Home / Browse projects / Nashik, Maharashtra / Amrut Shakti
Amrut Shakti
By SAHANE INFRA BUILDERS AND DEVELOPERS
RG-MH-74716 · RERA P51600048465 · Last updated on MahaRERA portal: 28 Dec 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Amrut Shakti is a Residential / Group Housing project by SAHANE INFRA BUILDERS AND DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600048465 on 3 Jan 2023. The registration is recorded completed; possession was promised by 31 Dec 2027. 7 of the 19 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameAmrut Shakti
- TypeResidential / Group Housing
- Location
- Nashik
- 422009
- Pincode422009
- RERA no.P51600048465
- ReraGenie IDRG-MH-74716
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on3 Jan 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed94 files
Current status
Figures as on 28 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Amrut Shakti | NA | 8 | 0 | 16 | 3 | 19 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
Amrut Shakti: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Chairman of Amrut Shakti | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHAN PEKHALE PEKHALE |
| Engineer | SANDIP VERMA VERMA |
| Chartered Accountant | Neetu Saxena |
| Chartered Accountant | DILIP PANDURANG PALDE |
| Chartered Accountant | MONALI S DUBEY |
| Partner | Role in project |
|---|---|
| SAHANE INFRA BUILDERS AND DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Sep 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Sep 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1 ARCHITECT.pdf | 28 Dec 2025 |
| Form 2File: FORM 2 ENGG CERTIFICATE.pdf | 28 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 28 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold inventory.pdf | 28 Dec 2025 |
| Occupational CertificateFile: OCCUPANCY CERTIFICATE AMRUTSHAKTI.pdf | 28 Dec 2025 |
| Form 1File: Amrutshakti architect certificate Sep 2023.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti architect certificate Sep 2023.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti - Sold Unsold - Sep-23.pdf | 18 Dec 2025 |
| Form 1File: Amrutshakti Architect certificate Dec 23.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti Engineer certificate Dec-23.pdf | 18 Dec 2025 |
| Form 3File: Amrutshakti - CA Certificate - Dec-23.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti Sold Unsold Stm Dec-23.pdf | 18 Dec 2025 |
| Form 1File: Amrutshakti Rera certificate Architect March 24.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti Rera certificate Eng March 24.pdf | 18 Dec 2025 |
| Form 3File: CA certificate Amrutshakti March 24.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti - sold unsold - Mar-24.pdf | 18 Dec 2025 |
| Form 1File: Amrutshakti Rera certificate Architect June 24.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti RERA certificate June 24.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti - sold unsold - Mar-24.pdf | 18 Dec 2025 |
| Form 1File: Amrutshakti Rera certificate Architect Sep 24.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti Engg certificate Sep 24.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti - sold unsold - Mar-24.pdf | 18 Dec 2025 |
| Form 1File: FORM 1 ARCHITECT.pdf | 18 Dec 2025 |
| Form 2File: FORM 2 Engineer Certi Amrutshakti.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold inventory.pdf | 18 Dec 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 18 Dec 2025 |
| Form 2File: FORM 2 ENGG CERTIFICATE.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold inventory.pdf | 18 Dec 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 18 Dec 2025 |
| Form 2File: FORM 2 engg certificate.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE 0625.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold inventory.pdf | 18 Dec 2025 |
| Form 1File: Amrutshakti architect certificate Sep 2023.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti - Engineer Certificate - Sep 2023.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti - Sold Unsold - Sep-23.pdf | 18 Dec 2025 |
| Form 1File: Amrutshakti architect certificate Sep 2023.pdf | 18 Dec 2025 |
| Form 2File: Amrutshakti - Engineer Certificate - Sep 2023.pdf | 18 Dec 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Amrutshakti - Sold Unsold - Sep-23.pdf | 18 Dec 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A Supervisor certificate.pdf | 18 Dec 2025 |
| Form 5 (FY 2022-2023)File: CA certificate form - 5 Amrutshakti MAR23.pdf | 18 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT.pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 11 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certi Amrutshakti.pdf | 11 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amrutshakti Rera certificate Architect March 24.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amrutshakti Rera certificate Architect June 24.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amrutshakti Rera certificate Architect Sep 24.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amrutshakti - CA Certificate - Dec-23_11zon.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Amrutshakti March 24.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 16 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amrutshakti Engg certificate Sep 24.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amrutshakti architect certificate Sep 2023.pdf | 10 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amrutshakti Architect certificate Dec 23.pdf | 10 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_11zon (3).pdf | 10 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amrutshakti - Engineer Certificate - Sep 2023.pdf | 10 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amrutshakti Engineer certificate Dec-23.pdf | 10 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-2023.pdf | 5 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 (1).pdf | 5 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD OCT 23.pdf | 4 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT 6-10-23-compressed (1).pdf | 4 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amrutshakti - Architech Certificate - Mar-23.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amrutshakti - Engineer Certi - Jun-23.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AMRUTSHAKTI CA FORM 3 - MARCH 23.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AMRUTSHAKTI CA FORM 3 - JUN 23.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT JUNE 23.pdf | 28 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 28 Aug 2023 |
| Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf | 25 Dec 2022 |
| Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf | 25 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NEW CA AMRUT.pdf | 15 Dec 2022 |
| Proforma of Agreement for saleFile: 2 Proforma of Allotment letter (1).pdf | 22 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: declaration model copy allotment letter.pdf | 22 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: declaration model copy aggrement.pdf | 22 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: Encumbrance certificate (1) - Copy_page-0001.pdf | 30 Sep 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| GIRIJA SOCIETYP51600025552 | NEAR MSEB COLONY SHIVAJI NAGAR, Nashik | Jun 2020 | Certificate Signed | Jun 2025 | Jun 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
Keep Amrut Shakti on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nashik4,100+ in Nashik
STAR WORLD
DEEPAK KALYANJI CHANDE
VRAJ CENTRAL VISTA
DHAIRYA DEVELOPERS
ROONGTA TECHONE APARTMENT
SHREE TIRUMALA BUILDCON
VRAJ CAPITAL
KAPILAVASTU CREATORS
MAA BHAGWATI RESIDENCY APARTMENT
ROONGTA LANDMARKS LLP
THREE LEAVES PHASE ONE
DEEPAK INFRA AND HOMES PRIVATE LIMITED
See every Nashik project, with the district possession charts
Builder: SAHANE INFRA BUILDERS AND DEVELOPERS
SAHANE INFRA BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including GIRIJA SOCIETY and Amrut Shakti. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Amrut Shakti is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Amrut Shakti?
The registered promoter entity is SAHANE INFRA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Amrut Shakti?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Amrut Shakti?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Amrut Shakti?
The professionals named in the filing: Architect: ARCHAN PEKHALE PEKHALE; Engineer: SANDIP VERMA VERMA; Chartered Accountant: Neetu Saxena; Chartered Accountant: DILIP PANDURANG PALDE; Chartered Accountant: MONALI S DUBEY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Amrut Shakti?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback