Home / Browse projects / Thane, Maharashtra / ADARSH TOWER

Completed No litigation declared Residential / Group Housing project

ADARSH TOWER

By CITY DEVELOPERS

RG-MH-71477 · RERA P51700017752 · Last updated on MahaRERA portal: 2 Jan 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: Stilt Floor, 96%
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

ADARSH TOWER is a Residential / Group Housing project by CITY DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700017752 on 11 Sep 2018. The registration is recorded completed; possession was promised by 15 Dec 2024. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameADARSH TOWER
  • TypeResidential / Group Housing
  • Location
    • ADARSH PARK
    • KOMAL PADA
    • NEAR NANA-NANI PARK
    • Bhiwandi (M Corp.)
    • Bhiwandi
    • Thane
    • 421302
  • Pincode421302
  • RERA no.P51700017752
  • ReraGenie IDRG-MH-71477

Builder

  • NameCITY DEVELOPERS
  • Entity typePartnership
  • PartnersSAIFULISLAM MASOOD AHAHMAD SHAIKH, MOHAMMAD SALEEM ABDUL JAISH
  • Other registrations1 more →
  • Completed1 of 2
  • Past their filed date1

Key dates

this monthRegisteredSep 2018First promiseDec 2022Revised toDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Sep 2018
  • Promised completion15 Dec 2024
  • Revised completionRevised to 15 Dec 2024 (originally 15 Dec 2022)
  • Buildings1 building record
  • Documents filed64 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ADARSH TOWERNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 96%.

ADARSH TOWER: 36% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor96%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area727 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
SAYEEDAHMED ABDULRAUF PUNJABIBhiwandi (M Corp.)Thane
SAFDAR SAYEEDAHMED PUNJABIBhiwandi (M Corp.)Thane

Approvals and building plan

Permissible FSI1259.04
Proposed, not sanctioned693 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTELIPADA BHIWANDI-421302, DIST THANE , MAHARASHTRA

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIRFAN HAJI MOHD HUSAIN MOMIN
PartnerRole in project
CITY DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700013196Dec 2022 → Dec 2023

Reason as filed by the promoterReson For Delay Project 1. Due to pandemic(corona) & lockdown in 2020 & 2021 Our Project has been stopped execuring for 6 months in 2020(Lockdown I) & 6 month 2021 (Lockdown II) 2. Shortage of labour & raw material post lockdown got very slow speed & construction 3. heavy monsoon in 2021

EXT51700018452Dec 2022 → Dec 2024

Reason as filed by the promoterDear Sir, We have registered as referred above & our project completion date as anticipated earlier was 15/12/2023. We here by apply for extension of due date of completion & project for 12 Months on the Following Grounds. 1) Due to Pandemic (Corona) & Lockdown in 2020 & 2021our project has been stopped executing for 6 months in 2020(lockdown I) & 6 months 2021 (lockdown II). 2) Shortage of labour& raw materials post lockdown got very slow speed & construction. 3) Heavy monsoon in 2021. 4) Further land owner Mr. Sayeed Ahmed Abdul Raoof Punjabi who has ex executed development agreement as well

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Jan 2025

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: CITY DEVELOPERS OC PLAN_11zon.pdf2 Jan 2025
Copy of Layout Approval (in case of layout)File: CITY DEVELOPERS OC PLAN_11zon.pdf2 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final OC.pdf2 Jan 2025
Disclosure of sold/ booked inventoryFile: discloser of sold unsold unit 31-01-24.pdf11 Feb 2024
Certificates of CA (Form 3)File: FORM 3_compressed.pdf11 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) (2).pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 01 JAN 23 TO 31 MAR 23.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 01 APRIL 2023 TO JUNE 23.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 01 JULY 23 TO 30 SEP 23.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 01 OCT 23 TO 31 DEC 23.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 01 JAN 23 TO 31 MAR 23.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 01 APR 23 TO JUNE 23.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 1 JULY 23 TO 30 SEP 23.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE 01 OCT 2023 TO 31 DEC 23.pdf22 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A MARCH 2023.pdf22 Jan 2024
Certificates of CA (Form 3)File: Jan 23 to March 23.pdf22 Jan 2024
Certificates of CA (Form 3)File: april 23 to june 23.pdf22 Jan 2024
Certificates of CA (Form 3)File: July 23 to Sep 23.pdf22 Jan 2024
Certificates of CA (Form 3)File: Oct 23 to Sep 23.pdf22 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY CITY DEVELOPERS.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: MARCH 2019.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: March 20.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: March 21.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: March 22.pdf11 Feb 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATES.pdf10 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATES JULY TO SEP 2022.pdf10 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATES OCT TO DEC 2022.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATES JULY TO SEP 2022 (1).pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATES OCT TO DEC 22.pdf10 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A city developers.pdf10 Feb 2023
Certificates of CA (Form 3)File: April 22 to June 22.pdf10 Feb 2023
Certificates of CA (Form 3)File: July to sep 22.pdf10 Feb 2023
Certificates of CA (Form 3)File: oct 22 to dec 22.pdf10 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATES JULY TO SEP 21.pdf3 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATES OCT TO DEC 21.pdf3 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATES JAN TO MAR 22.pdf3 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATES APRIL TO JUNE 22.pdf3 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATES JULY TO SEP 2021.pdf3 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATES OCT TO DEC 21.pdf3 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATES JAN TO MAR 22.pdf3 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATES APRIL TO JUNE 22.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-08-2018 TO 31-12-2018.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-01-2019 to 31-03-2019 _removed.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-04-20219 to 30-06-2019.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-07-2019 to 30-09-2019.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-10-2019 to 31-12-2019.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-01-2020 TO 31-03-2020.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-04-2020 to 30-06-2020.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-07-2020 to 30-09-2020.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-10-2020 to 31-12-2020.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-1-2021 to 31-03-2021.pdf3 Dec 2022
Certificates of CA (Form 3)File: 01-4-2021 to 31-06-2021.pdf3 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: City Developers CC up to 7th Floor.pdf20 Aug 2022
Layout approvalFile: Plan Layout.pdf2 Sep 2018
Building plan approvalFile: BLDG Plan Approval.pdf2 Sep 2018
Copy of the legal title reportFile: TITLE CLEARANCE CERIFICATE.pdf2 Sep 2018
Details of encumbrancesFile: declaration free from Encumbrance.pdf2 Sep 2018
Copy of Layout Approval (in case of layout)File: Plan Layout.pdf2 Sep 2018
Building Plan Approval (IOD)File: BLDG Plan Approval.pdf2 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 Sep 2018
Declaration in FORM BFile: Form B.pdf2 Sep 2018
Certificates of CA (Form 3)File: CA Certificate (Form 3).pdf2 Sep 2018
Proforma of Allotment letterFile: Flat Allotment Letter.pdf2 Sep 2018

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ADARSH TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR NANA-NANI PARK7,600+ in Thane

Builder: CITY DEVELOPERS

CITY DEVELOPERS has 2 registrations on MahaRERA, including ADARSH TOWER and CHANDAN HERITAGE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ADARSH TOWER is delayed beyond 15 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ADARSH TOWER?

The registered promoter entity is CITY DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ADARSH TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ADARSH TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ADARSH TOWER?

The professionals named in the filing: Architect: IRFAN HAJI MOHD HUSAIN MOMIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADARSH TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADARSH TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADARSH TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.