Home / Browse projects / Ratnagiri, Maharashtra / AKAR-ANAND VIHAR
AKAR-ANAND VIHAR
RG-MH-65494 · RERA P52800035144 · Last updated on MahaRERA portal: 8 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 3 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AKAR-ANAND VIHAR is a Residential / Group Housing project by AKAR INFRASTRUCTURE in Ratnagiri, Maharashtra, registered with MahaRERA as P52800035144 on 10 May 2022. Possession is promised by 23 Apr 2030. 55 of the 71 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameAKAR-ANAND VIHAR
- TypeResidential / Group Housing
- Location
- POLICE LINE ROAD
- OPPOSITE GST OFFICE
- Zadgaon CT
- Ratnagiri
- 415612
- Pincode415612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52800035144
- ReraGenie IDRG-MH-65494
Builder
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 May 2022
- Promised completion23 Apr 2030
- Revised completionNone
- Buildings1 building record
- Documents filed92 files
Current status
Figures as on 8 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AKAR- ANAND VIHAR | NA | 9 | 7 | 71 | 0 | 71 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.
AKAR- ANAND VIHAR: 81% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| AKAR- ANAND VIHAR | NA | Rs 15.87 cr | Rs 11.80 cr |
| - | NA | Rs 45.00 lakh | Rs 45.00 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ABHINAY JOGI |
| Engineer | MANOJ JOSHI |
| Engineer | NIKHIL DEEPAK WALAM |
| Chartered Accountant | ANTHONY RAJSHEKHAR & CO |
| Chartered Accountant | SATYAROOP & CO |
| Chartered Accountant | MASH & ASSOCIATES |
| Chartered Accountant | KARMARKAR NAIK & ASSOCIATES |
| Partner | Role in project |
|---|---|
| AKAR INFRASTRUCTURE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 23 Apr 2030
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2026-2027)File: 26-27.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 ANAND MARCH 26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: form 2 march 26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: akar anand vihar.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: form 1 anand vihar.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: form 2 dev25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: Anand Vihar form 3.pdf | 17 Jan 2026 |
| Form 5 (FY 2024-2025)File: form 5 anand vihar.pdf | 24 Dec 2025 |
| Withdrawal Update Form 1File: form 1 sept 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1 SEPT 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGI - SEPT 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGI - SEPT 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: FORM 3 SEPT 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: FORM 3 SEPT 25.pdf | 16 Oct 2025 |
| Withdrawal Update Form 1File: FORM -1 ANAND.pdf | 11 Jul 2025 |
| Withdrawal Update Form 2File: FORM 2 JUN 25 ANAND.pdf | 11 Jul 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 11 Jul 2025 |
| Form 1File: FORM- 1DEC-24.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 DEC 24.pdf | 18 Jun 2025 |
| Form 3File: Form -3 Dec-24.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory.pdf | 18 Jun 2025 |
| Form 1File: FORM-1 SEPT 24.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 SEPT 24.pdf | 18 Jun 2025 |
| Form 3File: FORM -3 SEPT- 24.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory sept -24.pdf | 18 Jun 2025 |
| Form 1File: FORM -1 JUN 24.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 JUN 24.pdf | 18 Jun 2025 |
| Form 3File: FORM -3 JUN 24.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: jun-24 inventory.pdf | 18 Jun 2025 |
| Form 1File: FORM-1 MARCH -24.pdf | 18 Jun 2025 |
| Form 2File: FORM-2 MARCH 24.pdf | 18 Jun 2025 |
| Form 3File: FORM-3 MARCH 24.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory.pdf | 18 Jun 2025 |
| Form 1File: FORM -1 DEC-23.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 DEC 23.pdf | 18 Jun 2025 |
| Form 3File: FORM 3 DEC-23.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Microsoft Winventory_.pdf | 18 Jun 2025 |
| Form 1File: FORM -1 SEPT 23.pdf | 18 Jun 2025 |
| Form 2File: FORM-2 SEPT-23.pdf | 18 Jun 2025 |
| Form 3File: FORM-2 SEPT-23.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory_.pdf | 18 Jun 2025 |
