ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / AMRUT HEIGHTS

Registered No litigation declared Residential / Group Housing project

AMRUT HEIGHTS

By AMRUT NIWAS

RG-MH-17776 · RERA P51700055652 · Last updated on MahaRERA portal: 1 May 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2029Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 38%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

AMRUT HEIGHTS is a Residential / Group Housing project by AMRUT NIWAS in Thane, Maharashtra, registered with MahaRERA as P51700055652 on 5 Apr 2024. Possession is promised by 30 Apr 2029.

At a glance

Project

  • NameAMRUT HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • SHIVAJI CHOWK
    • KALYAN
    • Thane
    • 421301
  • Pincode421301
  • RERA no.P51700055652
  • ReraGenie IDRG-MH-17776

Builder

  • NameAMRUT NIWAS
  • Entity typePartnership
  • PartnersRAKESH AMRITLAL MUTHA, DHANRAJ TULSARAM SUTHAR, PRADEEP AMRITLAL SHANKLESHA, HITESH TULSARAM SUTHAR

Key dates

this monthRegisteredApr 2024PromisedApr 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Apr 2024
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMRUT HEIGHTSNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 38%.

AMRUT HEIGHTS: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered1
Open Space117

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,151 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
NEW GIRIRAJ CHS LTDKalyanThane
RISHI JASWANTRAI KARIAKalyanThane

Approvals and building plan

Permissible FSI11514.67
Proposed, not sanctioned2,213 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWASAN AUTOMOBILE, GURU GOBIND HOUSE, OPP PURNIMA THEATRE, MURBAD ROAD, KALYAN W, THANE-421301

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectORDINATE DESIGN
EngineerKHASNIS & ASSOCIATES
Chartered AccountantANKIT PARAS JAIN & CO
PartnerRole in project
AMRUT NIWAS-

Litigation declared2

CaseCourtStatus
134/2023/2023KALYAN COURTPENDING
336/2023/2023KALYAN COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2029

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 31-03-2025 Sign.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31-03-2025 Sign.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 31-03-2025 Sign.pdf1 May 2025
Disclosure of sold/ booked inventoryFile: 31-03-2025.pdf1 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30-06-2024 Form 3_0001.pdf21 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30-09-2024 Form 3_0001.pdf21 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31-12-2024 Form 3_0001.pdf21 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 30-06-2024.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 30-09-2024.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-12-2024.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 sept 24.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 24.pdf20 Mar 2025
Disclosure of sold/ booked inventoryFile: 30 june 24.pdf20 Mar 2025
Disclosure of sold/ booked inventoryFile: 30 sept 24.pdf20 Mar 2025
Disclosure of sold/ booked inventoryFile: 31 dec 24.pdf20 Mar 2025
Building plan approvalFile: Building Layout.pdf27 Mar 2024
Building plan approvalFile: Original.pdf27 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Layout.pdf27 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Original.pdf27 Mar 2024
Declaration in FORM BFile: FORM B- Promoter revised.pdf19 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_merged.pdf19 Mar 2024
Proforma of Agreement for saleFile: Agreement for sale new.pdf19 Mar 2024
Layout approvalFile: Revised - converted (4).pdf26 Feb 2024
Copy of Layout Approval (in case of layout)File: Revised - converted (4).pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Oriiginal CC_compressed.pdf26 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Report On Deviation To Agreement For Sale_0001_compressed.pdf26 Feb 2024
Other - FinanceFile: Declaration for Allotment to landowner.pdf26 Feb 2024
Other - TechnicalFile: Declaration-Cum-Undertaking.pdf26 Feb 2024
Details of encumbrances concerned to FinanceFile: Declaration For Financial Encumrbances.pdf24 Feb 2024
Details of encumbrances concerned to FinanceFile: Declaration For Legal Encumrbances.pdf24 Feb 2024
Details of encumbrances concerned to LegalFile: Declaration For Financial Encumrbances.pdf24 Feb 2024
Details of encumbrances concerned to LegalFile: Declaration For Legal Encumrbances.pdf24 Feb 2024
Declaration about Commencement CertificateFile: FORM D-Declaration About Commencement Certificate.pdf24 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- Architech certificate.pdf24 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate_compressed.pdf24 Feb 2024
CERSAI detailsFile: Declaration For No Cersai Report.pdf24 Feb 2024
CERSAI detailsFile: CERSAI_Search_Report_200298041684_For_Asset_Based_Search_24_02_2024_13_17_52_621.pdf24 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Dhanraj Sutar_0001.pdf24 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Hitesh Sutar_0001.pdf24 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Pradeep Amritlal Shanklesha_0001.pdf24 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Rakesh Amritlal Mutha_0001.pdf24 Feb 2024
Proforma of Allotment letterFile: Draft_Allotment Letter_compressed.pdf24 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A _Decalaration for Bank account.pdf24 Feb 2024
Deviation Report with respect to Allotment letterFile: Report On Devivation To Allotment Letter_0001.pdf24 Feb 2024
PAN CardFile: Pan card_Amrut Niwas.pdf22 Feb 2024
Copy of the legal title reportFile: Title- Giriraj Society.pdf22 Feb 2024
Copy of the legal title reportFile: Title- Rishi Karia.pdf22 Feb 2024

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AMRUT HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN7,600+ in Thane

Builder: AMRUT NIWAS

AMRUT NIWAS has 1 registration on MahaRERA, including AMRUT HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if AMRUT HEIGHTS is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AMRUT HEIGHTS?

The registered promoter entity is AMRUT NIWAS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AMRUT HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AMRUT HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AMRUT HEIGHTS?

The professionals named in the filing: Architect: ORDINATE DESIGN; Engineer: KHASNIS & ASSOCIATES; Chartered Accountant: ANKIT PARAS JAIN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMRUT HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMRUT HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMRUT HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.