ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Aditya Chandrashali

Completed No litigation declared Residential / Group Housing project

Aditya Chandrashali

By Aditya Arayn Developers LLP

RG-MH-35371 · RERA P51800051664 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
0 of 11Construction stages donefurthest along: Excavation, 90%
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

Aditya Chandrashali is a Residential / Group Housing project by Aditya Arayn Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800051664 on 27 Jun 2023. The registration is recorded completed; possession was promised by 31 Dec 2024.

At a glance

Project

  • NameAditya Chandrashali
  • TypeResidential / Group Housing
  • Location
    • Mamlatdarwadi Road
    • Liberty Garden
    • Malad
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • RERA no.P51800051664
  • ReraGenie IDRG-MH-35371

Builder

  • NameAditya Arayn Developers LLP
  • Entity typePartnership
  • PartnersDineshkumar Chhabildas Agarwal, Rahul Bansal
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2023PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jun 2023
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Aditya AraynNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 90%.

Aditya Arayn: 51% average across the applicable activities

ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor80%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,585 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Aditya Arayn Developers LLPMaladMumbai Suburban
Mrs. Jyoti Jayantilal KawaMaladMumbai Suburban
Mr. Prashant Chhotu DesaiMaladMumbai Suburban
Mr. Vikas Chhotu DesaiMaladMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1605.51
Proposed, not sanctioned1,606 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSakinaka Branch

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPushkar Consultants
EngineerR D Magdum
Chartered AccountantPNS & Co
PartnerRole in project
Aditya Arayn Developers LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Jan 2025

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHETICHET CERTIFICATE NEW FOR ADITYA ARAYN 31032024.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHETICHET CERTIFICATE NEW FOR ADITYA ARAYN 30062024.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHETICHET CERTIFICATE NEW FOR ADITYA ARAYN 31092024 (1).pdf14 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2448731_OC_signed_250110_202112.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ADITYA ARAYN 30092023.pdf11 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ADITYA ARAYN 31122023.pdf11 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ADITYA ARAYN 31032024.pdf11 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ADITYA ARAYN 30062024.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30 sept 23.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 31 dec 23.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 31 march 24.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 30 june 24.pdf11 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect.pdf24 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf24 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf24 Nov 2023
Other - LegalFile: Declaration.pdf30 May 2023
Other - TechnicalFile: Declaration regarding plot area.pdf30 May 2023
Layout approvalFile: Plan 2.pdf19 May 2023
Building plan approvalFile: Plan 2.pdf19 May 2023
Copy of Layout Approval (in case of layout)File: Plan 2.pdf19 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf19 May 2023
Other - LegalFile: Form B_compressed.pdf19 May 2023
Deviation Report with respect to model copy of AgreementFile: AFS.pdf3 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Rahul Bansal.pdf30 Jan 2023
Proforma of Allotment letterFile: Final Allotment Letter.pdf30 Jan 2023
Proforma of Agreement for saleFile: AFS.pdf30 Jan 2023
Deviation Report with respect to Allotment letterFile: Final Allotment Letter Deviation Report.pdf30 Jan 2023
Building plan approvalFile: Plan 1.pdf21 Jan 2023
Layout approvalFile: Plan 1.pdf21 Jan 2023
PAN CardFile: AAD Pan Card.pdf21 Jan 2023
Copy of the legal title reportFile: LTR Final.pdf21 Jan 2023
Details of encumbrances concerned to FinanceFile: Finance and legal encumbrance declaration.pdf21 Jan 2023
Details of encumbrances concerned to LegalFile: Finance and legal encumbrance declaration.pdf21 Jan 2023
Copy of Layout Approval (in case of layout)File: Plan 1.pdf21 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf21 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 Jan 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf21 Jan 2023
Declaration in FORM BFile: Form B - Dinesh Agarwal.pdf21 Jan 2023
Declaration in FORM BFile: Form B - Rahul Bansal.pdf21 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect's Certificate.pdf21 Jan 2023
CERSAI detailsFile: CERSAI REPORT.pdf21 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Dinesh Agarwal.pdf21 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate bank account declaration.pdf21 Jan 2023

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aditya Chandrashali on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Liberty Garden6,700+ in Mumbai Suburban

Builder: Aditya Arayn Developers LLP

Aditya Arayn Developers LLP has 2 registrations on MahaRERA, including Aditya Chandrashali and Aditya Breeze. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Aditya Chandrashali is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aditya Chandrashali?

The registered promoter entity is Aditya Arayn Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aditya Chandrashali?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aditya Chandrashali?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aditya Chandrashali?

The professionals named in the filing: Architect: Pushkar Consultants; Engineer: R D Magdum; Chartered Accountant: PNS & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aditya Chandrashali?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aditya Chandrashali. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aditya Chandrashali to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.