ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ADITYA ENCLAVE

Registered No litigation declared Others project

ADITYA ENCLAVE

By RAKHI PANKAJ CHOPADA

RG-MH-72075 · RERA P52100050290 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 18.00 crore secured on the land, in favour of AU Small Finance Bank Limited

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 95%
117 of 128Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 91 documents Report an error

ADITYA ENCLAVE is a Others project by RAKHI PANKAJ CHOPADA in Pune, Maharashtra, registered with MahaRERA as P52100050290 on 1 Apr 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 11 of the 128 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameADITYA ENCLAVE
  • TypeOthers
  • Location
    • HINJAWADI
    • PUNE
    • Man
    • Mulshi
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050290
  • ReraGenie IDRG-MH-72075

Builder

  • NameRAKHI PANKAJ CHOPADA
  • Entity typeIndividual

Key dates

this monthRegisteredApr 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Apr 2023
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed91 files

Current status

9%11 of 128 units booked
69.6%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ADITYA ENCLAVENA984088128

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

ADITYA ENCLAVE: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed238

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots238
Closed/Covered212
Open Space26

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,366 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAU Small Finance Bank Limited
Secured amountRs 18.00 crore
CERSAI search filedYes
Declared on12 Jul 2025

Approvals and building plan

Sanctioning authorityMaharashtra Industrial Development Corporation
Permissible FSI8870.73
Proposed, not sanctioned6,168 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch102 103 S No 184 Anand Park Haveli Aundh Pune 411007
Estimated costRs 27.71 cr
Cost incurredRs 19.29 cr
Work done69.61%
BuildingWingEstimatedIncurred
ADITYA ENCLAVENARs 25.61 crRs 18.55 cr
-NARs 2.10 crRs 73.62 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUDHIR PATIL & ASSOCIATES
EngineerRATHI'S GROUP
Chartered AccountantPGMJ AND ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
RAKHI PANKAJ CHOPADA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA06032620119Mar 2026 → Mar 2027

Reason as filed by the promoterWe have applied for changes to the project plan with the planning authority. Due to delays in receiving approval for the revised plan, the project will take longer than originally expected.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed91

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Q1 26-27 FINAL.pdf20 Jul 2026
Withdrawal Update Form 2File: FORM 2 Q1 26-27 FINAL.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM 3 Q1 26-27.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf16 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf16 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf16 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf6 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf6 Mar 2026
Withdrawal Update Form 3File: Form 3 Upload.pdf6 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A Final.pdf23 Dec 2025
Form 5 (FY 2023-2024)File: Final Form 5 2023-24.pdf18 Dec 2025
Form 5 (FY 2024-2025)File: Final Form 5 2024-25.pdf18 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf20 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf20 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf20 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf17 Oct 2025
Layout approvalFile: Sanction Plan.pdf17 Sep 2025
Building plan approvalFile: Building Plan.pdf17 Sep 2025
Building plan approvalFile: Building Plan 1.pdf17 Sep 2025
Building plan approvalFile: Building Plan 2.pdf17 Sep 2025
Form 1File: Form 1 Final.pdf19 Jul 2025
Form 2File: Form 2.pdf19 Jul 2025
Form 3File: Form 3 Final_compressed.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular Final.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Circular_organized.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf18 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Eng Certificate Quality Assurance_0001.pdf14 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf29 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 Upload.pdf29 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclousure.pdf29 Nov 2024
Proforma of Agreement for saleFile: REVISED MODEL RERA draft -COMMERCIAL-ADITYA ENCLAVE-16-10-2024 (2).pdf19 Nov 2024
Proforma of Agreement for saleFile: REVISED MODEL RERA draft -RESIDENTIAL-ADITYA ENCLAVE-23-10-2024 (1).pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Rera Sold Unsold letter.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: SD.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 upload.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular Upload.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upload.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate_0001.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory Signed.pdf15 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_compressed.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: Rera Sold Circlular.pdf26 Dec 2023
Disclosure of sold/ booked inventoryFile: Rera Sold Booked Invetory.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf30 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf30 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf30 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: compressed_FORM 2.pdf30 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: compressed_Form 3 CA SIGNED Q1_merged.pdf30 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: compressed_edited_Form 3 CA SIGNED.pdf30 Oct 2023
Proforma of Agreement for saleFile: MODEL RERA draft -COMMERCIAL-ADITYA ENCLAVE-MIDC- PLOT 18-32-MAN-RGIT PARK-20-04-2023.pdf21 Apr 2023
Proforma of Agreement for saleFile: MODEL RERA draft -RESIDENTIAL-ADITYA ENCLAVE-MIDC- PLOT 18-32-MAN-RGIT PARK-20-04-2023.pdf21 Apr 2023
Proforma of Agreement for saleFile: MODEL RERA draft -COMMERCIAL-ADITYA ENCLAVE-MIDC- PLOT 18-32-MAN-RGIT PARK-24-03-2023.pdf24 Mar 2023
Proforma of Agreement for saleFile: MODEL RERA draft -RESIDENTIAL-ADITYA ENCLAVE-MIDC- PLOT 18-32-MAN-RGIT PARK-24-03-2023.pdf24 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement - COMMERCIAL-ADITYA ENCLAVE-24-03-2023.pdf24 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement -ADITYA ENCLAVE-24-03-2023.pdf24 Mar 2023
Layout approvalFile: Layout Plan1_compressed.pdf17 Mar 2023
Building plan approvalFile: Building Plan_compressed (1).pdf17 Mar 2023
Copy of Layout Approval (in case of layout)File: Layout Plan1_compressed.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_compressed (1).pdf17 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: cc aditya.pdf17 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200263236629_For_Asset_Based_Search_17_03_2023_11_03_43_549.pdf17 Mar 2023

How this compares with Pune

9%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ADITYA ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

2 kmADITYA ENCLAVECompleted 32Lapsed / revoked 11Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 82 registered projects within 2 km.

Builder: RAKHI PANKAJ CHOPADA

RAKHI PANKAJ CHOPADA has 1 registration on MahaRERA, including ADITYA ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ADITYA ENCLAVE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ADITYA ENCLAVE?

The registered promoter entity is RAKHI PANKAJ CHOPADA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ADITYA ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ADITYA ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ADITYA ENCLAVE?

The professionals named in the filing: Architect: SUDHIR PATIL & ASSOCIATES; Engineer: RATHI'S GROUP; Chartered Accountant: PGMJ AND ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADITYA ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADITYA ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADITYA ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.