Home / Browse projects / Palghar, Maharashtra / Acciano-Aurelia No. 1

Completed No litigation declared Residential / Group Housing project

Acciano-Aurelia No. 1

By M/s Ideal Enterprises

RG-MH-02797 · RERA P99000019904 · Last updated on MahaRERA portal: 24 Feb 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
24 of 88Construction stages doneacross 8 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

Acciano-Aurelia No. 1 is a Residential / Group Housing project by M/s Ideal Enterprises in Palghar, Maharashtra, registered with MahaRERA as P99000019904 on 13 Mar 2019. The registration is recorded completed; possession was promised by 30 Jun 2023.

At a glance

Project

  • NameAcciano-Aurelia No. 1
  • TypeResidential / Group Housing
  • Location
    • Chobare Road
    • Chobare
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401207
  • Pincode401207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000019904
  • ReraGenie IDRG-MH-02797

Builder

  • NameM/s Ideal Enterprises
  • Entity typePartnership
  • PartnersSandra Percival Furtado, Sanpras Percival Furtado
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredMar 2019PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on13 Mar 2019
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings8 building records
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Acciano-Aurelia No 1NA20000
Acciano-Aurelia No 2NA20000
Acciano-Aurelia No 3NA20000
Acciano-Aurelia No 4NA20000
Acciano-Aurelia No 5NA20000
Acciano-Aurelia No 6NA20000
Acciano-Aurelia No 7NA20000
Acciano-Aurelia No 8NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 24 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Podiums (if any), at 0%.

Acciano-Aurelia No 127%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 227%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 327%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 427%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 527%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 627%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 727%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Acciano-Aurelia No 827%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes13%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Open Space8
BuildingOpen SpaceTotal
Acciano-Aurelia No 111
Acciano-Aurelia No 211
Acciano-Aurelia No 311
Acciano-Aurelia No 411
Acciano-Aurelia No 511
Acciano-Aurelia No 611
Acciano-Aurelia No 711
Acciano-Aurelia No 811

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,530 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6325.0
Proposed, not sanctioned759 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPapdy, Vasai West, Taluka Vasai, District Palghar

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKuldip B Patil
PartnerRole in project
M/s Ideal Enterprises-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Feb 2022

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Feb 2022
Certificates of CA (Form 3)File: Form 3.pdf24 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf24 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf24 Feb 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf24 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf22 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: Acciano.pdf23 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf23 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Details.pdf15 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf11 Feb 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf11 Feb 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf11 Feb 2021
Certificates of CA (Form 3)File: Form-3.pdf11 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf5 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf5 Sep 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf5 Sep 2020
Certificates of CA (Form 3)File: Form 3.pdf5 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf24 Aug 2020
Certificates of CA (Form 3)File: Form 3.pdf24 Aug 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Aug 2020
Details of Restarting of Construction work post lockdownFile: Letter.pdf2 Jul 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf28 Feb 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY - Form 2A.pdf28 Feb 2020
Certificates of CA (Form 3)File: CA Form 3.pdf28 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Ideal enterprises 2018-19 Rera Form 5.pdf8 Feb 2020
PAN CardFile: Ideal Ent Pancard.pdf3 Jan 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AA Form 1.pdf2 Jan 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AA Form 2A.pdf2 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: AA Form 2A.pdf2 Jan 2020
Certificates of CA (Form 3)File: CA Certificate.pdf2 Jan 2020
OtherFile: Architect certificate.pdf21 Nov 2019
OtherFile: Architect certificate.pdf21 Nov 2019
OtherFile: Site Supervisior.pdf21 Nov 2019
OtherFile: Structural Eng.pdf21 Nov 2019
Copy of the legal title reportFile: Title-R.pdf8 Mar 2019
Copy of the legal title reportFile: Title 2-R.pdf8 Mar 2019
Details of encumbrancesFile: Letter.pdf8 Mar 2019
Declaration in FORM BFile: Form B.pdf8 Mar 2019
Proforma of Allotment letterFile: Draft AFS-6050.pdf8 Mar 2019
Proforma of Allotment letterFile: Allotment-6050.pdf8 Mar 2019
Building plan approvalFile: CC.pdf26 Feb 2019
Layout approvalFile: Layout.pdf26 Feb 2019
Copy of Layout Approval (in case of layout)File: Layout.pdf26 Feb 2019
Building Plan Approval (IOD)File: CC.pdf26 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf26 Feb 2019
Certificates of CA (Form 3)File: CA Certifiacte Form 3-r.pdf26 Feb 2019

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Acciano-Aurelia No. 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chobare3,200+ in Palghar

2 kmAcciano-Aurelia No. 1Completed 30Lapsed / revoked 14Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: M/s Ideal Enterprises

M/s Ideal Enterprises has 2 registrations on MahaRERA, including Acciano-Aurelia No. 1 and Acciano Bianca. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Acciano-Aurelia No. 1 is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Acciano-Aurelia No. 1?

The registered promoter entity is M/s Ideal Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Acciano-Aurelia No. 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Acciano-Aurelia No. 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Acciano-Aurelia No. 1?

The professionals named in the filing: Architect: Kuldip B Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Acciano-Aurelia No. 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Acciano-Aurelia No. 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Acciano-Aurelia No. 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.