| Form 1File: FORM-1 JUN -23.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 JUN 23.pdf | 18 Jun 2025 |
| Form 3File: FORM 3 JUN 23.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory.pdf | 18 Jun 2025 |
| Form 1File: FORM-1 MARCH -23.pdf | 18 Jun 2025 |
| Form 2File: FORM-2 MARCH 23.pdf | 18 Jun 2025 |
| Form 3File: FORM -3 MARCH 23.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory.pdf | 18 Jun 2025 |
| Form 1File: FORM-1 DEC-22.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 DEC 22.pdf | 18 Jun 2025 |
| Form 3File: FORM -3 DEC-22.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory.pdf | 18 Jun 2025 |
| Form 1File: FORM-1 SEPT-22.pdf | 18 Jun 2025 |
| Form 2File: FORM -2 SEPT 22.pdf | 18 Jun 2025 |
| Form 3File: FORM-3 SEPT 22.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory sept22.pdf | 18 Jun 2025 |
| Form 1File: FORM -1 JUN 22.pdf | 18 Jun 2025 |
| Form 2File: FORM-2 JUN 22.pdf | 18 Jun 2025 |
| Form 3File: FORM -3 JUN 22.pdf | 18 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: inventory jun-22.pdf | 18 Jun 2025 |
| Form 2A (FY 2022-2023)File: 22-23.pdf | 7 Jun 2025 |
| Form 2A (FY 2023-2024)File: 23-24.pdf | 7 Jun 2025 |
| Form 2A (FY 2024-2025)File: 24-25.pdf | 7 Jun 2025 |
| Form 2A (FY 2025-2026)File: 25-26.pdf | 7 Jun 2025 |
| Form 5 (FY 2022-2023)File: FORM 5 22-23.pdf | 3 Jun 2025 |
| Form 1File: Form -1 march 25.pdf | 26 May 2025 |
| Form 2File: Form - 2 march -25.pdf | 26 May 2025 |
| Form 3File: form -3 march 25.pdf | 26 May 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 -23-24.pdf | 19 May 2025 |
| Building plan approvalFile: Revised Building permition.pdf | 14 Jun 2024 |
| Building plan approvalFile: AKAR ANAND VIHAR-1 .pdf | 14 Jun 2024 |
| Building plan approvalFile: AKAR ANAND VIHAR-2.pdf | 14 Jun 2024 |
| Building plan approvalFile: AKAR ANAND VIHAR-3.pdf | 14 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Revised Building permition.pdf | 14 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: AKAR ANAND VIHAR-1 .pdf | 14 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: AKAR ANAND VIHAR-2.pdf | 14 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: AKAR ANAND VIHAR-3.pdf | 14 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: akar anand vihar form 5.pdf | 8 Feb 2024 |
| Copy of the legal title reportFile: search report.pdf | 5 May 2022 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| AKAR VISHWA PHASE 2P52800016360 | BEHIND CHIRAYU HOSPITAL, Ratnagiri | 25 | May 2018 | Completed | May 2024 | Aug 2023 |
| AKAR SWAROOPP52800018675 | BEHIND BANK OF INDIA, Ratnagiri | 13 | Nov 2018 | Completed | Jan 2024 | Mar 2021 |
| AKAR VISHWA PHASE 1P52800011556 | BEHIND CHIRAYU HOSPITAL, Ratnagiri | 24 | Aug 2017 | Completed | Oct 2020 | Feb 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AKAR-ANAND VIHAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near OPPOSITE GST OFFICE1,100+ in Ratnagiri
Filed coordinates, straight-line distance. 99 registered projects within 2 km.
Navkar Enclave
Evergreen Associates
Kalpavriksha Heritage
Kalpavriksha Builders & Developers
LAXMI KEHSAV NAGAR PHASE II
DEEPAK YASHWANT SALVI
THE WIND
Arihant Vastu Nirman Pvt. Ltd
THE WOODLAND
Siddhivinayak Realty
AKAR VANAJU ESTATE
AKAR INFRASTRUCTURE
See every Ratnagiri project, with the district possession charts
Builder: AKAR INFRASTRUCTURE
AKAR INFRASTRUCTURE has 7 registrations on MahaRERA, including AKAR VISHWA PHASE 1 and AKAR VISHWA PHASE 2. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if AKAR-ANAND VIHAR is delayed beyond 23 Apr 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AKAR-ANAND VIHAR?
The registered promoter entity is AKAR INFRASTRUCTURE, a partnership as per the filing. Its GSTIN 27ABHFA3858L1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AKAR-ANAND VIHAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AKAR-ANAND VIHAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AKAR-ANAND VIHAR?
The professionals named in the filing: Architect: ABHINAY JOGI; Engineer: MANOJ JOSHI; Engineer: NIKHIL DEEPAK WALAM; Chartered Accountant: ANTHONY RAJSHEKHAR & CO; Chartered Accountant: SATYAROOP & CO; Chartered Accountant: MASH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AKAR-ANAND VIHAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback