Home / Browse projects / Mumbai Suburban, Maharashtra / Aishwarya Height
Aishwarya Height
RG-MH-84094 · RERA P51800007856 · Last updated on MahaRERA portal: 9 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 48 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Aishwarya Height is a Others project by Shree Samruddhi Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007856 on 18 Aug 2017. Possession was promised by 29 Oct 2022 and is now 48 months past that date. The completion date has moved by 12 months from the original filing. 119 of the 122 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 8 complaints are on record with the regulator.
At a glance
Project
- NameAishwarya Height
- TypeOthers
- Location
- MULUND EAST
- MITHANAGAR
- Kurla
- Mumbai Suburban
- 400081
- Pincode400081
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007856
- ReraGenie IDRG-MH-84094
Builder
- NameShree Samruddhi Developers
- Entity typePartnership
- PartnersArchita Anil Pandit, Anil Gangadhar Pandit
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion29 Oct 2022
- Revised completionRevised to 29 Oct 2022 (originally 30 Oct 2021)
- Buildings1 building record
- Documents filed117 files
Current status
Figures as on 9 Jul 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Aishwarya Height | NA | 26 | 22 | 121 | 1 | 122 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 9 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.
Aishwarya Height: 43% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S S Associates |
| Engineer | Vinayak Chandorkar |
| Engineer | Saurabh Lalge |
| Chartered Accountant | Esha Ramesh Bhanushali |
| Partner | Role in project |
|---|---|
| Shree Samruddhi Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDELAY IN APPROVAL FOR GETTING SANCTION FOR APPROVAL
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000023944 | MRS. HEMALATA TAVADE | SHREE SAMRUDDHI DEVELOPERS | 03/04/2018 |
| CC006000000044063 | MR. ANIL MANE & MRS. AKSHADA MANE | SHREE SAMRUDDHI DEVELOPERS | 10/04/2018 |
| CC006000000056029 | Chandrashekhar L. Khanvilkar | Shree Samruddhi Developers | 31/08/2018 |
| CC006000000056123 | Mr. Anand Joshi | Shree Samruddhi Developers | 14/09/2018 |
| CC006000000195906 | NITIN BOMBLE | Anil Gangadhar Pandit | 11/02/2021 |
| CC006000000210225 | NILESH CHAFEKAR, HEMANGI CHAFEKAR | ANIL GANGADHAR PANDIT | 03/03/2022 |
| CC006000000303150 | Sheetal Ajit Thakkar | Shree Samruddhi Developers | 04/11/2022 |
| CC006000000303151 | Amita Bharat Thakkar | Shree Samruddhi Developers | 04/11/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jul 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Dec 2022
Documents filed117
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2018.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2019.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2020.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2021.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2022.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2023.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 2024.pdf | 9 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2 - 2023.pdf | 9 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM - 2 - 2024.pdf | 9 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 - CA CERTIFICATEAS ON 310318.pdf | 7 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 - CA CERTIFICATES AS ON 31032019.pdf | 7 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 - CA CERTIFICATES AS ON 31032020.pdf | 7 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 - CA CERTIFICATES AS ON 31032021 COMP.pdf | 7 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 - CA CERTIFICATES AS ON 31032022 COMP.pdf | 7 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 - CA CERTIFICATES AS ON 31032023.pdf | 7 Jul 2025 |
| Certificates of CA (Form 3)File: FORM - 3 -CA CERTIFICATES AS ON 31032024.pdf | 7 Jul 2025 |
| Details of encumbrancesFile: Encumbrence Finance.pdf | 5 Jul 2025 |
| Details of encumbrancesFile: Encumbrence Finance 2024.pdf | 5 Jul 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrence legal.pdf | 5 Jul 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrence legal 2024.pdf | 5 Jul 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: AISHWARYA HEIGTHS REGISTER CERTIFICATE.pdf | 5 Jul 2025 |
| Declaration about Commencement CertificateFile: Decleration on cc 1.pdf | 5 Jul 2025 |
| Declaration about Commencement CertificateFile: Decleration on cc 2.pdf | 5 Jul 2025 |
| Declaration about Commencement CertificateFile: Decleration on cc 3.pdf | 5 Jul 2025 |
| Declaration about Commencement CertificateFile: Decleration on cc 4.pdf | 5 Jul 2025 |
