Registered No litigation declared Commercial project

AISHWARYAM ONE MOSHI

By SAI ESSEN DEVELOPERS

RG-MH-68589 · RERA P52100053655 · Last updated on MahaRERA portal: 22 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 65%
187 of 246Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 147 documents Report an error

AISHWARYAM ONE MOSHI is a Commercial project by SAI ESSEN DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100053655 on 21 Nov 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 12 months from the original filing. 59 of the 246 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAISHWARYAM ONE MOSHI
  • TypeCommercial
  • Location
    • NEAR SNBP INTERNATIONAL SCHOOL
    • MOSHI
    • CHIKHALI
    • Haveli
    • Pune
    • 412114
  • Pincode412114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100053655
  • ReraGenie IDRG-MH-68589

Builder

  • NameSAI ESSEN DEVELOPERS
  • Entity typePartnership
  • GSTIN27ABRFS7781C1ZL
  • PartnersNITIN BHIMSEN AGARWAL, NARENDRA BHIMSEN AGARWAL, SATISH BHIMSEN AGARWAL, DEEPAK ASHOK MANE, SURENDRA BHIMSEN AGARWAL, ASHOK RAGHUNATH MANE
  • Other registrations7 more →
  • Completed4 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects6 →

Key dates

this monthRegisteredNov 2023First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Nov 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2026)
  • Buildings1 building record
  • Documents filed147 files

Current status

24%59 of 246 units booked
42.9%Work done, per cost certificate

Figures as on 22 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA1190246246

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 65%.

Building A: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1477

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,477
Closed/Covered1,477

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,500 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 May 2026

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI21600.0
Proposed, not sanctioned20,921 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO1 TO 6 ABHANG VISHWA PHASE2 GATE NO 1599 DEHU ALANDI ROAD CHIKHALI PIMPRI CHINCHWAD MAHARASHT
Estimated costRs 73.23 cr
Cost incurredRs 31.40 cr
Work done42.88%
BuildingWingEstimatedIncurred
Building ANARs 69.02 crRs 30.14 cr
-NARs 4.21 crRs 1.26 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAB Architects
Engineersneha sawant
EngineerAkshay Tambe
EngineerSTRUDCOM CONSULTANTS
Chartered AccountantOSWAL SOLANKI
Chartered AccountantOSWAL SOLANKI AND ASSOCIATES
Chartered AccountantSheetal Jindal
PartnerRole in project
SAI ESSEN DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100053655/WarDec 2026 → Apr 2027

Reason as filed by the promoterNA

EA22092638960Dec 2026 → Dec 2027

Reason as filed by the promoterRespected Sir/Madam, We, the promoters of the project Aishwaryam One Moshi, registered under Registration No. P52100053655, humbly submit this application seeking extension of the project registration. The registration of the said project is presently valid till 30/04/2027, and we request the Authority to kindly extend the validity till 31/12/2027 to enable completion of the balance work and procurement of the Occupation Certificate. I. Grounds for Seeking Extension 1. Labour Shortages Due to Bihar Elections in 2025 A significant portion of the project’s skilled and unskilled labour force orig

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12605215Parag Umakantrao PuranikSAI ESSEN DEVELOPERS16/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed147

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf22 Sep 2026
Form 5 (FY 2025-2026)File: Form 5.pdf10 Sep 2026
Withdrawal Update Form 1File: One Moshi June form 1.pdf17 Jul 2026
Withdrawal Update Form 2File: One Moshi June form 2.pdf17 Jul 2026
Withdrawal Update Form 3File: One Moshi June form 3.pdf17 Jul 2026
Layout approvalFile: Highlighted Layout.pdf13 Jul 2026
Withdrawal Update Form 1File: One Moshi form 1.pdf24 Apr 2026
Withdrawal Update Form 2File: One moshi form 2.pdf24 Apr 2026
Withdrawal Update Form 3File: One Moshi form 3 March.pdf24 Apr 2026
Building plan approvalFile: Sanctioned plan 2.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 3.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 4.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 5.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 6.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 7.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 8.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 9.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 10.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 11.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 12.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 13.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 14.pdf1 Apr 2026
Building plan approvalFile: Sanctioned plan 15.pdf1 Apr 2026
Form 2A (FY 2024-2025)File: form2a One Moshi.pdf17 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 one Moshi Signed.pdf13 Feb 2026
Withdrawal Update Form 1File: One Moshi form 1 dec.pdf8 Feb 2026
Withdrawal Update Form 1File: One Moshi form 1 dec.pdf8 Feb 2026
Withdrawal Update Form 2File: One moshi form 2 sep-25.pdf8 Feb 2026
Withdrawal Update Form 2File: One moshi form 2 Dec.pdf8 Feb 2026
Withdrawal Update Form 3File: One moshi form 3 Dec.pdf8 Feb 2026
Withdrawal Update Form 3File: One moshi form 3 Dec.pdf8 Feb 2026
Layout approvalFile: Layout.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 2.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 3.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 4.pdf12 Jan 2026
Layout approvalFile: Sanctioned plan 5.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 6.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 7.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 8.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 9.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 10.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 11.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 12.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 13.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 14.pdf12 Jan 2026
Building plan approvalFile: Sanctioned plan 15.pdf12 Jan 2026
Withdrawal Update Form 1File: One moshi form sep - 25.pdf25 Oct 2025
Withdrawal Update Form 2File: One moshi form 2 sep-25.pdf25 Oct 2025
Withdrawal Update Form 3File: One moshi form 3 september - 2025.pdf25 Oct 2025
Withdrawal Update Form 1File: One Moshi Form 1 June 25.pdf20 Oct 2025
Withdrawal Update Form 2File: One Moshi Form 2 June 25 RERA.pdf20 Oct 2025
Withdrawal Update Form 3File: One Moshi Form 3 June 25 (1).pdf20 Oct 2025
Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Aug 2025
Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Aug 2025
Form 3File: 6 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory.pdf19 Aug 2025
Form 1File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Aug 2025
Form 2File: 5 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Aug 2025
Form 3File: 5 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory.pdf19 Aug 2025
Form 1File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Aug 2025
Form 2File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Aug 2025
Form 3File: 4 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf19 Aug 2025
Form 1File: FORM 1 Q4 JAN-MARCH 2025 AISH ONE MOSHI.pdf18 Aug 2025
Form 2File: FORM 2 Q4 JAN-MARCH 2025 ONE MOSHI.pdf18 Aug 2025
Form 3File: FORM 3 JAN-MARCH 2025 ONE MOSHI.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY Q4- JAN-MARCH 2025 GAURAV ONE MOSHI.pdf18 Aug 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2025 ONE MOSHI.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JAN-MARCH 2025 ONE MOSHI.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q4 JAN-MARCH 2025 AISH ONE MOSHI.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q4 JAN-MARCH 2025 ONE MOSHI.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY Q4- JAN-MARCH 2025 GAURAV ONE MOSHI.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3 OCT-DEC 2024 ONE MOSHI.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 OCT-DEC 2024 ONE MOSHI.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 OCT-DEC 2024 ONE MOSHI.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold booked inventory ONE MOSHI.pdf20 Jan 2025
CERSAI detailsFile: CERSAI Search Report.pdf2 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AISH ONE MOSHI.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Aish one moshi.pdf19 Oct 2024

How this compares with Pune

24%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AISHWARYAM ONE MOSHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHIKHALI13,700+ in Pune

2 kmAISHWARYAM ONE MOSHICompleted 66Lapsed / revoked 40Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 171 registered projects within 2 km.

Builder: SAI ESSEN DEVELOPERS

SAI ESSEN DEVELOPERS has 8 registrations on MahaRERA, including AISHWARYAM HAMARA PHASE I and AISHWARYAM HAMARA PHASE II. Its filings disclose 6 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AISHWARYAM ONE MOSHI is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AISHWARYAM ONE MOSHI?

The registered promoter entity is SAI ESSEN DEVELOPERS, a partnership as per the filing. Its GSTIN 27ABRFS7781C1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AISHWARYAM ONE MOSHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AISHWARYAM ONE MOSHI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AISHWARYAM ONE MOSHI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AISHWARYAM ONE MOSHI?

The professionals named in the filing: Architect: AB Architects; Engineer: sneha sawant; Engineer: Akshay Tambe; Engineer: STRUDCOM CONSULTANTS; Chartered Accountant: OSWAL SOLANKI; Chartered Accountant: OSWAL SOLANKI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AISHWARYAM ONE MOSHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AISHWARYAM ONE MOSHI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AISHWARYAM ONE MOSHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.