AMBIKA ESTATE PHASE 1
RG-MH-88824 · RERA P51700008966 · Last updated on MahaRERA portal: 19 Dec 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 5 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMBIKA ESTATE PHASE 1 is a Residential / Group Housing project by Ambika Brickwell LLP in Thane, Maharashtra, registered with MahaRERA as P51700008966 on 19 Aug 2017. Possession is promised by 30 Dec 2028. 5 complaints are on record with the regulator.
At a glance
Project
- NameAMBIKA ESTATE PHASE 1
- TypeResidential / Group Housing
- Location
- Bhiwandi Wada road
- Near Shelar village
- Borpada
- Bhiwandi
- Thane
- 421302
- Pincode421302
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008966
- ReraGenie IDRG-MH-88824
Builder
- NameAmbika Brickwell LLP
- Entity typePartnership
- PartnersSHAMMI KANHIYALAL MAMTANI, MAHENDRA RANVIR NEGI, KANCHAN HANUMANT DOLAS
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Aug 2017
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings14 building records
- Documents filed110 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MOUNT PLEASANT B | NA | 24 | 0 | 0 | 0 | 0 |
| MONT BLANC C | NA | 24 | 0 | 0 | 0 | 0 |
| MONT BLANC A | NA | 24 | 0 | 0 | 0 | 0 |
| MONT BLANC B | NA | 24 | 0 | 0 | 0 | 0 |
| MOUNT PLEASANT A | NA | 24 | 0 | 0 | 0 | 0 |
| HIMALAYAS A , Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| HIMALAYAS B, Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| HIMALAYAS C, Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| ACROPLOLIS, Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| MOUNT EVEREST A, Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| MOUNT EVEREST B,Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| MOUNT EVEREST C, Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| MOUNT EVEREST D, Bookings not Open | NA | 24 | 0 | 0 | 0 | 0 |
| SHOPPING | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building14
As on 19 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Slabs of Super Structure, at 50%.
MOUNT PLEASANT B58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 18% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
MONT BLANC C53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 7% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
MONT BLANC A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MONT BLANC B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MOUNT PLEASANT A19%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 50% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
HIMALAYAS A , Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
HIMALAYAS B, Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
HIMALAYAS C, Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ACROPLOLIS, Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MOUNT EVEREST A, Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MOUNT EVEREST B,Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MOUNT EVEREST C, Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MOUNT EVEREST D, Bookings not Open0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHOPPING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 19 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 65% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 15% |
| Storm Water Drains | Yes | 5% |
| Landscaping & Tree Planting | Yes | 44% |
| Street Lighting | Yes | 35% |
| Community Buildings | Yes | 10% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 15% |
| Water conservation /Rain water harvesting | Yes | 32% |
| Energy managemcnt | Yes | 45% |
| Fire protection and fire safety requirements | Yes | 5% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | Yes | 10% |
| Open Parking | Yes | 0% |
| Others | Yes | 75% |
Parking filed1603
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| MOUNT PLEASANT B | 176 | 0 | 176 |
| MONT BLANC C | 65 | 0 | 65 |
| MONT BLANC A | 65 | 0 | 65 |
| MONT BLANC B | 54 | 0 | 54 |
| MOUNT PLEASANT A | 176 | 0 | 176 |
| HIMALAYAS A , Bookings not Open | 146 | 30 | 176 |
| HIMALAYAS B, Bookings not Open | 146 | 30 | 176 |
| HIMALAYAS C, Bookings not Open | 146 | 30 | 176 |
| ACROPLOLIS, Bookings not Open | 96 | 80 | 176 |
| MOUNT EVEREST A, Bookings not Open | 40 | 47 | 87 |
| MOUNT EVEREST B,Bookings not Open | 40 | 47 | 87 |
| MOUNT EVEREST C, Bookings not Open | 40 | 47 | 87 |
| MOUNT EVEREST D, Bookings not Open | 39 | 48 | 87 |
| SHOPPING | 0 | 15 | 15 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ANUP SHYAM KARNANI | Andheri | Mumbai Suburban |
| Ambika Colonisers LLP | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE & ASSOCIATES |
| Architect | SPACIOUS DESIGN ARCHITECTS PVT LTD |
| Engineer | ASCENT STRUCTURAL ENGINEERS PVTLTD |
| Partner | Role in project |
|---|---|
| Ambika Brickwell LLP | - |
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000171889 | V Vinay Kumar | Anup Karnani | 17/12/2019 |
| CC006000000375368 | Sagar Pramod Pawar | Ambika Brickwell LLP (through MD) | 08/05/2023 |
| CC006000000480335 | ROHIT WATTAL | AMBIKA BRICKWELL LLP | 19/07/2024 |
| CC006000000530684 | RUBINA JACOB ROBIN | M/S. AMBIKA BRICKWELL LLP THROUGH ITS DESIGNATED PARTNER MR. ANUP SHYAM KARNANI | 06/06/2024 |
| CC12600192 | MOHAMMAD QAYYUM BADRUDDIN SHAIKH | Ambika Brickwell LLP | 11/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Dec 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Jul 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2028
Documents filed110
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: C A Certificate as on March 2023.pdf | 19 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Quarter 4 of 22-23.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Quarter 4 of 22-23.pdf | 30 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Quality Certificate Quarter 4 of 22-23.pdf | 30 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 CA Annual Certificate of FY 22-23.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Quarter 2 of FY 22-23.pdf | 2 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Quarter 3 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 1 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 2 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 3 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 1 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 1 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 2 of FY 22-23.pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Certificate Quarter 3 of FY 22-23.pdf | 2 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1Q22022-23ARCHITECT.pdf | 1 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1Q32022-23ARCHITECT.pdf | 1 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3,CA Certificate,Quarter 2 2022-23.pdf | 1 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3,CA Certificate,Quarter 3 2022-23.pdf | 1 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5FY2021-22.pdf | 1 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Quarter 3 of 21-22-compressed (2).pdf | 8 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Quarter 4 of 21-22-compressed (1).pdf | 8 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Quarter 1 of 22-23-compressed (1).pdf | 8 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Quarter 3 of 21-22-compressed (2).pdf | 8 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Quarter 4 of 21-22-compressed (1).pdf | 8 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Quarter 1 of 22-23-compressed.pdf | 8 Oct 2022 |
| Certificates of CA (Form 3)File: CA Certificate Quarter 4 of 21-22-compressed (1).pdf | 8 Oct 2022 |
| Certificates of CA (Form 3)File: CA Certificate Quarter 1 of 22-23-compressed (1).pdf | 8 Oct 2022 |
| Certificates of CA (Form 5)File: CA Certificate Quarter 3 of 21-22-compressed (1).pdf | 8 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 CA Annual Certificate of 21-22.pdf | 8 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Form 3A as on 30-9-2021 of Ambika Estate Phase 1.pdf | 13 Nov 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for July-2021 to Sep-2021 of Ambika Estate Phase 1.pdf | 9 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for Apr-2021 to June-2021 of Ambika Estate Phase 1.pdf | 7 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for July-2021 to Sep-2021 of Ambika Estate Phase 1.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for Apr-2021 to June-2021 of Ambika Estate Phase 1.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for July-2021 to Sep-2021 of Ambika Estate Phase 1.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Eng Quality Certificae June-21.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Eng Quality Certificae Sept-21.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: CA Certificate for Apr-2021 to June-2021 of Ambika Estate Phase 1.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: CA Certificate for July-2021 to Sep-2021 of Ambika Estate Phase 1.pdf | 7 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: MahaRera Form 3A for Jan 2021 to March 2021 of Ambika Estate Phase 1.pdf | 7 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 CA Certificate of FY 2019-2020.pdf | 7 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - CA Certificate FY 2020-2021.pdf | 7 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for Jan-2020 to March-2020 of Ambika Estate Phase 1.pdf | 26 May 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for Jan-2020 to March-2020 of Ambika Estate Phase 1.pdf | 26 May 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Quality Certificate for Jan-2020 to March-2020 of Ambika Estate Phase 1.pdf | 26 May 2021 |
| Certificates of CA (Form 3)File: CA Certificate for Jan-2020 to March-2020 of Ambika Estate Phase 1.pdf | 26 May 2021 |
| Certificates of CA (Form 5)File: Form 5 - CA Certificate.pdf | 26 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for Jan-2021 to March-2021 of Ambika Estate Phase 1.pdf | 13 May 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for Jan-2021 to March-2021 of Ambika Estate Phase 1.pdf | 13 May 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Quality Certificate for Jan-2021 to March-2021 of Ambika Estate Phase 1.pdf | 13 May 2021 |
| Certificates of CA (Form 3)File: CA Certificate for Jan-2021 to March-2021 of Ambika Estate Phase 1.pdf | 13 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for Oct-2020 to Dec-2020 of Ambika Estate Phase 1.pdf | 23 Apr 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for Oct-2020 to Dec-2020 of Ambika Estate Phase 1.pdf | 23 Apr 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for Oct-2020 to Dec-2020 of Ambika Estate Phase 1.pdf | 23 Apr 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Quality Assurance Certificate for Oct-2020 to Dec-2020 of Ambika Estate Phase 1.p | 23 Apr 2021 |
| Certificates of CA (Form 3)File: CA Certificate of Oct-2020 to Dec-2020 of Ambika Estate Phase 1.pdf | 23 Apr 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RERA Quality Engineer Certificate as on 31-12-19.pdf | 25 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Forms_Architect certificate Phase-1 Dec-19.pdf | 5 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Forms_Engineer_Certificate_Dec-19.pdf | 5 Feb 2020 |
| Certificates of CA (Form 3)File: RERA forms_C A certificate_ Dec-19.pdf | 5 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Forms_Architect certificate Phase-1 Sep-19.pdf | 1 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Forms_Engineer_Certificate_Sep-19.pdf | 1 Nov 2019 |
| Certificates of CA (Form 3)File: RERA forms_C A certificate_ Sep-19.pdf | 1 Nov 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - CA Certificate.pdf | 1 Nov 2019 |
| Certificates of CA (Form 5)File: Form 5 - CA Certificate.pdf | 26 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ambika City_RERA Architect certificate_ June-19.pdf | 9 Aug 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ambika City_RERA Engineer certificate_June-19.pdf | 9 Aug 2019 |
| Certificates of CA (Form 3)File: Ambika City_RERA C A certificate_ June-19.pdf | 9 Aug 2019 |
| Building plan approvalFile: Layout.pdf | 23 Jul 2019 |
| Building Plan Approval (IOD)File: Layout.pdf | 23 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Forms_Architect certificate Phase-1 Mar-19.pdf | 6 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Forms_Engineer_Certificate_Mar-19.pdf | 6 May 2019 |
| Certificates of CA (Form 3)File: RERA forms_C A certificate_ Mar-19.pdf | 6 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Amended Commencement Certificate dated 3-1-2019.pdf | 22 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Dec-18.pdf | 30 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Dec-18.pdf | 30 Jan 2019 |
| Certificates of CA (Form 3)File: CA Certificate_Dec-18.pdf | 30 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_Sep-18.pdf | 5 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Sep-18.pdf | 5 Nov 2018 |
| Certificates of CA (Form 3)File: C A certificate_ Sep-18.pdf | 5 Nov 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 110 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep AMBIKA ESTATE PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Shelar village7,600+ in Thane
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
DGT - Sector 3A - Cluster 2 - Phase 1
ADRIKA DEVELOPERS PRIVATE LIMITED
DOSTI GREATER THANE - PHASE 1
ADRIKA DEVELOPERS PRIVATE LIMITED
Dosti Greater Thane - Sector 3A - Cluster 1B -
ADRIKA DEVELOPERS PRIVATE LIMITED
USHA RESIDENCY
SHREE BUDHDEV INFRA
NARAYANI DHAM BUILDING NO 2A AND 2B
MAYA DEVELOPER
See every Thane project, with the district possession charts
Builder: Ambika Brickwell LLP
Ambika Brickwell LLP has 1 registration on MahaRERA, including AMBIKA ESTATE PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if AMBIKA ESTATE PHASE 1 is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMBIKA ESTATE PHASE 1?
The registered promoter entity is Ambika Brickwell LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMBIKA ESTATE PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMBIKA ESTATE PHASE 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AMBIKA ESTATE PHASE 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMBIKA ESTATE PHASE 1?
The professionals named in the filing: Architect: AJAY WADE & ASSOCIATES; Architect: SPACIOUS DESIGN ARCHITECTS PVT LTD; Engineer: ASCENT STRUCTURAL ENGINEERS PVTLTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMBIKA ESTATE PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback