ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Aishwarya Sadan Co-Op Housing Society Ltd.

Registered No litigation declared Residential / Group Housing project

Aishwarya Sadan Co-Op Housing Society Ltd.

By Nitant Narendra Desai

RG-MH-32554 · RERA PR1330002500844 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
3 of 9Construction stages donefurthest along: Slabs of Super Structure, 70%
53 of 55Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 14 documents Report an error

Aishwarya Sadan Co-Op Housing Society Ltd. is a Residential / Group Housing project by Nitant Narendra Desai in Thane, Maharashtra, registered with MahaRERA as PR1330002500844 on 19 Sep 2025. Possession is promised by 31 Dec 2028. 2 of the 55 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameAishwarya Sadan Co-Op Housing Society Ltd.
  • TypeResidential / Group Housing
  • Location
    • Belavli
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1330002500844
  • ReraGenie IDRG-MH-32554

Builder

  • NameNitant Narendra Desai
  • Entity typeIndividual
  • GSTIN27AEYPD8439C2Z4
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Sep 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed14 files

Current status

4%2 of 55 units booked
42.9%Work done, per cost certificate

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1NA8755055

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

1: 42% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNo0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed109

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots109
Stilt / Ground109

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area923 sq m
Land owned byNot the promoter
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jun 2025
LandownerVillageDistrict
Pascal Boaventure PinhoBadlapur (M Cl)Thane
Aishwarya Sadan CHSLBadlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Municipal Council
Permissible FSI3520.96
Proposed, not sanctioned2,905 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOTUS HOUSE SHOP NO 5-12 KATRAP ROAD BADLAPUR EAST
Estimated costRs 10.60 cr
Cost incurredRs 4.54 cr
Work done42.88%
BuildingWingEstimatedIncurred
1NARs 10.10 crRs 4.54 cr
-NARs 50.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSwastik Creation
EngineerKB Consultants
Chartered AccountantA Y Kale & Associates
Chartered AccountantCA Ashwini J Patil
PartnerRole in project
Nitant Narendra Desai-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalNot on the file

    The planning authority's approval of how the plots and buildings sit on the land.

  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 May 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed14

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf14 May 2026
Withdrawal Update Form 2File: Form 2.pdf14 May 2026
Withdrawal Update Form 3File: Form3 signed.pdf14 May 2026
Withdrawal Update Form 1File: Form 1.pdf12 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 31 12 25.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 31 12 25.pdf12 Mar 2026
Withdrawal Update Form 3File: From 3 311225.pdf12 Mar 2026
Withdrawal Update Form 3File: From 3 311225.pdf12 Mar 2026
Withdrawal Update Form 1File: Form 1 SSKD Aish.pdf11 Mar 2026
Withdrawal Update Form 2File: Form 2_Signed.pdf11 Mar 2026
Withdrawal Update Form 3File: Form 3 Signed.pdf11 Mar 2026
Declaration and undertaking (Annexure A)File: One land one project.pdf17 Jun 2025
Building plan approvalFile: Full Plan.pdf29 May 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
Yashshree Co.Op.Hsg.SocP51700034984-, ThaneApr 2022CompletedSep 2025May 2024

How this compares with Thane

4%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aishwarya Sadan Co-Op Housing Society Ltd. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Belavli7,600+ in Thane

2 kmAishwarya Sadan Co-Op HoCompleted 200Lapsed / revoked 79Other 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 407 registered projects within 2 km.

Builder: Nitant Narendra Desai

Nitant Narendra Desai has 2 registrations on MahaRERA, including Yashshree Co.Op.Hsg.Soc and Aishwarya Sadan Co-Op Housing Society Ltd.. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Aishwarya Sadan Co-Op Housing Society Ltd. is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aishwarya Sadan Co-Op Housing Society Ltd.?

The registered promoter entity is Nitant Narendra Desai, an individual as per the filing. Its GSTIN 27AEYPD8439C2Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aishwarya Sadan Co-Op Housing Society Ltd.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aishwarya Sadan Co-Op Housing Society Ltd.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aishwarya Sadan Co-Op Housing Society Ltd.?

The professionals named in the filing: Architect: Swastik Creation; Engineer: KB Consultants; Chartered Accountant: A Y Kale & Associates; Chartered Accountant: CA Ashwini J Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aishwarya Sadan Co-Op Housing Society Ltd.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aishwarya Sadan Co-Op Housing Society Ltd.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aishwarya Sadan Co-Op Housing Society Ltd. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.