Home / Browse projects / AMEX RESIDENCY
AMEX RESIDENCY
RG-MH-56817 · RERA P51900009319 · Last updated on MahaRERA portal: 28 Mar 2025
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMEX RESIDENCY is a Others project by AMEX DEVELOPERS PVT. LTD., in 400009, registered with MahaRERA as P51900009319 on 22 Aug 2017. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 0 of the 80 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameAMEX RESIDENCY
- TypeOthers
- Location
- Ward ABCD
- 400009
- Pincode400009
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900009319
- ReraGenie IDRG-MH-56817
Builder
- NameAMEX DEVELOPERS PVT. LTD.,
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on22 Aug 2017
- Promised completion30 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed67 files
Current status
Figures as on 28 Mar 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AMEX RESIDENCY | NA | 25 | 21 | 64 | 16 | 80 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 60%.
AMEX RESIDENCY: 47% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJPURKAR ASSOCIATES |
| Chartered Accountant | A K Yadav and Associates |
| Partner | Role in project |
|---|---|
| AMEX DEVELOPERS PVT. LTD., | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000044208 | KUNAL PARMAR | Amex developer | 21/04/2018 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed67
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Discolsure March 2022.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure March 2023.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure March 2024.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure June 2024.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure Sept 2024.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure december 2024.pdf | 28 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 DATED 31122024.pdf | 8 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 DATED 30092024.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 30-06-2024_compressed.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-12-2024_compressed.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 30-09-2024_compressed.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2024.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2023.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2022.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2021.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2020.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2019_compressed.pdf | 8 Mar 2025 |
| Certificates of CA (Form 3)File: CA FROM -3 DATED 31-03-2018_compressed.pdf | 8 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 30062024.pdf | 8 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 30092024.pdf | 8 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31122024.pdf | 8 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Form-5 2021_22.pdf | 8 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA Form-5 2022_23.pdf | 8 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form-5 2023_ 24.pdf | 8 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 DATED 31032023.pdf | 5 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 DATED 31032024.pdf | 5 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 DATED 30062024.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032018.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032019.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032020.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032021.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032022.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032023.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEER CERTIFICATE 31032024.pdf | 5 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM- 2A FINANCIAL YEAR 2019 -2020.pdf | 5 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM- 2A FINANCIAL YEAR 2020 -2021.pdf | 5 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM- 2A FINANCIAL YEAR 2021 -2022.pdf | 5 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM- 2A FINANCIAL YEAR 2022 -2023.pdf | 5 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM- 2A FINANCIAL YEAR 2023-2024.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 ( 2018 - 2019).pdf | 6 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM -5 ( 2019 - 2020 ).pdf | 6 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM -5 ( 2020-2021 ).pdf | 6 Apr 2023 |
| Certificates of CA (Form 5)File: amex rera form CA.pdf | 24 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf | 5 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation .pdf | 5 Apr 2018 |
| Layout approvalFile: amex iod 3.pdf | 31 Jul 2017 |
| Layout approvalFile: amex iod 4.pdf | 31 Jul 2017 |
| Layout approvalFile: amex iod 5.pdf | 31 Jul 2017 |
| Layout approvalFile: amex iod 6.pdf | 31 Jul 2017 |
| Layout approvalFile: amex iod 1.pdf | 31 Jul 2017 |
| Layout approvalFile: amex iod 2.pdf | 31 Jul 2017 |
| Building plan approvalFile: iod amex.pdf | 31 Jul 2017 |
| PAN CardFile: PAN card .pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: K4 title certificate.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: DRAFT SALE AGREEMENT.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: amex iod 1.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: amex iod 2.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: amex iod 3.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: amex iod 4.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: amex iod 5.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: amex iod 6.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: iod amex.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: form B amex.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AMEX ARCHITECT CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Amex.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: DRAFT SALE AGREEMENT.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 67 filed documents as one ZIP, foldered, with a manifest
Keep AMEX RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near this project
Filed coordinates, straight-line distance. 12 registered projects within 2 km.
AL AMIR APARTMENT
JANZEB AMIRKAMAL KHAN
AL MEHDI HEIGHTS
AL HAADI DEVELOPERS
Sauda Heights - Phase II
MK India Enterprises
21, Baugh-E-Hasnain
Amex Developers Private Limited
Aqdas Residency
M/s. Alamdar Kapde Developer
HASAN ALI
Citymaker Builders Private Limited
Builder: AMEX DEVELOPERS PVT. LTD.,
AMEX DEVELOPERS PVT. LTD., has 1 registration on MahaRERA, including AMEX RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that AMEX RESIDENCY shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if AMEX RESIDENCY is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMEX RESIDENCY?
The registered promoter entity is AMEX DEVELOPERS PVT. LTD.,, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMEX RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMEX RESIDENCY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AMEX RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMEX RESIDENCY?
The professionals named in the filing: Architect: RAJPURKAR ASSOCIATES; Chartered Accountant: A K Yadav and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMEX RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback