ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / AKAR RAJASHRI SANKUL

Completed No litigation declared Residential / Group Housing project

AKAR RAJASHRI SANKUL

By AKAR INFRASTRUCTURE

RG-MH-85844 · RERA P52800034762 · Last updated on MahaRERA portal: 24 Dec 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0 of 15Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

AKAR RAJASHRI SANKUL is a Residential / Group Housing project by AKAR INFRASTRUCTURE in Ratnagiri, Maharashtra, registered with MahaRERA as P52800034762 on 28 Apr 2022. The registration is recorded completed; possession was promised by 28 Sep 2028. 15 of the 15 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameAKAR RAJASHRI SANKUL
  • TypeResidential / Group Housing
  • Location
    • SHIVAJI NAGAR
    • NACHANE MUN.IN
    • Nachane (CT)
    • Ratnagiri
    • 415612
  • Pincode415612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800034762
  • ReraGenie IDRG-MH-85844

Builder

  • NameAKAR INFRASTRUCTURE
  • Entity typePartnership
  • GSTIN27ABHFA3858L1Z0
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersNITYANAND RAVINDRA BHUTE, VIRENDRA VISHNU VANAJU
  • Other registrations6 more →
  • Completed4 of 7
  • Declared earlier projects3 →

Key dates

this monthRegisteredApr 2022PromisedSep 2028Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Apr 2022
  • Promised completion28 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed46 files

Current status

100%15 of 15 units booked

Figures as on 24 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AKAR RAJASHRI SANKULNA8515015

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

AKAR RAJASHRI SANKUL: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered1
Open Space8

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area964 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
RAJANISH RAMAKANT MAHAGAONKARNachane (CT)Ratnagiri
VIRENDRA VISHNU VANAJUNachane (CT)Ratnagiri
NITYANAND RAVINDRA BHUTEZadgaon CTRatnagiri
RAJASHRI RAMAKANT MAHAGAONKARNachane (CT)Ratnagiri

Approvals and building plan

Sanctioning authorityRATNAGIR MUNCIPL COUNCIL
Permissible FSI1680.55
Proposed, not sanctioned1 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch RATNAGIRI

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND YADAV
EngineerMANOJ JOSHI
Chartered AccountantANTHONY RAJSHEKHAR & CO
Chartered AccountantMASH & ASSOCIATES
Chartered AccountantSATYAROOP & CO
PartnerRole in project
AKAR INFRASTRUCTURE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Oct 2024

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: rajshri sankul_11zon.pdf24 Dec 2025
Occupational CertificateFile: bcc verification.pdf24 Jun 2025
Occupational CertificateFile: 6-12-23_11zon.pdf23 Jun 2025
Occupational CertificateFile: 6-12-23-1_11zon.pdf23 Jun 2025
Occupational CertificateFile: 24-5-24_11zon.pdf23 Jun 2025
Occupational CertificateFile: 24-5-24-1_11zon.pdf23 Jun 2025
Occupational CertificateFile: 30-8-24_11zon.pdf23 Jun 2025
Occupational CertificateFile: FORM 4 ARC RAJASHRI.pdf23 Jun 2025
Form 5 (FY 2022-2023)File: FORM 5 22-23.pdf19 Jun 2025
Form 1File: FORM -1 MARCH 25.pdf28 May 2025
Form 2File: Form -2 -March 2025.pdf28 May 2025
Form 3File: FORM 3 March 2025 akar rajashri (1)_11zon.pdf28 May 2025
Form 1File: FORM 1 ARC CERTIFICATE DEC2024.pdf23 May 2025
Form 2File: Engineer certificate DEC24.pdf23 May 2025
Form 3File: rajastri sankul form 3 up to dec24.pdf23 May 2025
Form 5 (FY 2023-2024)File: form -5 23-24.pdf19 May 2025
Occupational CertificateFile: 3 rd completion .pdf19 May 2025
Occupational CertificateFile: bcc rajashri sankul 2ND.pdf19 May 2025
Occupational CertificateFile: rajashri first completion.pdf19 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rajastri sankul form 3 up to dec24.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARC CERTIFICATE DEC2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate DEC24.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Document 328.pdf23 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 3 rd completion .pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: akar rajashri sankul form 5.pdf8 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: rajashri first completion.pdf8 Feb 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY FORMATION.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE.pdf19 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: PERMISSION 1.pdf6 Apr 2022
Proforma of Allotment letterFile: allotment letter.pdf1 Apr 2022
Proforma of Allotment letterFile: allotment letter.pdf1 Apr 2022
Declaration in FORM BFile: DECLRATION B form.pdf31 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate .pdf31 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate .pdf31 Mar 2022
Layout approvalFile: SHIVAJI NAGAR-RERA.pdf30 Mar 2022
Layout approvalFile: SHIVAJI NAGAR-RERA.pdf30 Mar 2022
Copy of the legal title reportFile: SEARCH REPORT.pdf30 Mar 2022
Details of encumbrancesFile: ENCUMBRANCES.pdf30 Mar 2022
Copy of Layout Approval (in case of layout)File: SHIVAJI NAGAR-RERA.pdf30 Mar 2022
Copy of Layout Approval (in case of layout)File: SHIVAJI NAGAR-RERA.pdf30 Mar 2022
Declaration about Commencement CertificateFile: DECLARATION ABT commencement CERTIFICATE.pdf30 Mar 2022
PAN CardFile: Document 43.pdf1 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: building permisn.pdf1 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200231344584_For_Asset_Based_Search_28_02_2022_20_38_45_180.pdf1 Mar 2022
Building plan approvalFile: SHIVAJI NAGAR-RERA.pdf22 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: SHIVAJI NAGAR-RERA.pdf22 Feb 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AKAR VISHWA PHASE 2P52800016360BEHIND CHIRAYU HOSPITAL, Ratnagiri25May 2018CompletedMay 2024Aug 2023
AKAR SWAROOPP52800018675BEHIND BANK OF INDIA, Ratnagiri13Nov 2018CompletedJan 2024Mar 2021
AKAR VISHWA PHASE 1P52800011556BEHIND CHIRAYU HOSPITAL, Ratnagiri24Aug 2017CompletedOct 2020Feb 2019

How this compares with Ratnagiri

100%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep AKAR RAJASHRI SANKUL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NACHANE MUN.IN1,100+ in Ratnagiri

2 kmAKAR RAJASHRI SANKULCompleted 52Lapsed / revoked 14Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 102 registered projects within 2 km.

Builder: AKAR INFRASTRUCTURE

AKAR INFRASTRUCTURE has 7 registrations on MahaRERA, including AKAR VISHWA PHASE 1 and AKAR VISHWA PHASE 2. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if AKAR RAJASHRI SANKUL is delayed beyond 28 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AKAR RAJASHRI SANKUL?

The registered promoter entity is AKAR INFRASTRUCTURE, a partnership as per the filing. Its GSTIN 27ABHFA3858L1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AKAR RAJASHRI SANKUL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AKAR RAJASHRI SANKUL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AKAR RAJASHRI SANKUL?

The professionals named in the filing: Architect: MILIND YADAV; Engineer: MANOJ JOSHI; Chartered Accountant: ANTHONY RAJSHEKHAR & CO; Chartered Accountant: MASH & ASSOCIATES; Chartered Accountant: SATYAROOP & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKAR RAJASHRI SANKUL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKAR RAJASHRI SANKUL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKAR RAJASHRI SANKUL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.