Home / Browse projects / Pune, Maharashtra / ADITYA VARDHAN HEIGHTS

Registered No litigation declared Residential / Group Housing project

ADITYA VARDHAN HEIGHTS

By SHREE GANESH DEVELOPERS

RG-MH-26700 · RERA P52100015460 · Last updated on MahaRERA portal: 17 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 84 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 84 months from the original
10 of 33Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 95%
0Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

ADITYA VARDHAN HEIGHTS is a Residential / Group Housing project by SHREE GANESH DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100015460 on 27 Feb 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 84 months from the original filing.

At a glance

Project

  • NameADITYA VARDHAN HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • WADGAON
    • Wadagaon (CT)
    • Mawal
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015460
  • ReraGenie IDRG-MH-26700

Builder

  • NameSHREE GANESH DEVELOPERS
  • Entity typePartnership
  • PartnerPRADEEP VASANTRAO CHAVAN
  • Other registrations23 more →
  • Completed9 of 24
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2018First promiseDec 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Feb 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2019)
  • Buildings3 building records
  • Documents filed123 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA100000
BUILDING BNA60000
AMENITIES BUILDINGNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 17 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 95%.

BUILDING A77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
BUILDING B17%
ActivityProgress
Excavation100%
Basement (if any)35%
Podiums (if any)0%
Plinth35%
Stilt Floor15%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
AMENITIES BUILDING84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 17 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes10%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes25%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes55%

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Open Space31
BuildingOpen SpaceTotal
BUILDING A3030
BUILDING B11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,961 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAIN BAZAR DEHUROAD

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
SHREE GANESH DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010518Dec 2019 → Dec 2022

Reason as filed by the promoterDUE TO COVID 19 PANDEMIC THE WORK OF BUILDING NOT COMPLETED AND BECAUSE OF LOCKDWON THE PROJECT WORKS INCOMPLETE

EXT52100005654Dec 2019 → Dec 2020

Reason as filed by the promoterWE REQUEST YOU TO KINDLY GIVE EXTENSION FOR OUR RERA CERTIFICATE FOR ONE YEAR UPTO 31/12/2020 SINCE OUR PROJECT COMPLETED 70% WE REQUIRED ONE YEAR FOR COMPLETING WORK AND OTHER FORMALITIES AT ADITYA VARADHAN HEIGHTS

EXT52100025596Dec 2019 → Dec 2026

Reason as filed by the promoterWe hereby apply the extension u/s 7(3) of the project bearing vide No. P521000015460 As prescribed under circular no. 07/2019 dated 8 Feb 2019 the consent of 51% of the allotees is enclosed herewith.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: As on June 21.pdf17 Mar 2025
Certificates of CA (Form 3)File: As on sept 2021.pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 DEC 2021.pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 MARCH 2022.pdf17 Mar 2025
Certificates of CA (Form 3)File: form 3 june 2022.pdf17 Mar 2025
Certificates of CA (Form 3)File: form 3 september 2022.pdf17 Mar 2025
Certificates of CA (Form 3)File: form 3 june 2022.pdf17 Mar 2025
Certificates of CA (Form 3)File: form 3 december 2022.pdf17 Mar 2025
Certificates of CA (Form 3)File: DEC 2023_11zon.pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 JUNE 2023_11zon.pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 MARCH 2024_11zon.pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 SEPT 2023_11zon.pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 JUNE 2024 (1).pdf17 Mar 2025
Certificates of CA (Form 3)File: FORM 3 SEPT 2024.pdf17 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 22.pdf15 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 23.pdf15 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 24.pdf15 Feb 2025
Certificates of CA (Form 3)File: form-3 As on june 2022_11zon (1).pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on September 2024(1)_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on september 2023_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on September 2022_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on September 2021_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on march 2024_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on March 2023_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on march 2022_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on june 2024_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on june 2023_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on December 2023_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form-3 As on December 2022_11zon.pdf4 Feb 2025
Certificates of CA (Form 3)File: form -3 As on june 2021.pdf4 Feb 2025
Declaration in FORM BFile: FORM B.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD INVENTORY.pdf18 Dec 2024
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE DECLARATION.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE JUNE 2023.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE MARCH 24.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE DEC 2023.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE SEPT 2023.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE MARCH 2023.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE DEC 22.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE SEPT 22.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE JUNE 22.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE MARCH 22.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE DEC 2021.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE SEPT 2021.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE SEPT 2021.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE JUNE 2021.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE DEC 21.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SEPT 24.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE JUNE 24.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE MARCH 24.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE DEC 23.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SEPT 23.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE JUNE 2023.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE MARCH 23.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE DEC 2022.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SEPT 2022.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE JUNE 22.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE MARCH 22.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SEPT 21.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE JUNE 21.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE DEC 2022.pdf17 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 31-03-2021.pdf17 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: format -A bank.pdf17 Dec 2024
Details of encumbrances concerned to LegalFile: ENCUMBRANCE DECLARATION.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form-5 march 22.pdf17 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 31-03-2022.pdf17 Dec 2024
Proforma of Agreement for saleFile: sales_11zon.pdf17 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf17 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 31-03-2023.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form-5 march 2023.pdf17 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 31-03-2024.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 05 march 24.pdf17 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B (HDFC BANK).pdf17 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Annexure A.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: My Doc - 562694 2018-2019.pdf23 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: My Doc - 199243 2019-20.pdf23 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: My Doc - 339061 2020-21.pdf23 Aug 2021
OtherFile: CONSET OF EXTENTION.pdf11 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-2019.pdf9 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-2020.pdf9 Aug 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 84 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ADITYA VARDHAN HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WADGAON13,700+ in Pune

2 kmADITYA VARDHAN HEIGHTSCompleted 27Lapsed / revoked 23Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: SHREE GANESH DEVELOPERS

SHREE GANESH DEVELOPERS has 24 registrations on MahaRERA, including MANGALMURTI RESIDENCY and Siddhi Homes. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ADITYA VARDHAN HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ADITYA VARDHAN HEIGHTS?

The registered promoter entity is SHREE GANESH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ADITYA VARDHAN HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ADITYA VARDHAN HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in ADITYA VARDHAN HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADITYA VARDHAN HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADITYA VARDHAN HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.