Home / Browse projects / Pune, Maharashtra / ABC NIVRITI
ABC NIVRITI
RG-MH-65818 · RERA P52100017771 · Last updated on MahaRERA portal: 24 Oct 2024
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 24 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ABC NIVRITI is a Others project by AGARWAL GARDEN in Pune, Maharashtra, registered with MahaRERA as P52100017771 on 17 Sep 2018. Possession was promised by 30 Oct 2024 and is now 24 months past that date.
At a glance
Project
- NameABC NIVRITI
- TypeOthers
- Location
- WADGON
- MAVAL
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412106
- Pincode412106
- RERA no.P52100017771
- ReraGenie IDRG-MH-65818
Builder
- NameAGARWAL GARDEN
- Entity typePartnership
- PartnersRAKESH CHANDRABHAN AGARWAL, CHANDRABHAN CHOTURAM GARG
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on17 Sep 2018
- Promised completion30 Oct 2024
- Revised completionNone
- Buildings3 building records
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 6 | 0 | 0 | 0 | 0 |
| B | NA | 3 | 0 | 0 | 0 | 0 |
| C | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 24 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.
A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VINOD ASSOCIATES |
| Partner | Role in project |
|---|---|
| AGARWAL GARDEN | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Sep 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Sep 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: AGARWAL GARDEN 23-24.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10-1-22.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10-7-22.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10-10-22.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20-1-23.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20-4-23.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20-7-23.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20-10-23.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 1_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 2_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 3_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 4_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 5_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 6_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 7_001.pdf | 20 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 8_001.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: APR - JUN22.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: APR -JUN 23.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: JAN -MARCH 23.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: JAN22-MAR 22.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: JUL-SEP 22.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: JUL-SEP 23.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: OCT -DEC 22.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: OCT -DEC 23.pdf | 20 May 2024 |
| Certificates of CA (Form 3)File: OCT-DEC21.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Ag Garden Architect Certificate.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Garden Engineeer Certificate Mar 24.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 3 Garden Sold Unsold Inv Mar 24.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architechs certificate.pdf | 8 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf | 8 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: STATEMENT.pdf | 8 Feb 2024 |
| Certificates of CA (Form 3)File: NIL Declaration.pdf | 8 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ABC Nivriti - form 5.pdf | 29 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Agarwal garden (ABC Nivriti).pdf | 5 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Agarwal Garden Nivriti - Rera update FINAL.pdf | 14 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5)File: abc nivriti.pdf | 24 Sep 2020 |
| Annual Audit Report of Statutory CA (Form 5)File: Form 5 Agarwal Garden.pdf | 30 Sep 2019 |
| Building plan approvalFile: A BLDG (as per rera) 1st 2nd 3rd 4th.pdf | 5 Sep 2018 |
| Building plan approvalFile: B BLDG (as per rera) first floor.pdf | 5 Sep 2018 |
| Building plan approvalFile: COMMERCIAL BLDG (as per rera).pdf | 5 Sep 2018 |
| Layout approvalFile: MYSCAN_20180611_0001-ilovepdf-compressed (1).pdf | 5 Sep 2018 |
| Copy of the legal title reportFile: search report.pdf | 5 Sep 2018 |
| Details of encumbrancesFile: 7 Nil letigation certificate.pdf | 5 Sep 2018 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20180611_0001-ilovepdf-compressed (1).pdf | 5 Sep 2018 |
| Building Plan Approval (IOD)File: A BLDG (as per rera) 1st 2nd 3rd 4th.pdf | 5 Sep 2018 |
| Building Plan Approval (IOD)File: B BLDG (as per rera) first floor.pdf | 5 Sep 2018 |
| Building Plan Approval (IOD)File: COMMERCIAL BLDG (as per rera).pdf | 5 Sep 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement cert.pdf | 5 Sep 2018 |
| Declaration in FORM BFile: REVISED FORM B DT 25-8-18.pdf | 5 Sep 2018 |
| Certificates of CA (Form 3)File: RERA CA CERTIFICATE AGARWAL GARDEN-ilovepdf-compressed.pdf | 5 Sep 2018 |
| Proforma of Allotment letterFile: 2 FINAL AGREEMENT APPROVED BY RCA 19-07-2018 ABC NIVRITI.pdf | 5 Sep 2018 |
| OtherFile: 10 Nivriti - Allotment Letter.pdf | 5 Sep 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ABC JUNCTION | H -16 AKURDI PUNE | 68 | Completed | Apr 2007 | Late, Jan 2008 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 52 filed documents as one ZIP, foldered, with a manifest
Keep ABC NIVRITI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAVAL13,700+ in Pune
Residential Building on CTS No 107/1P -GIRIVAR
SHRIVAR BUILDERS LLP
Aranya
Naiknavare Township LLP.
Land of Dreams
Krisala Buildscape LLP
Mount Vista
Tirupati Lands and Building Constructions
Osian LifeLands 2
Planet-i Realty
RKL INDRAYANI CITY
R K LUNKAD HOUSING COMPANY
Builder: AGARWAL GARDEN
AGARWAL GARDEN has 1 registration on MahaRERA, including ABC NIVRITI. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that ABC NIVRITI shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ABC NIVRITI is delayed beyond 30 Oct 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ABC NIVRITI?
The registered promoter entity is AGARWAL GARDEN, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ABC NIVRITI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ABC NIVRITI?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ABC NIVRITI?
The professionals named in the filing: Architect: VINOD ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ABC NIVRITI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback