Completed No litigation declared Residential / Group Housing project

Alpinia

By Acme Housing India Private Limited

RG-MH-10346 · RERA P51700000778 · Last updated on MahaRERA portal: 25 Mar 2023

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Internal walls, 95%
6Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

Alpinia is a Residential / Group Housing project by Acme Housing India Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700000778 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameAlpinia
  • TypeResidential / Group Housing
  • Location
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700000778
  • ReraGenie IDRG-MH-10346

Builder

  • NameAcme Housing India Private Limited
  • Entity typeCompany
  • ChairpersonMunish Pravin Doshi
  • Other registrations7 more →
  • Completed6 of 8
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AlpiniaNA280000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

Alpinia: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises74%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.63%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%

Progress on shared amenities19

As on 25 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
stiltYes100%
External PodiumYes82%
AmenitiesYes0%
2 Level podiumYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area566 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11875.45
Proposed, not sanctioned11,875 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGanga jamuna apts, gr floor, opp shoppers stop, S V Road, Andheri West, Mumbai - 400058

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSCAPES
ArchitectMandviwala Qutub and Associates
EngineerJW CONSULTANTS LLP
PartnerRole in project
Acme Housing India Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700003930Dec 2019 → Dec 2020

Reason as filed by the promoter• 17 Months Delay - Tree cutting permission delay • 06 Months Delay - Between tree authority permission and commencement certificate from TMC • 05 Months Delay - High Court Stay Order on TMC • 6 Months Delay - New Labour Law Compliance by all Contractors • 4 Months Delay - Demonetization exercised by Central Government • 3 Months Delay - Compliance of new RERA Act • 3 Months Delay - Compliance of new GST Policies • 24 Months Delay - Building Material Shortage of Sand, Cement, RMC, etc. • 1 Month Delay - Till Date after submission of Application of OC • Several Months On-Going Delay Till Date -

Litigation declared6

CaseCourtStatus
7949 of 2015/2015High Court BombayPending
First Appeal No 1264 of 2015/2015High Court BombayPending
SCS 925 of 2008 New no RCS 1120 of 2012/2012Thane Civil CourtPending
Cri WP No 4182 of 2015/2015High Court BombayPending
Civil WP No 4096 of 2015/2015High Court BombayPending
CC/13/18/2013Consumer Court State CommissionPending

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000078600RAJESH KUMAR PODDARACME HOUSING INDIA PRIVATE LTD06/04/2019
CC006000000079085Jaywant Anant Pandit & 2 Ors.Acme Housing India Private Limited03/05/2019
CC006000000100395DHRUBA JYOTI BORAACME HOUSING INDIA PVT. LTD.04/08/2019
CC006000000192582PIJUSH BISWAS AND KANIKA BISWASMs Ascent construction pvt ltd12/02/2020
CC006000000193084Mr. Aniket Deelip Alashe and Mrs. Rajashree Deelip AlasheAcme Housing India Private Limited20/06/2020
CC006000000396217SHAHEEN IFTIKHAR PUNJABIAscent construction private limited23/06/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Jun 2021

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: ALPINIA REGISTRTION CERTFICATE.pdf25 Mar 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER RERA FORMAT - ALPINIA.pdf5 Jan 2023
Declaration about Commencement CertificateFile: Alpinia Declaration for Commencement Certificate.pdf4 Jan 2023
Proforma of Agreement for saleFile: Proforma of AFS.pdf31 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A-(April-June).pdf27 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A-(July-Sept).pdf27 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A-(Oct-Dec)).pdf27 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A-(Jan-March).pdf27 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ACME HOUSING FORM 5 DELAY LETTER.pdf29 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Acme Ozone Alpinia OC.pdf28 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: 20200402 FORM 4 Arch Certificate for Alpinia.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY2019-20 Form 5 ALPINIA.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- Alpinia.pdf18 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20191218 FORM 4_A_Arch Certificate- Alpinia_Bldg.pdf18 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Scan20191218174738.pdf18 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: 20191218 FORM 4_A_Arch Certificate- Alpinia_Bldg.pdf18 Dec 2019
Certificates of CA (Form 5)File: Form 5- Alpinia.pdf30 Sep 2019
Certificates of CA (Form 5)File: Alpinia Form 5 COMPRESSED.pdf30 Sep 2018
Proforma of Allotment letterFile: Ozone-Alpinia-AFS as per RERA - Revised.pdf28 Dec 2017
Declaration in FORM BFile: Affidavit Cum Declaration - Alpinia.pdf23 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: Ozone IOD.pdf20 Jul 2017
Declaration in FORM BFile: Affidavit Cum Declaration - Alpinia.pdf20 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Alpinia.pdf20 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-Alpinia.pdf20 Jul 2017
Proforma of Allotment letterFile: Ozone-Alpinia-AFS 15-07-2017.pdf20 Jul 2017
OtherFile: Proposed layout-20-07-17.pdf20 Jul 2017
Certificates of CA (Form 3)File: CA Certiifcate - Alpinia.pdf19 Jul 2017
Building plan approvalFile: Acme Ozone Amended IOD Date 04-03-2017.pdf15 Jul 2017
Layout approvalFile: Alpinia plan 1.pdf15 Jul 2017
Layout approvalFile: Alpinia plan 2.pdf15 Jul 2017
Copy of the legal title reportFile: Ozone TC 12th July, 2017_Compressed.pdf15 Jul 2017
Details of encumbrancesFile: Ozone TC 12th July, 2017_Compressed.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: Alpinia plan 1.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: Alpinia plan 2.pdf15 Jul 2017
Building Plan Approval (IOD)File: Acme Ozone Amended IOD Date 04-03-2017.pdf15 Jul 2017
PAN CardFile: Acme Housing.pdf13 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Oakwood and AshwoodThane Maharashtra382CompletedDec 2013Late, Dec 2014

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Alpinia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane (M Corp.)7,600+ in Thane

2 kmAlpiniaCompleted 88Lapsed / revoked 13Other 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 158 registered projects within 2 km.

Builder: Acme Housing India Private Limited

Acme Housing India Private Limited has 8 registrations on MahaRERA, including Alpinia and Oasis - Tower 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Alpinia is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Alpinia?

The registered promoter entity is Acme Housing India Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Alpinia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Alpinia?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Alpinia?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Alpinia?

The professionals named in the filing: Architect: SCAPES; Architect: Mandviwala Qutub and Associates; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Alpinia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Alpinia. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Alpinia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.