Home / Browse projects / Mumbai Suburban, Maharashtra / AMAZON PARK BUILDING NO 2 - WING C

Completed No litigation declared Residential / Group Housing project

AMAZON PARK BUILDING NO 2 - WING C

By R.J. CONSTRUCTIONS

RG-MH-42939 · RERA P51800002956 · Last updated on MahaRERA portal: 21 Feb 2025

Source: official MahaRERA filing

Red flags

  • 14 complaints at MahaRERA
  • Completion date moved by 45 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Installation of Lifts, 90%
14Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

AMAZON PARK BUILDING NO 2 - WING C is a Residential / Group Housing project by R.J. CONSTRUCTIONS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002956 on 4 Aug 2017. The registration is recorded completed; possession was promised by 31 Mar 2025. The completion date has moved by 45 months from the original filing. 14 complaints are on record with the regulator.

At a glance

Project

  • NameAMAZON PARK BUILDING NO 2 - WING C
  • TypeResidential / Group Housing
  • Location
    • LINK ROAD
    • BORIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400103
  • Pincode400103
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002956
  • ReraGenie IDRG-MH-42939

Builder

  • NameR.J. CONSTRUCTIONS
  • Entity typePartnership
  • GSTIN27AAAFR4765R1ZG
  • PartnersHARESH MOHANBHAI JOSHI, SUNIL BABARAM DEVRUKHKAR
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Aug 2017
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed106 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMAZON PARK BUILDING NO 2 - WING CNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

AMAZON PARK BUILDING NO 2 - WING C: 54% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities16

As on 21 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
LIGHTNING ARRESTERYes100%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Open Space20

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area250 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Oct 2024

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2371.0
Proposed, not sanctioned2,371 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 3 4 RAJKIRAN CHS LTD M G ROAD KANDIVALI WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTARUN H MOTTA
Chartered AccountantCHAHAN VORA AND ASSOCIATES
Chartered AccountantVAYEDA AND ASSOCIATES
PartnerRole in project
R.J. CONSTRUCTIONS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013255Jun 2021 → Jun 2023

Reason as filed by the promoterWe have already completed 95% of the work and are awaiting certain permissions. We will apply for Occupation Certificate once we received those permissions. please grant us 6 months Extension.

EXT51800010057Jun 2021 → Jun 2022

Reason as filed by the promoterDue to Pandemic of Covid 19 the construction activity was stopped from March'2020 and after unlock there was non availability of Labour and Building Material because of that the work was slow down.

EXT51800017785Jun 2021 → Jun 2024

Reason as filed by the promoterThe Fire NOC required for obtaining Occupation Certificate is delayed due to some technical reason in the layout

EXT51800024604Jun 2021 → Mar 2025

Reason as filed by the promoterThe Construction activity of the Project is 100% completed except the Installation of Mechanical Parking. The Mechanical Parking work is in progress which is time consuming process.

Litigation declared2

CaseCourtStatus
SUIT LOD NO 2449 OF 2010/2010BOMBAY HIGH COURTINJUNCTION PREVAILS
SUIT L NO 644 OF 2016 /2016BOMBAY HIGH COURTINJUNCTION PREVAILS

Complaints filed with MahaRERA14

Case no.ComplainantRespondentFiled
CC006000000197703Rajiv Vasant ShahR.J. CONSTRUCTIONS23/07/2021
CC006000000197705Rajiv Vasant ShahR.J. CONSTRUCTIONS23/07/2021
CC006000000197706Pallavi M MunshiR.J. CONSTRUCTIONS23/07/2021
CC006000000197707Vasant Premji Shah through his power of attorney holder Rajiv Vasant ShahR.J. Construction26/07/2021
CC006000000197708Pallavi M MunshiR.J. CONSTRUCTIONS26/07/2021
CC006000000197709Smita Vasant Shah through power of attorney Rajiv Vasant ShahR.J. Construction26/07/2021
CC006000000197710Vasant Premji Shah through power of attorney holder Rajiv Vasant ShahR.J. CONSTRUCTIONS26/07/2021
CC006000000197711smita vasant shah through power of attorney holder rajiv vasant shahR.J. Construction26/07/2021
CC006000000197712Vinod Shah, through Power of Attorney Holder, Jinesh ShahR.J. CONSTRUCTIONS27/07/2021
CC006000000197713Vinod P Shah through Power of Attorney Holder Jinesh ShahR.J. CONSTRUCTIONS27/07/2021
CC006000000197714Varsha Vasant Shah through power of attorney holder Jinesh ShahRJ Construction27/07/2021
CC006000000197715Varsha Shah through power of attorney holder Jinesh ShahR.J. CONSTRUCTIONS27/07/2021
CC006000000210005Estate of the late Mr. Premji Hirji Shah through his administrators and legal heirsR.J. Construction partnership firm through its partners12/02/2022
CC006000000210006Estate of the Late Mr. Premji Hirji Shah through his Administrators and Legal HeirsM/s R.J. Construction, a partnership firm through its partners12/02/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Dec 2024

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: page 1.pdf21 Feb 2025
Building plan approvalFile: page 2.pdf21 Feb 2025
Building plan approvalFile: page 3.pdf21 Feb 2025
Building plan approvalFile: page 4.pdf21 Feb 2025
Building plan approvalFile: page 5.pdf21 Feb 2025
Building plan approvalFile: page 6.pdf21 Feb 2025
Building plan approvalFile: page 7.pdf21 Feb 2025
Building plan approvalFile: page 8.pdf21 Feb 2025
Building plan approvalFile: page 9.pdf21 Feb 2025
Building plan approvalFile: page 10.pdf21 Feb 2025
Building plan approvalFile: page 11.pdf21 Feb 2025
Building plan approvalFile: page 12.pdf21 Feb 2025
Building plan approvalFile: page 13.pdf21 Feb 2025
Building plan approvalFile: page 14.pdf21 Feb 2025
Building plan approvalFile: page 15.pdf21 Feb 2025
Building plan approvalFile: page 16.pdf21 Feb 2025
Copy of Layout Approval (in case of layout)File: page 1.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 8.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 16.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 15.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 14.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 13.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 12.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 11.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 10.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 9.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 7.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 6.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 5.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 4.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 3.pdf21 Feb 2025
Building Plan Approval (IOD)File: page 2.pdf21 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf7 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf2 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE.pdf2 Dec 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY.pdf2 Dec 2024
Certificates of CA (Form 3)File: FORM - 3.pdf29 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf11 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Site Supervisior Certificate.pdf11 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf11 Oct 2024
Declaration about Commencement CertificateFile: Format D - Declartion About Commencement Certificate.pdf13 Aug 2024
Declaration in FORM BFile: FORM B .pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3 JUNE 2023.pdf12 Aug 2024
Certificates of CA (Form 3)File: FORM 3 SEPTEMBER 2023.pdf12 Aug 2024
Certificates of CA (Form 3)File: FORM 3 DECEMBER 2023.pdf12 Aug 2024
Certificates of CA (Form 3)File: FORM 3 MARCH 2024.pdf12 Aug 2024
Certificates of CA (Form 3)File: FORM 3 JUNE 2024.pdf12 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Site Supervisior Certificate.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf6 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Site Supervisior Certificate1.pdf6 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate1.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Architect Certificate.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Site Supervisior Certificate.pdf5 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Site Supervisior Certificate1.pdf5 Apr 2024
Declaration about Commencement CertificateFile: Format D - Declartion About Commencement Certificate.pdf27 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Certifcate of Engineer for Quality Assurance.pdf27 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf27 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Certifcate of Architect.pdf19 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf19 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Certifcate of Site Supervisior.pdf19 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Certificate from Site Supervisior.pdf19 Oct 2023
Certificates of CA (Form 3)File: FORM 3 June 2023.pdf19 Oct 2023
Certificates of CA (Form 3)File: FORM 3 March 2023.pdf19 Oct 2023
Certificates of CA (Form 3)File: FORM 3 Sept 2023.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM5.pdf19 Oct 2023
Certificates of CA (Form 3)File: FORM 3.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf15 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf15 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf15 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cerificate.pdf13 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Site Supervisior Certificate.pdf13 Jun 2022
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD.pdf13 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: C A Certificate Form 5.pdf13 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CertificatefromLicensedSurveyor.pdf1 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CertificatefromSiteSupervisior.pdf1 Oct 2021
Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE.pdf30 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE FROM LICENSE SURVEYOR.pdf30 Jun 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
AMAZON PARK BUILDING NO 2 WING C - 1 TO 7 FLOORCTS NO 532 PT 1541 1533 1532 DIVISION R WARD VILLAGE EKSAR TALUKA BORIVALI MUMBAI 40010314CompletedJan 2015Late, Jan 2016

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 45 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AMAZON PARK BUILDING NO 2 - WING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI WEST6,700+ in Mumbai Suburban

2 kmAMAZON PARK BUILDING NO Completed 109Lapsed / revoked 69Other 154Dot size: filed unitsN

Filed coordinates, straight-line distance. 332 registered projects within 2 km.

Builder: R.J. CONSTRUCTIONS

R.J. CONSTRUCTIONS has 1 registration on MahaRERA, including AMAZON PARK BUILDING NO 2 - WING C. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AMAZON PARK BUILDING NO 2 - WING C is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AMAZON PARK BUILDING NO 2 - WING C?

The registered promoter entity is R.J. CONSTRUCTIONS, a partnership as per the filing. Its GSTIN 27AAAFR4765R1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AMAZON PARK BUILDING NO 2 - WING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AMAZON PARK BUILDING NO 2 - WING C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AMAZON PARK BUILDING NO 2 - WING C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AMAZON PARK BUILDING NO 2 - WING C?

The professionals named in the filing: Architect: TARUN H MOTTA; Chartered Accountant: CHAHAN VORA AND ASSOCIATES; Chartered Accountant: VAYEDA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMAZON PARK BUILDING NO 2 - WING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMAZON PARK BUILDING NO 2 - WING C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMAZON PARK BUILDING NO 2 - WING C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.