Home / Browse projects / Pune, Maharashtra / Ambrosia Alley

Registered No litigation declared Residential / Group Housing project

Ambrosia Alley

By AMBROSIA LANDMARK PRIVATE LIMITED

RG-MH-16593 · RERA P52100026792 · Last updated on MahaRERA portal: 13 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 24 months from the original
10 of 11Construction stages donefurthest along: Stilt Floor, 0%
30 of 74Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

Ambrosia Alley is a Residential / Group Housing project by AMBROSIA LANDMARK PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100026792 on 25 Oct 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 44 of the 74 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAmbrosia Alley
  • TypeResidential / Group Housing
  • Location
    • 17 1/2 Nali Road
    • NR DSK Sundarbun
    • Hadapsar
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100026792
  • ReraGenie IDRG-MH-16593

Builder

  • NameAMBROSIA LANDMARK PRIVATE LIMITED
  • Entity typeCompany
  • DirectorSachin Laxman Bhadale
  • DirectorSHAILENDRA DNYANESHWAR TUPE

Key dates

this monthRegisteredOct 2020First promiseJun 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2020
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed86 files

Current status

59%44 of 74 units booked
100.2%Work done, per cost certificate

Figures as on 13 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA1614631174

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

WING A: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes60%
Street LightingYes60%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes95%
Energy managemcntYes60%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes75%
Open ParkingYes50%

Parking filed77

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots77
Closed/Covered48
Open Space29

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Sep 2025
LandownerVillageDistrict
Appasaheb Rangnath KalbhorLoni-kalbhorPune
Sachin Laxman BhadaleURULI DEVACHIPune
GULAB TUPEPune (M Corp.)Pune

Approvals and building plan

Permissible FSI7764.87
Proposed, not sanctioned3,416 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShri Ganesh Complex Shop No 1TO6 Surve No 255 213 kadam Wak Vasti Loni Kalbhor Pune 412201
Estimated costRs 26.13 cr
Cost incurredRs 26.19 cr
Work done100.24%
BuildingWingEstimatedIncurred
WING ANARs 24.41 crRs 24.41 cr
-NARs 1.72 crRs 1.78 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDnyaneshwar Birajdar a BIRAJDAR
ArchitectVINAYAK D WAGHMARE
EngineerDattatray Gorakshnath Mate
Chartered AccountantSRPA & Associate LLP
PartnerRole in project
AMBROSIA LANDMARK PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA26062501741Jun 2025 → Jun 2027

Reason as filed by the promoterThe extension is majorly due to revision of Sanctioned Plan. As a result of this revision, additional construction work is required, which has extended the overall timeline.We would like to emphasize that all necessary consents and permissions for the revised plan have been obtained, and we are attaching the relevant documents for your reference.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000269585Tukaram Sarjerao SawantAppasaheb Rangnath Kalbhor15/10/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q4 25-26.pdf7 May 2026
Withdrawal Update Form 2File: Form 2 Q4 25-26.pdf7 May 2026
Withdrawal Update Form 3File: Form 3 Q4 25-26_compressed.pdf7 May 2026
Withdrawal Update Form 1File: Form 1 Q3 25-26.pdf6 May 2026
Withdrawal Update Form 1File: Form 1 Q4 25-26.pdf6 May 2026
Withdrawal Update Form 2File: Form 2 Q3 25-26.pdf6 May 2026
Withdrawal Update Form 2File: Form 2 Q4 25-26.pdf6 May 2026
Withdrawal Update Form 3File: Form 3 Q3 25-26.pdf6 May 2026
Withdrawal Update Form 3File: Form 3 Q4 25-26_compressed.pdf6 May 2026
Withdrawal Update Form 1File: Form 1.pdf31 Mar 2026
Withdrawal Update Form 2File: Engineers Certificate.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3.pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Q1 25-26.pdf8 Sep 2025
Withdrawal Update Form 2File: Form 2 - Q1 25-26.pdf8 Sep 2025
Withdrawal Update Form 3File: Form 3 CA Q1 25-26.pdf8 Sep 2025
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf8 Sep 2025
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf8 Sep 2025
Form 2A (FY 2024-2025)File: 2024-25 Form 2A.pdf8 Sep 2025
Form 5 (FY 2022-2023)File: Form 5 2022-2023 Final.pdf5 Sep 2025
Form 5 (FY 2023-2024)File: Form 5 2023-2024 Final.pdf5 Sep 2025
Form 1File: Form 1 Architect Q1 24-25.pdf1 Sep 2025
Form 2File: Form 2 Engineer Q1 24-25.pdf1 Sep 2025
Form 3File: Form 3 CA Q1 24-25.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold-Booked Q1 24-25.pdf1 Sep 2025
Form 1File: Form 1 Q2 24-25 Architect.pdf1 Sep 2025
Form 2File: Form 2 Q2 24-25 Engineers.pdf1 Sep 2025
Form 3File: Form 3 CA Q2 24-25.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold-Booked Q2 24-25.pdf1 Sep 2025
Form 1File: Form 1 Architect Q3 24-25.pdf1 Sep 2025
Form 2File: Form 2 Engineer Q3 24-25.pdf1 Sep 2025
Form 3File: Form 3 CA Q3 24-25.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold-Booked Q3 24-25.pdf1 Sep 2025
Form 1File: Form 1 Architect Q4 24-25.pdf1 Sep 2025
Form 2File: Form 2 Engineer Q4 24-25.pdf1 Sep 2025
Form 3File: Form 3 CA Q4 24-25.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold-Booked Q4 24-25.pdf1 Sep 2025
Form 1File: Form 1 Architect Q1 25-26.pdf1 Sep 2025
Form 2File: Form 2 - Q1 25-26.pdf1 Sep 2025
Form 3File: Form 3 CA Q1 25-26.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold-Booked Q1 25-26.pdf1 Sep 2025
Copy of the legal title reportFile: landowner flats details.pdf10 May 2024
Layout approvalFile: SANCTION LAYOUT_11zon.pdf22 Dec 2023
Copy of Layout Approval (in case of layout)File: SANCTION LAYOUT_11zon.pdf22 Dec 2023
Building plan approvalFile: 2_11zon.pdf6 May 2023
Building plan approvalFile: 2_11zon.pdf6 May 2023
Building plan approvalFile: 3_11zon.pdf6 May 2023
Building plan approvalFile: 3_11zon.pdf6 May 2023
Building plan approvalFile: 4_11zon.pdf6 May 2023
Building plan approvalFile: 5_11zon.pdf6 May 2023
Building plan approvalFile: 6_11zon.pdf6 May 2023
Building plan approvalFile: 7_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 2_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 2_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 3_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 3_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 4_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 5_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 6_11zon.pdf6 May 2023
Building Plan Approval / NA Order for plotted developmentFile: 7_11zon.pdf6 May 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENSEMENT CERTIFICATE2_11zon.pdf6 May 2023
Declaration about Commencement CertificateFile: COMMENSEMENT CERTIFICATE_11zon.pdf6 May 2023
Other - FinanceFile: ambrosia sanction letter_00001.pdf14 Mar 2023
Details of encumbrancesFile: ENCUMBRANCES .pdf4 Aug 2021
Proforma of Allotment letterFile: REVISED_AGREEMENT FOR SALE_NEW.pdf4 Aug 2021
Proforma of Allotment letterFile: Agreement For Sale.pdf29 Sep 2020
Proforma of Allotment letterFile: Agreement For Sale.pdf29 Sep 2020
Copy of the legal title reportFile: title search report final.pdf25 Sep 2020
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf25 Sep 2020
Proforma of Allotment letterFile: allotment latter.pdf25 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AMBROSIA LANDMARK CA CERTIFICATER.pdf22 Sep 2020
Building plan approvalFile: NOC 2.pdf17 Sep 2020
Building plan approvalFile: NOC 2.pdf17 Sep 2020
Building plan approvalFile: NOC 2.pdf17 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: NOC 2.pdf17 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: NOC 2.pdf17 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: NOC 2.pdf17 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENSEMENT CERTIFICATE.pdf17 Sep 2020
Declaration in FORM BFile: FORM B.pdf17 Sep 2020
PAN CardFile: PAN CARD AMBROSIA.pdf14 Sep 2020

How this compares with Pune

59%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ambrosia Alley on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NR DSK Sundarbun13,700+ in Pune

2 kmAmbrosia AlleyCompleted 86Lapsed / revoked 19Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 196 registered projects within 2 km.

Builder: AMBROSIA LANDMARK PRIVATE LIMITED

AMBROSIA LANDMARK PRIVATE LIMITED has 1 registration on MahaRERA, including Ambrosia Alley. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ambrosia Alley is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ambrosia Alley?

The registered promoter entity is AMBROSIA LANDMARK PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ambrosia Alley?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ambrosia Alley?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ambrosia Alley?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ambrosia Alley?

The professionals named in the filing: Architect: Dnyaneshwar Birajdar a BIRAJDAR; Architect: VINAYAK D WAGHMARE; Engineer: Dattatray Gorakshnath Mate; Chartered Accountant: SRPA & Associate LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ambrosia Alley?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ambrosia Alley. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ambrosia Alley to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.