Home / Browse projects / Mumbai Suburban, Maharashtra / Anand Bhawan
Anand Bhawan
By Jet Speed Realtors Private Limited
RG-MH-91670 · RERA P51800035189 · Last updated on MahaRERA portal: 2 May 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Anand Bhawan is a Others project by Jet Speed Realtors Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800035189 on 10 May 2022. The registration is recorded completed; possession was promised by 28 Feb 2026.
At a glance
Project
- NameAnand Bhawan
- TypeOthers
- Location
- Bajaj Road
- Vile Parle West
- Andheri
- Mumbai Suburban
- 400056
- Pincode400056
- RERA no.P51800035189
- ReraGenie IDRG-MH-91670
Builder
- NameJet Speed Realtors Private Limited
- Entity typeCompany
- CINU45200MH2005PTC157834
- GSTIN27AACCD2841D1Z2
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsKeyur Hemant Shah, Hemant Kantilal Shah
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on10 May 2022
- Promised completion28 Feb 2026
- Revised completionNone
- Buildings2 building records
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 16 | 0 | 0 | 0 | 0 |
| B Wing | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 2 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
A Wing100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B Wing100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed260
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A Wing | 130 | 130 |
| B Wing | 130 | 130 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Nav Vile Parle Co Operative Housing Society Ltd | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| Jet Speed Realtors Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Mar 2025
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anand Bhawan as on March 2025.pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anand Bhawan as on March 2025.pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anand Bhawan as on March 2025.pdf | 18 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GFDGVS.pdf | 27 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anand Bhawan as on 31-12-2024.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anand Bhawan as on 31-12-2024.pdf | 21 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Anand Bhawan 31-12-2024.pdf | 17 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 Signed Anand Bhawan as on September 2024.pdf | 2 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anand Bhawan as on 30-09-2024.pdf | 26 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2024.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Anand Bhawan 30-09-2024.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Anand Bhawan FY 2023-24.pdf | 8 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anand Bhawan as on June 2024.pdf | 15 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anand Bhawan as on June 2024.pdf | 13 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anand Bhawan as on June 2024.pdf | 12 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 Signed Anand Bhawan as on March 2024.pdf | 10 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anand Bhawan as on March 2024.pdf | 25 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anand Bhawan as on March 2024.pdf | 15 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anand Bhawan as on March 2024.pdf | 12 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 ) Form-1.pdf | 16 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6) Form-2.pdf | 16 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3 ) Form 2-A.pdf | 16 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: 4) Circular 29.pdf | 16 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5) Form-3- (10-02-24 ).pdf | 16 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 8) Form-5 (FY 2022-23).pdf | 16 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - Anand Bhawan.pdf | 9 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anand Bhawan Dec 2023.pdf | 11 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Format-Form-3 Anand Bhawan 31-12-2023.pdf | 11 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - anand Bhawan as on Dec 2023.pdf | 10 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jet speed realtors pvt ltd form -1 Anand bhavan sep 2023.pdf | 28 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Bhawan Sept 23 - Form 2.pdf | 23 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Anand Bhawan 30-09-2023.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Anand Bhawan FY 22-23.pdf | 27 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Anand Bhawan June 2023.pdf | 15 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Anand Bhawan as on June 2023.pdf | 15 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Anand Bhawan as on 30-06-2023.pdf | 15 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 18 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anand bhawan.pdf | 18 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Anand Bhawan.pdf | 17 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 2708_20230401105812_001.pdf | 29 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Anand Bhawan as on December 2022.pdf | 28 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anand Bhawan December 2022.pdf | 28 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29- Anand Bhawan.pdf | 11 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Anand Bhavan.pdf | 10 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Anand Bhawan.pdf | 14 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Bhawan Form 2- September 2022.pdf | 13 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anand Bhawan September 2022.pdf | 13 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Anand Bhavan June 2022.pdf | 21 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Bhawan Form 2- June 2022.pdf | 21 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Anand Bhawan june 2022_compressed.pdf | 21 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: download (23)-1-7_merged.pdf | 29 Apr 2022 |
| Copy of the legal title reportFile: 1 Copy of the legal title report.pdf | 21 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: First CC Anand Bhawan.pdf | 21 Apr 2022 |
| Declaration about Commencement CertificateFile: C 32.pdf | 21 Apr 2022 |
| Declaration in FORM BFile: Anand Bhawan chs vile parla Promoter Form B Notarised.pdf | 23 Mar 2022 |
| CERSAI detailsFile: CERSAI -Anand Bhawan.pdf | 15 Mar 2022 |
| Proforma of Allotment letterFile: Final Agr Anand Bhawan.pdf | 15 Mar 2022 |
| Details of encumbrancesFile: Anand Bhavan -Encumbrance.pdf | 13 Jan 2022 |
| Layout approvalFile: Plan Anand Bhawan_1-1.pdf | 11 Jan 2022 |
| Building plan approvalFile: Plan Anand Bhawan_2-3.pdf | 11 Jan 2022 |
| Building plan approvalFile: Plan Anand Bhawan_4-5.pdf | 11 Jan 2022 |
| Building plan approvalFile: Plan Anand Bhawan_6-end.pdf | 11 Jan 2022 |
| PAN CardFile: Jet Speed Realtors p l pan card.pdf | 11 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Plan Anand Bhawan_1-1.pdf | 11 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Anand Bhawan_2-3.pdf | 11 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Anand Bhawan_4-5.pdf | 11 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Anand Bhawan_6-end.pdf | 11 Jan 2022 |
| Proforma of Allotment letterFile: Allotment Letter draft RERA.pdf | 11 Jan 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
Keep Anand Bhawan on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vile Parle West6,700+ in Mumbai Suburban
CHANDAK VANSHAM
CHANDAK REALTORS PRIVATE LIMITED
AJOD ONE
AJOD REALTY LLP
GAUTAM DHAN
NEW INDIA CONSTRUCTIONS
AJMERA SHRINGAAR
H J CORPORATION
Imperial Landmark
Neminath and Disha Realtors
PINAL EVANA
Pinal Realty LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Jet Speed Realtors Private Limited
Jet Speed Realtors Private Limited has 2 registrations on MahaRERA, including Anand Bhawan and Trinity Towers. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Anand Bhawan is delayed beyond 28 Feb 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Anand Bhawan?
The registered promoter entity is Jet Speed Realtors Private Limited, a company as per the filing. Its CIN U45200MH2005PTC157834 and GSTIN 27AACCD2841D1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Anand Bhawan?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Anand Bhawan?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in Anand Bhawan?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback