ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / AISHWARYA REDEVELOPMENT PROJECT

Registration lapsed No litigation declared Residential / Group Housing project

AISHWARYA REDEVELOPMENT PROJECT

By BHS HOUSING PRIVATE LIMITED

RG-MH-93506 · RERA P51800012044 · Last updated on MahaRERA portal: 4 Nov 2017

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 99 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2018Possession promised99 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
1Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

AISHWARYA REDEVELOPMENT PROJECT is a Residential / Group Housing project by BHS HOUSING PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012044 on 1 Sep 2017. Possession was promised by 31 Jul 2018 and is now 99 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAISHWARYA REDEVELOPMENT PROJECT
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400076
  • Pincode400076
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012044
  • ReraGenie IDRG-MH-93506

Builder

  • NameBHS HOUSING PRIVATE LIMITED
  • Entity typeCompany

Key dates

99 months past promisethis monthRegisteredSep 2017PromisedJul 2018

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion31 Jul 2018
  • Revised completionNone
  • Buildings2 building records
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AISHWARYA - A WINGNA150000
AISHWARYA - B WINGNA210000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Nov 2017, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

AISHWARYA - A WING95%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
AISHWARYA - B WING98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities17

As on 4 Nov 2017, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
FITNESS CENTREYes100%
SOCIETY OFFICEYes100%

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,395 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4235.13
Proposed, not sanctioned3,483 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Ghanshyam Chambers, Plot No B-12, Link Road, Opp City Mall, Andheri West Mumbai 40005

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVSA Space Design Pvt Ltd
EngineerEpicon consultants Pvt. Ltd.
PartnerRole in project
BHS HOUSING PRIVATE LIMITED-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000193829BHS HOUSING PRIVATE LIMITEDMr. Sadique Elias Moulla01/09/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Proforma of Allotment letterFile: RERA Agreement 04 11 2017.pdf4 Nov 2017
Building plan approvalFile: Sanctioned Plan.pdf31 Jul 2017
Building plan approvalFile: Original IOD.pdf31 Jul 2017
Building plan approvalFile: Amended IOD.pdf31 Jul 2017
Layout approvalFile: Declaration for No Layout.pdf31 Jul 2017
PAN CardFile: PAN CARD BHS Housing.pdf31 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf31 Jul 2017
Details of encumbrancesFile: Declaration for Encumbrances.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Declaration for No Layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: Original IOD.pdf31 Jul 2017
Building Plan Approval (IOD)File: Amended IOD.pdf31 Jul 2017
Building Plan Approval (IOD)File: Sanctioned Plan.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Full CC.pdf31 Jul 2017
Declaration in FORM BFile: Form B Promoter.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Declaration for Non Furnishing of RERA Compliant Agreement for Sale and Allotment.pdf31 Jul 2017
OtherFile: Salient Features of Real Estate Project.pdf31 Jul 2017
OtherFile: Self Declaration fo No Co Promoter.pdf31 Jul 2017
OtherFile: Development Agreement I.pdf31 Jul 2017
OtherFile: Development Agreement II.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AISHWARYA REDEVELOPMENT PROJECT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmAISHWARYA REDEVELOPMENT Completed 21Lapsed / revoked 15Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: BHS HOUSING PRIVATE LIMITED

BHS HOUSING PRIVATE LIMITED has 1 registration on MahaRERA, including AISHWARYA REDEVELOPMENT PROJECT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that AISHWARYA REDEVELOPMENT PROJECT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AISHWARYA REDEVELOPMENT PROJECT is delayed beyond 31 Jul 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AISHWARYA REDEVELOPMENT PROJECT?

The registered promoter entity is BHS HOUSING PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AISHWARYA REDEVELOPMENT PROJECT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AISHWARYA REDEVELOPMENT PROJECT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AISHWARYA REDEVELOPMENT PROJECT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AISHWARYA REDEVELOPMENT PROJECT?

The professionals named in the filing: Architect: VSA Space Design Pvt Ltd; Engineer: Epicon consultants Pvt. Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AISHWARYA REDEVELOPMENT PROJECT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AISHWARYA REDEVELOPMENT PROJECT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AISHWARYA REDEVELOPMENT PROJECT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.