Home / Browse projects / Palghar, Maharashtra / Acciano Bianca

Registration lapsed No litigation declared Residential / Group Housing project

Acciano Bianca

By M/s. Ideal Enterprises

RG-MH-46387 · RERA P99000035182 · Last updated on MahaRERA portal: 1 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
27 of 110Construction stages doneacross 10 buildings; furthest along: Internal walls, 50%
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

Acciano Bianca is a Residential / Group Housing project by M/s. Ideal Enterprises in Palghar, Maharashtra, registered with MahaRERA as P99000035182 on 10 May 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameAcciano Bianca
  • TypeResidential / Group Housing
  • Location
    • Karachiwala baug
    • Papdy
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401207
  • Pincode401207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000035182
  • ReraGenie IDRG-MH-46387

Builder

  • NameM/s. Ideal Enterprises
  • Entity typePartnership
  • PartnersSanpras Percival Furtado, Sandra Percival Furtado, Percival Paul Furtado
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredMay 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 May 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings10 building records
  • Documents filed71 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bungalow no 1NA20000
Bungalow no 2NA20000
Bungalow no 3NA20000
Bungalow no 4NA20000
Bungalow no 5NA20000
Bungalow no 6NA20000
Bungalow no 7NA20000
Bungalow no 8NA20000
Bungalow no 9NA10000
Bungalow no 10NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 1 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Internal walls, at 50%.

Bungalow no 136%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 236%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 336%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 436%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 527%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 645%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 745%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 80%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 90%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow no 100%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Open Space10
BuildingOpen SpaceTotal
Bungalow no 111
Bungalow no 211
Bungalow no 311
Bungalow no 411
Bungalow no 511
Bungalow no 611
Bungalow no 711
Bungalow no 811
Bungalow no 911
Bungalow no 1011

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,937 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1281.01
Proposed, not sanctioned881 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPapdy Vasai West

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMegha Urbanscapes
EngineerPragnesh Oza
Chartered AccountantJ N Kamerkar & Co
PartnerRole in project
M/s. Ideal Enterprises-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf1 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Acciano.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold.pdf24 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf4 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Mar 2023
Disclosure of sold/ booked inventoryFile: Book Inventory.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Mar 2023
Layout approvalFile: Layout.pdf8 Jan 2023
Building plan approvalFile: Bungalow Plan.pdf8 Jan 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf8 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Bungalow Plan.pdf8 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf8 Jan 2023
Other - LegalFile: RERA Carpet Area.pdf8 Jan 2023
Building plan approvalFile: Bung 1234.pdf4 Oct 2022
Building plan approvalFile: Bung 5678.pdf4 Oct 2022
Building plan approvalFile: Bung 9 10.pdf4 Oct 2022
Building plan approvalFile: Layout.pdf4 Oct 2022
Details of encumbrances concerned to LegalFile: Write up on encumbrance legal.pdf4 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Bung 1234.pdf4 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Bung 5678.pdf4 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Bung 9 10.pdf4 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Layout.pdf4 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf4 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: CC Bungalow No10.pdf4 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf4 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Oct 2022
Disclosure of sold/ booked inventoryFile: sold unsold list.pdf4 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf4 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Write up on details on Bank account.pdf4 Oct 2022
Deviation Report with respect to Allotment letterFile: Write up on deviation on Allotment letter.pdf4 Oct 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report.pdf4 Oct 2022
Other - LegalFile: Application for correction.pdf4 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf1 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf1 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf1 Sep 2022
Layout approvalFile: Layout.pdf2 May 2022
Building plan approvalFile: Bungalow Plan 1.pdf2 May 2022
Building plan approvalFile: Bungalow Plan 2.pdf2 May 2022
Copy of Layout Approval (in case of layout)File: Layout.pdf2 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Bungalow Plan 1.pdf2 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Bungalow Plan 2.pdf2 May 2022
Building plan approvalFile: NA.pdf21 Apr 2022
PAN CardFile: Ideal Ent Pancard.pdf21 Apr 2022
Copy of the legal title reportFile: Title.pdf21 Apr 2022
Details of encumbrancesFile: Nil encumbrances.pdf21 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: NA.pdf21 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Old CC.pdf21 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf21 Apr 2022
Declaration about Commencement CertificateFile: Declaration CC.pdf21 Apr 2022
Declaration in FORM BFile: Declaration Form B.pdf21 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Apr 2022
CERSAI detailsFile: CERSAI Search Report.pdf21 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Apr 2022
Proforma of Allotment letterFile: Draft allotment letter Acciano Bianca.pdf21 Apr 2022
Proforma of Allotment letterFile: Clean AFS Acciano Bianca Bunglow.pdf21 Apr 2022

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Acciano Bianca on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Papdy3,200+ in Palghar

2 kmAcciano BiancaCompleted 124Lapsed / revoked 56Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 316 registered projects within 2 km.

Builder: M/s. Ideal Enterprises

M/s Ideal Enterprises has 2 registrations on MahaRERA, including Acciano-Aurelia No. 1 and Acciano Bianca. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that Acciano Bianca shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Acciano Bianca is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Acciano Bianca?

The registered promoter entity is M/s. Ideal Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Acciano Bianca?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Acciano Bianca?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Acciano Bianca?

The professionals named in the filing: Architect: Megha Urbanscapes; Engineer: Pragnesh Oza; Chartered Accountant: J N Kamerkar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Acciano Bianca?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Acciano Bianca. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Acciano Bianca to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.