| CERSAI detailsFile: Cersai Declaration.pdf | 5 Jul 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Declaration format A old ac.pdf | 5 Jul 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Declaration format A new ac.pdf | 5 Jul 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.pdf | 5 Jul 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrence legal.pdf | 5 Jul 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrence legal 2024.pdf | 5 Jul 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation AFS.pdf | 5 Jul 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC CRETIFICATE UP TO 22 nd Floor original.pdf | 4 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 MARCH'2018.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 MARCH'2019.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - JUNE'2019.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 DEC'2019.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH'2020.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 JUNE'2020.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - SEP'2020.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - DEC'2020.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - MARCH'2021.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 JUNE'21.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - SEP'2021.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - DEC'2021.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - MARCH'2022.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 JUNE'2022.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - MARCH'2023.pdf | 24 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 MARCH'2024.pdf | 24 Jun 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: mulund OC.pdf | 16 Dec 2022 |
| Building plan approvalFile: IOD 22nd Floor.pdf | 22 Jul 2021 |
| Building Plan Approval (IOD)File: IOD 22nd Floor.pdf | 22 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: MULUND CC1.pdf | 8 Aug 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: MULUND CC1.pdf | 8 Aug 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: MULUND CC.pdf | 8 Aug 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: fruther cc copy.pdf | 28 Sep 2019 |
| Building plan approvalFile: iod samruddhi development.pdf | 5 Apr 2019 |
| Building plan approvalFile: iod plan 1.pdf | 5 Apr 2019 |
| Building plan approvalFile: iod plan 2.pdf | 5 Apr 2019 |
| Building plan approvalFile: iod plan 3.pdf | 5 Apr 2019 |
| Building plan approvalFile: iod plan 4.pdf | 5 Apr 2019 |
| Building Plan Approval (IOD)File: iod samruddhi development.pdf | 5 Apr 2019 |
| Building Plan Approval (IOD)File: iod plan 1.pdf | 5 Apr 2019 |
| Building Plan Approval (IOD)File: iod plan 2.pdf | 5 Apr 2019 |
| Building Plan Approval (IOD)File: iod plan 3.pdf | 5 Apr 2019 |
| Building Plan Approval (IOD)File: iod plan 4.pdf | 5 Apr 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC samrudhi developers.pdf | 5 Apr 2019 |
| Declaration in FORM BFile: FROM B NEW.pdf | 5 Apr 2019 |
| Declaration in FORM BFile: FROM B NEW1.pdf | 5 Apr 2019 |
| Declaration in FORM BFile: FROM B NEW2.pdf | 5 Apr 2019 |
| Building plan approvalFile: 1ST FLOOR PODIUM PLAN SALE IOA 16-04-2011.pdf | 31 Jul 2017 |
| Building plan approvalFile: ELEVATION PLAN SALE IOA 16-04-2011.pdf | 31 Jul 2017 |
| Building plan approvalFile: LAYOUT SALE IOA 16-04-2011.pdf | 31 Jul 2017 |
| Building plan approvalFile: TYPICALSALE IOA 16-04-2011.pdf | 31 Jul 2017 |
| Building plan approvalFile: SALE PLINTH CC SALE IOA.pdf | 31 Jul 2017 |
| Layout approvalFile: AMENDED APPLICATION PROPOSED WITH CFO NOC.pdf | 31 Jul 2017 |
| Layout approvalFile: GROUND FLOOR PROPOSED.pdf | 31 Jul 2017 |
| Layout approvalFile: 1ST 2ND PODIUM 3RD TO 23 TYPICAL 8TH 15TH REFUGE.pdf | 31 Jul 2017 |
| Layout approvalFile: 22ND REFUGE AND ELEVATION.pdf | 31 Jul 2017 |
| PAN CardFile: ssd pan.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 117 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Aishwarya Height on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MITHANAGAR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 294 registered projects within 2 km.
Ekvira and Saishakti
Magnaacasa Infrastructures and Realtors Pr
SENROOFS PHASE - III
PIONEER HOUSING
THE ALTEZZA
M/s. VIPL Varasiddhi Infra Project LLP
SUPREMO PHASE I SALVIA D WING
K V BUILDHOME LLP
SUPREMO PHASE II, WING C known as SAKURA
K V BUILDHOME LLP
Aveza Phase 2
Tata Housing Development Company Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Shree Samruddhi Developers
Shree Samruddhi Developers has 1 registration on MahaRERA, including Aishwarya Height. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Aishwarya Height shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Aishwarya Height is delayed beyond 29 Oct 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Aishwarya Height?
The registered promoter entity is Shree Samruddhi Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Aishwarya Height?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Aishwarya Height?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Aishwarya Height?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Aishwarya Height?
The professionals named in the filing: Architect: S S Associates; Engineer: Vinayak Chandorkar; Engineer: Saurabh Lalge; Chartered Accountant: Esha Ramesh Bhanushali. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Aishwarya Height?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback