Home / Browse projects / Thane, Maharashtra / AL-QUDDUS RESIDENCY

Registered No litigation declared Residential / Group Housing project

AL-QUDDUS RESIDENCY

By ALLIANCE REALTY

RG-MH-53579 · RERA P51700009468 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 84 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 84 months from the original
5 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 90%
38 of 61Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

AL-QUDDUS RESIDENCY is a Residential / Group Housing project by ALLIANCE REALTY in Thane, Maharashtra, registered with MahaRERA as P51700009468 on 22 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 84 months from the original filing. 23 of the 61 units on this registration are recorded sold or booked, and 5 of 22 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameAL-QUDDUS RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • THANE
    • Thane (M Corp.)
    • 400612
  • Pincode400612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700009468
  • ReraGenie IDRG-MH-53579

Builder

  • NameALLIANCE REALTY
  • Entity typePartnership
  • PartnerAAMIR MIRZA

Key dates

this monthRegisteredAug 2017First promiseJun 2020Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2020)
  • Buildings2 building records
  • Documents filed64 files

Current status

38%23 of 61 units booked
86.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AL-QUDDUS RESIDENCY ANA9021021
AL-QUDDUS RESIDENCY BNA9040040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 90%.

AL-QUDDUS RESIDENCY A56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
AL-QUDDUS RESIDENCY B55%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
AL-QUDDUS RESIDENCY A11
AL-QUDDUS RESIDENCY B11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NADIA ZAHID SHAIKHThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityTHANE MUNICIPAL CORPORATION
Permissible FSI3986.0
Proposed, not sanctioned1,883 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKAUSA MUMBRA
Estimated costRs 13.21 cr
Cost incurredRs 11.36 cr
Work done86.0%
BuildingWingEstimatedIncurred
AL-QUDDUS RESIDENCY ANARs 6.48 crRs 5.57 cr
AL-QUDDUS RESIDENCY BNARs 6.48 crRs 5.57 cr
-NARs 25.00 lakhRs 21.50 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINAY PATIL& ASSOCIATES
EngineerVINAYAK CHOPDEKAR
Chartered AccountantHEENA NADEEM PAWASKAR
Chartered AccountantHADFA & CO
PartnerRole in project
ALLIANCE REALTY-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700012308Jun 2020 → Jun 2023

Reason as filed by the promoterDue to lockdown situation in the country the cash flow was very low from the customer and also Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly grant us an extension upto 30/06/2023.

EXT51700002533Jun 2020 → Jun 2021

Reason as filed by the promoterDear Sir/Madam, Work is slow due to some Statutory permissions are to be obtained, which is in the process. Kindly grant us extension we will complete the project in the extended time.

EXT51700016864Jun 2020 → Jun 2024

Reason as filed by the promoterStatutory permissions/clearances from various authorities are pending.

EA15052501131Jun 2020 → Jun 2027

Reason as filed by the promoterWork is slow due to some Statutory permissions are to be obtained, which is in the process. Kindly grant us extension we will complete the project in the extended time.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000195225Zaheer Dawood ArzabegiMr. Mirza Aamir Baig30/12/2020
CC12503762Abu Fahim Abu Hakim ShaikhALLIANCE REALTY28/10/2025
CC12504420Mehboob Zikri KhanALLIANCE REALTY11/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1 Q1 26-27.pdf20 Jul 2026
Withdrawal Update Form 2File: form 2 Q1 26-27.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM 3 Q1 Signed.pdf20 Jul 2026
Withdrawal Update Form 1File: Aamir Bhai Alliance Realty RERA - July 2026.pdf16 Jul 2026
Withdrawal Update Form 2File: Scan_20260714_181914.pdf16 Jul 2026
Withdrawal Update Form 3File: FORM 3 Q1 Signed.pdf16 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf5 Jun 2026
Withdrawal Update Form 1File: FORM 1.pdf5 Jun 2026
Withdrawal Update Form 1File: FORM 1.pdf5 Jun 2026
Withdrawal Update Form 1File: FORM 1.pdf5 Jun 2026
Withdrawal Update Form 2File: FORM 2_compressed.pdf5 Jun 2026
Withdrawal Update Form 2File: FORM 2_compressed.pdf5 Jun 2026
Withdrawal Update Form 2File: FORM 2_compressed.pdf5 Jun 2026
Withdrawal Update Form 2File: FORM 2_compressed.pdf5 Jun 2026
Withdrawal Update Form 3File: RERA FORM 3.pdf5 Jun 2026
Withdrawal Update Form 3File: RERA FORM 3.pdf5 Jun 2026
Withdrawal Update Form 3File: RERA FORM 3.pdf5 Jun 2026
Withdrawal Update Form 3File: RERA FORM 3.pdf5 Jun 2026
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf17 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 SIgn.pdf14 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Circular 29 A Wing Signed.pdf6 Feb 2025
Disclosure of sold/ booked inventoryFile: circular 29 B wing signed.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Adobe Scan Oct 24, 2024 (2).pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_COMP.pdf13 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf13 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a.pdf31 Jul 2024
Disclosure of sold/ booked inventoryFile: circular 29 signed.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: Circular 29 A Wing Signed.pdf7 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf27 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2a.pdf26 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf28 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf28 Jun 2023
Layout approvalFile: Blueprint.pdf15 Jun 2023
Building plan approvalFile: Blueprint.pdf15 Jun 2023
Copy of Layout Approval (in case of layout)File: Blueprint.pdf15 Jun 2023
Building Plan Approval (IOD)File: Blueprint.pdf15 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Alliance CC.pdf15 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.pdf25 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Alliance Rera audit 19-20.pdf25 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Alliance Rera audit 20 - 21.pdf25 Aug 2022
Declaration about Commencement CertificateFile: alliance format D.pdf24 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Alliance Form 2A.pdf24 Aug 2022
Disclosure of sold/ booked inventoryFile: Alliance circular 29 A wing.pdf24 Aug 2022
Disclosure of sold/ booked inventoryFile: Alliance Circular 29 B wing.pdf24 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DocScanner Jul 15, 2022 9-33 PM.pdf23 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf14 Aug 2021
Certificates of CA (Form 5)File: FORM 5.pdf28 Sep 2019
Certificates of CA (Form 5)File: FORM 5.pdf5 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: alliance CC (2).pdf16 May 2018
OtherFile: Plinth certificate.pdf16 May 2018
Layout approvalFile: blue print.pdf29 Jul 2017
Building plan approvalFile: blue print.pdf29 Jul 2017
PAN CardFile: Alliance PAN.pdf29 Jul 2017
Copy of the legal title reportFile: title certificate (1).pdf29 Jul 2017
Details of encumbrancesFile: encumbrances.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: blue print.pdf29 Jul 2017
Building Plan Approval (IOD)File: blue print.pdf29 Jul 2017
Declaration in FORM BFile: form B partners.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: alliance form 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf29 Jul 2017
Certificates of CA (Form 3)File: form 3.pdf29 Jul 2017
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf29 Jul 2017

How this compares with Thane

38%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 84 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AL-QUDDUS RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane (M Corp.)7,600+ in Thane

2 kmAL-QUDDUS RESIDENCYCompleted 34Lapsed / revoked 22Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 111 registered projects within 2 km.

Builder: ALLIANCE REALTY

ALLIANCE REALTY has 1 registration on MahaRERA, including AL-QUDDUS RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if AL-QUDDUS RESIDENCY is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AL-QUDDUS RESIDENCY?

The registered promoter entity is ALLIANCE REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AL-QUDDUS RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AL-QUDDUS RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AL-QUDDUS RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AL-QUDDUS RESIDENCY?

The professionals named in the filing: Architect: VINAY PATIL& ASSOCIATES; Engineer: VINAYAK CHOPDEKAR; Chartered Accountant: HEENA NADEEM PAWASKAR; Chartered Accountant: HADFA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AL-QUDDUS RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AL-QUDDUS RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AL-QUDDUS RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.