 2026
Withdrawal Update Form 3File: ANAND FORM.pdf25 Mar 2026
Form 2A (FY 2024-2025)File: ANAND FORM 2A.pdf7 Nov 2025
Withdrawal Update Form 1File: Anand Form 1.PDF20 Oct 2025
Withdrawal Update Form 2File: Anand Form 2.PDF20 Oct 2025
Withdrawal Update Form 3File: anand form 3.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf21 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANAND RERA architect form 1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anand Form 3 Signed_.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANAND RERA engineer form 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: ANAND RERA sales inventory.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Anand sales inventory 2.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Anand Architect Form 1.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Engineer FORM 2.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ARCHWAY ANAND FORM 3_compressed.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ARCHWAY ANAND FORM 3_compressed.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ARCHWAY PROPERTIES CIVCON FORM 5.pdf25 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ARCHWAY PROPERTIES ANAND FORM 5.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf22 Jul 2024
Layout approvalFile: Sanction Plan Page 1_compressed.pdf1 Jun 2024
Layout approvalFile: Sanction Plan Page 2.pdf1 Jun 2024
Copy of Layout Approval (in case of layout)File: Sanction Plan Page 1_compressed.pdf1 Jun 2024
Copy of Layout Approval (in case of layout)File: Sanction Plan Page 2.pdf1 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 31 MAY 2024 - ANAND.pdf1 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anand Form3 Q4 FY 23-24_compressed.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1Anand.pdf13 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer FORM 2 Anand.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Anand.pdf28 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anand.pdf24 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Anand Rera Architect Form 1.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Rera Engineer FORM 2.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: Anand Rera Sales Inventory.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anand Form 3 30-9-23.pdf30 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Anand form 1 Architect.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand form 2 engineers.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Anand FORM 5.pdf5 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANAND FORM 3.pdf23 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf21 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: Sales inventory.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Form 3 Anand.pdf26 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archway Properties Anand Architect Form 1.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Archway Properties Anand Engineer FORM 2.pdf19 Apr 2023
Disclosure of sold/ booked inventoryFile: Archway Properties Anand Sales inventory.pdf19 Apr 2023
Copy of the legal title reportFile: 4 Search and Title report updated_compressed.pdf2 Mar 2023
Proforma of Agreement for saleFile: 2 Agreement for Sale.pdf24 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 22 Anand form 3.pdf18 Feb 2023
Disclosure of sold/ booked inventoryFile: 15 Inventory.pdf17 Feb 2023
Layout approvalFile: 7 Layout approval_compressed.pdf14 Feb 2023
Building plan approvalFile: 8 Building Approval_compressed.pdf14 Feb 2023
PAN CardFile: 1 PAN Card.PDF14 Feb 2023
Details of encumbrances concerned to FinanceFile: 5 No Encumbrances Khadilkar.pdf14 Feb 2023
Details of encumbrances concerned to FinanceFile: 6 No Legal Encumbrances anand.pdf14 Feb 2023
Details of encumbrances concerned to LegalFile: 5 No Encumbrances Khadilkar.pdf14 Feb 2023
Details of encumbrances concerned to LegalFile: 6 No Legal Encumbrances anand.pdf14 Feb 2023
Copy of Layout Approval (in case of layout)File: 7 Layout approval_compressed.pdf14 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 8 Building Approval_compressed.pdf14 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: 9 Commencment Certificate.pdf14 Feb 2023
Declaration about Commencement CertificateFile: 10 Declaration about commencement certificate Khadilkar.pdf14 Feb 2023
Declaration in FORM BFile: 11 Form B Archway Properties.pdf14 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 Form 1 Architect certificate.pdf14 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 Form 2 Engineer certificate.pdf14 Feb 2023
CERSAI detailsFile: 16 CERSAI Khadilkar.pdf14 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 20 Interest Disclosure DBD.pdf14 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 21 Interest Disclosure Sameer Joshi.pdf14 Feb 2023
Proforma of Allotment letterFile: 3 Allotment letter.pdf14 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 19 Separate Bank account disclosure.pdf14 Feb 2023
Deviation Report with respect to Allotment letterFile: 18 Deviation report as to Model Allotment Letter.pdf14 Feb 2023
Deviation Report with respect to model copy of AgreementFile: 17 Deviation report as per AFS.pdf14 Feb 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
MOHAN APARTMENTSSADASHIV PETH PUNE 41103018CompletedSep 2022Jul 2021
JAYSHREE APARTMENTSS NO 720 CTS NO 177 PLOT NO 1 NAVI PETH PUNE 3012CompletedDec 2018Nov 2018

How this compares with Pune

29%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 14 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANAND on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ERANDWANA13,700+ in Pune

Builder: ARCHWAY PROPERTIES

ARCHWAY PROPERTIES has 9 registrations on MahaRERA, including JAYSHREE APARTMENTS PHASE I and MOHAN APARTMENT PHASE I. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that ANAND shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANAND is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANAND?

The registered promoter entity is ARCHWAY PROPERTIES, a partnership as per the filing. Its GSTIN 27ABGFA2219J1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANAND?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANAND?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANAND?

The professionals named in the filing: Architect: Chitale Jog Associates; Engineer: Kalpak Constructions; Engineer: Makardhwaj Kamble; Chartered Accountant: Chandorkar and Limaye Chartered Accountants; Chartered Accountant: Ashish Awati. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANAND?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANAND. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANAND to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.