Home / Browse projects / Pune, Maharashtra / Aishwaryam Hamara Abhimaan
Aishwaryam Hamara Abhimaan
RG-MH-04957 · RERA P52100020889 · Last updated on MahaRERA portal: 12 Jul 2024
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 22 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Aishwaryam Hamara Abhimaan is a Residential / Group Housing project by SAI ESSEN DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100020889 on 16 May 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date.
At a glance
Project
- NameAishwaryam Hamara Abhimaan
- TypeResidential / Group Housing
- Location
- Dehu Moshi road
- Moshi
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412114
- Pincode412114
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100020889
- ReraGenie IDRG-MH-04957
Builder
- NameSAI ESSEN DEVELOPERS
- Entity typePartnership
- GSTIN27ABRFS7781C1ZL
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersNITIN BHIMSEN AGARWAL, NARENDRA BHIMSEN AGARWAL, SATISH BHIMSEN AGARWAL, DEEPAK ASHOK MANE, SURENDRA BHIMSEN AGARWAL, ASHOK RAGHUNATH MANE
- Other registrations7 more →
- Completed4 of 8
- No longer live1 lapsed, de-registered or revoked
- Past their filed date1
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on16 May 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings4 building records
- Documents filed104 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 13 | 0 | 0 | 0 | 0 |
| B | NA | 14 | 0 | 0 | 0 | 0 |
| C | NA | 14 | 0 | 0 | 0 | 0 |
| D | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 12 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Basement (if any), at 0%.
A9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed540
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A | 68 | 61 | 129 |
| B | 74 | 67 | 141 |
| C | 74 | 67 | 141 |
| D | 67 | 62 | 129 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Mahendra Thakur |
| Engineer | SNEHA SAWANT |
| Partner | Role in project |
|---|---|
| SAI ESSEN DEVELOPERS | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 114/2018/2018 | Honorable civil judge junior division Pimpri Pune | ARGUMENT |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 May 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 May 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 May 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 May 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed104
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2019.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2019.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2019.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2019-20.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q 1 2020.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2020.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2020-21.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2021.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2021.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2021.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2021-22.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2022.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2022.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2022.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2022-23.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2023.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2023.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2023.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2023- 24.pdf | 12 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3 Q4 2023-24 compressed.pdf | 26 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2023- 24.pdf | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 2023- 24.pdf | 13 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-2023.pdf | 31 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN -31-12-2019.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-9-2019.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-6-2020.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-9-2020.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-3-2020.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-12-2020.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-6-2021.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-9-2021.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-3-2021.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-12-2021.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-6-2022.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-1-2022.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-12-2022.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-6-2023.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-30-9-2023.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-3-2023.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: ABHIMAN-31-12-2023.pdf | 29 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5-14-1-2024.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 2019-20.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 2020-21.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 2021-22.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 2022-23.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 2023.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 2023.pdf | 9 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 2023.pdf | 9 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 20 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13) Form 2 Q4 2021-22 30-03-2022 OK.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14) Form 2 Q1 2022 30-06-2022.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 16) Form 2 Q3 2022 30-12-2022.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 17) Form 2 Q4 2022-23 30-03-2023.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 18) Form 2 Q1 2023 30-06-2023 ok.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 19) Form 2 Q2 2023 30-09-2023.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20) Form 2 Q3 2023 30-12-2023.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 21) Form 2 Q2 2022 30-02-2022.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7) Form 1 Q 2 2020 25-9-2020.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8) Form 1 Q3 2020 21-12-2020.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9) Form 1 Q4 2021 26-03-2021.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10) Form 1 Q1 2021 28-06-2021.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11) Form 1 Q2 2021 28-09-2021.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12) Form 1 Q3 2021 25-12-2021.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13) Form 1 Q4 2022 26-03-2022.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14) Form 1 Q1 2022 26-06-2022.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15) Form 1 Q2 2022 25-09-2022.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 16) Form 1 Q3 2022 28-12-2022.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17) Form 1 Q4 2022-2023 27-03-2023.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 18) Form 1 Q1 2023 26-06-2023.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 19) Form 1 Q2 2023 27-09-2023.pdf | 14 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20) Form 1 Q3 2023 28-12-2023.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2) Form 2 Q1 2019 30-06-2019.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3) Form 2 Q2 2019 30-09-2019.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4) Form 2 Q3 2019 30-12-2019.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5)Form 2 Q4 2019-20 30-03-2020.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6) Form 2 Q1 30-06- 2020.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7) Form 2 Q2 2020 30-09-2020.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8) Form 2 Q3 2020 31-12-2020.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9) Form 2 Q4 2020-21 30-03-2021.pdf | 14 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10) Form 2 Q1 2021 30-06-2021.pdf | 14 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 104 filed documents as one ZIP, foldered, with a manifest
Keep Aishwaryam Hamara Abhimaan on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Moshi13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
Aishwaryam Anand
Sai Essen Developers
AISHWARYAM HAMARA ABHIMAAN
SAI ESSEN DEVELOPERS
AISHWARYAM HAMARA GAURAV
SAI ESSEN DEVELOPERS
VAASTU DREAMS III
SAI ESSEN 7 AND 8 LLP
AISHWARYAM COURTYARD GOLD
SAI ESSEN PROPERTIES
GANESH PARADISE PHASE 2
EKDANTA NEST LLP
Builder: SAI ESSEN DEVELOPERS
SAI ESSEN DEVELOPERS has 8 registrations on MahaRERA, including AISHWARYAM HAMARA PHASE I and AISHWARYAM HAMARA PHASE II. Its filings disclose 6 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Aishwaryam Hamara Abhimaan shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Aishwaryam Hamara Abhimaan is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Aishwaryam Hamara Abhimaan?
The registered promoter entity is SAI ESSEN DEVELOPERS, a partnership as per the filing. Its GSTIN 27ABRFS7781C1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Aishwaryam Hamara Abhimaan?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Aishwaryam Hamara Abhimaan?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Aishwaryam Hamara Abhimaan?
The professionals named in the filing: Architect: Ar Mahendra Thakur; Engineer: SNEHA SAWANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Aishwaryam Hamara Abhimaan?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.