ALBIN DEVELOPERS
RG-MH-30091 · RERA P51700030834 · Last updated on MahaRERA portal: 23 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ALBIN DEVELOPERS is a Residential / Group Housing project by ALBIN ANTHONY CHEYADEN in Thane, Maharashtra, registered with MahaRERA as P51700030834 on 20 Sep 2021. Possession was promised by 15 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameALBIN DEVELOPERS
- TypeResidential / Group Housing
- Location
- KAMBA ROAD
- KAMBA
- Kalyan
- Thane
- 421306
- Pincode421306
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700030834
- ReraGenie IDRG-MH-30091
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Sep 2021
- Promised completion15 Jun 2025
- Revised completionRevised to 15 Jun 2025 (originally 15 Jun 2024)
- Buildings1 building record
- Documents filed64 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SWEET HOMES | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.
SWEET HOMES: 81% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 97% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Progress on shared amenities15
As on 23 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| ALBIN ANTHONY CHEYADEN | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to unavoidable circumstances beyond our control & Fund crisis due to slow sales,I was unable to complete project within stipulated time as there was slack in sales and recoveries from existing customers.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12603961 | SANTOSH MAHADEV INGALE | ALBIN ANTHONY CHEYADEN | 26/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Sep 2021
Documents filed64
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 23 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 23 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 Sweet home.pdf | 23 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 Sweet home.pdf | 23 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 23 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 23 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Pro Disclosure.pdf | 23 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Pro Disclosure.pdf | 23 Jun 2025 |
| Declaration in FORM BFile: notarised Form B.pdf | 7 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect.pdf | 26 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect.pdf | 26 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer.pdf | 26 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer.pdf | 26 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE_31 MARCH 2023.pdf | 26 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE_31 MARCH 2024.pdf | 26 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Audit Report- 2023-24-signed.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect- Annexure A 31-Mar-2023.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A 31-Dec-2022.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect- Annexure A 30-Sep-2022.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A 30-June-2022.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q4 23-24 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Q2-2024-25 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Q1-2024-25 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 23-24 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q2 23-24 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q1 22-23 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q2 22-23 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 22-23 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q4 22-23 SIGNED.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 -2023-24.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q2 -2023-24 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q4 -2023-24 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q3 -2023-24 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q1 -2023-24 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q1 -2022-23 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q2 -2022-23 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q3 -2022-23 SH.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Q4 -2022-23 SH.pdf | 23 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Pro Disclosuresigned.pdf | 23 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Audit Report-Signed.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 11 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SH.pdf | 11 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 signed.pdf | 11 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FINAL.pdf | 11 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FINAL.pdf | 11 Feb 2023 |
| Layout approvalFile: 4COPY OF LAYOUT.pdf | 18 Sep 2021 |
| Building plan approvalFile: 5BUILDING LAYOUT.pdf | 18 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: 4COPY OF LAYOUT.pdf | 18 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 5BUILDING LAYOUT.pdf | 18 Sep 2021 |
| Declaration about Commencement CertificateFile: 6Declaration about commencement certificate format D.pdf | 18 Sep 2021 |
| Declaration in FORM BFile: 8Declaration in FORM B.pdf | 18 Sep 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20 PERFORMA ALLOTMENT LETTER.pdf | 18 Sep 2021 |
| PAN CardFile: 1PAN CARD.pdf | 12 Jul 2021 |
| Copy of the legal title reportFile: 2FORMAT A LEGAL TITAL REPORT.pdf | 12 Jul 2021 |
| Details of encumbrancesFile: 3No encubersement certificate.pdf | 12 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CONSTRUCTION APPORVAL_compressed.pdf | 12 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9FORM 1 ARCHITECH CERTIFICATE.pdf | 12 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10FORM 2 Engineer.pdf | 12 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11FORM 3 FINAL.pdf | 12 Jul 2021 |
| Proforma of Allotment letterFile: 19DRAFT sale AGREEMENT.pdf | 12 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 64 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ALBIN DEVELOPERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KAMBA7,600+ in Thane
Kohinoor Eden
KGI REALTY PRIVATE LIMITED
Olympia City Phase 1
Balaji Rattan Lifespaces
Krishna Trident
Sonawane Infrastructure Private Limited
Rai s Heaven
RAI RESIDENCY Private Limited
Metro Grande Tower C and D
West Pioneer Properties India Pvt Ltd
SEASON SAHARA BUILDING NO 4 AND 5
SAMARTH SAI BUILDERS & DEVELOPERS
See every Thane project, with the district possession charts
Builder: ALBIN ANTHONY CHEYADEN
ALBIN ANTHONY CHEYADEN has 2 registrations on MahaRERA, including ALBIN DEVELOPERS and SWEET HOME LUXURIA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that ALBIN DEVELOPERS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ALBIN DEVELOPERS is delayed beyond 15 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ALBIN DEVELOPERS?
The registered promoter entity is ALBIN ANTHONY CHEYADEN, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ALBIN DEVELOPERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ALBIN DEVELOPERS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ALBIN DEVELOPERS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in ALBIN DEVELOPERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback