Home / Browse projects / Dadra & Nagar Haveli / ABHINANDAN MOUNTREEA

Registered No litigation declared Residential / Group Housing project

ABHINANDAN MOUNTREEA

By ABHI DEVELOPERS

RG-MH-79025 · RERA PR3001012502322 · Last updated on MahaRERA portal: 11 May 2026

Source: official MahaRERA filing

Red flags

  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Oct 2028Possession promisedno revision filed
10 of 40Construction stages doneacross 5 buildings; furthest along: Plinth, 90%
5 of 5Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 6 documents Report an error

ABHINANDAN MOUNTREEA is a Residential / Group Housing project by ABHI DEVELOPERS in Dadra & Nagar Haveli, registered with MahaRERA as PR3001012502322 on 11 Feb 2026. Possession is promised by 31 Oct 2028. 0 of the 5 units on this registration are recorded sold or booked, and 10 of 40 construction stages are filed complete.

At a glance

Project

  • NameABHINANDAN MOUNTREEA
  • TypeResidential / Group Housing
  • Location
    • No. Survey no 318
    • Plot No.2
    • 4
    • 5
    • 7
    • 9
    • Near Kamat Hotel
    • Behind haveli ground
    • Opp. Swaminarayan Temple
    • Athal
    • Others
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR3001012502322
  • ReraGenie IDRG-MH-79025

Builder

  • NameABHI DEVELOPERS
  • Entity typePartnership
  • GSTIN26AARFA5509K1Z4
  • PartnersChetankumar Natwarlal Shah, Eleshkumar Natwarlal Shah, Seema Chetankumar Shah, Sarojben Dilipkumar Parmar, Dilipkumar Himmatsinh Parmar, Yogitaben Molilalji Bora

Key dates

this monthRegisteredFeb 2026PromisedOct 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Feb 2026
  • Promised completion31 Oct 2028
  • Revised completionNone
  • Buildings5 building records
  • Documents filed6 files

Current status

0%0 of 5 units booked
62.0%Work done, per cost certificate

Figures as on 11 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Plot 2 Building ANA33101
Plot 4 Building ANA33101
Plot 5 Building ANA33101
Plot 7 Building ANA33101
Plot 9 Building ANA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 40 construction stages are filed complete across 5 buildings. The stage furthest along is Plinth, at 90%.

Plot 2 Building A2%
ActivityProgress
Excavation20%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Plot 4 Building A24%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth90%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Plot 5 Building A51%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Plot 7 Building A57%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Plot 9 Building A78%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo40%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area35,407 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Oct 2025

Approvals and building plan

Sanctioning authorityPlanning and Development Authority, Dada & Nagar Haveli
Permissible FSI2686.0
Proposed, not sanctioned2,686 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVRAJ DARSHAN APPARTMENTSSHOP NO. U 23-24-25-26VAPI-SILVASSA ROAD
Estimated costRs 4.61 cr
Cost incurredRs 2.86 cr
Work done62.01%
BuildingWingEstimatedIncurred
Plot 2 Building ANARs 86.65 lakhRs 2.50 lakh
Plot 4 Building ANARs 86.65 lakhRs 38.10 lakh
Plot 5 Building ANARs 86.65 lakhRs 75.50 lakh
Plot 7 Building ANARs 86.65 lakhRs 78.20 lakh
Plot 9 Building ANARs 86.65 lakhRs 84.30 lakh
-NARs 28.10 lakhRs 7.50 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHPA Design
EngineerSadguru Consultant ASVC
Chartered AccountantMavani Santoki & Co.
Chartered AccountantKakaria and Associates LLP
PartnerRole in project
ABHI DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2028

Documents filed6

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 signed.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 Signed.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Signed.pdf11 May 2026
Declaration and undertaking (Annexure A)File: Annexure A order 50.pdf20 Sep 2025
Layout approvalFile: merged PlansC.pdf19 Sep 2025
Building plan approvalFile: merged PlansC.pdf19 Sep 2025

How this compares with Dadra & Nagar Haveli

0%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one has not
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is on the register

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep ABHINANDAN MOUNTREEA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Behind haveli ground, Opp. Swaminarayan Temple, Athal210+ in Dadra & Nagar Haveli

2 kmABHINANDAN MOUNTREEACompleted 19Lapsed / revoked 9Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 40 registered projects within 2 km.

Builder: ABHI DEVELOPERS

ABHI DEVELOPERS has 1 registration on MahaRERA, including ABHINANDAN MOUNTREEA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What are my rights if ABHINANDAN MOUNTREEA is delayed beyond 31 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ABHINANDAN MOUNTREEA?

The registered promoter entity is ABHI DEVELOPERS, a partnership as per the filing. Its GSTIN 26AARFA5509K1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ABHINANDAN MOUNTREEA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ABHINANDAN MOUNTREEA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ABHINANDAN MOUNTREEA?

The professionals named in the filing: Architect: HPA Design; Engineer: Sadguru Consultant ASVC; Chartered Accountant: Mavani Santoki & Co.; Chartered Accountant: Kakaria and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABHINANDAN MOUNTREEA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABHINANDAN MOUNTREEA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABHINANDAN MOUNTREEA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.