Completed No litigation declared Residential / Group Housing project

Aarya Residency

By Aarya Construction

RG-MH-24287 · RERA P52100004009 · Last updated on MahaRERA portal: 9 Nov 2021

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

Aarya Residency is a Residential / Group Housing project by Aarya Construction in Pune, Maharashtra, registered with MahaRERA as P52100004009 on 7 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameAarya Residency
  • TypeResidential / Group Housing
  • Location
    • Prayeja City Road
    • Wadgaon Bk
    • Wadgaon Bk
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004009
  • ReraGenie IDRG-MH-24287

Builder

  • NameAarya Construction
  • Entity typePartnership
  • PartnersArun Kisanrao Garud, Prashant Ramchandra Harsule, Anil Jagannath Maral, Ketan Sambhaji Gosavi

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered78
Open Space6

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
GOSAVI KETAN SAMBHAJIWadgaon BkPune
Arun Kisanrao GarudKothrudPune
Prashant Ramchandra HarsuleKothrudPune
Anil Jagannath MaralKothrudPune

Approvals and building plan

Permissible FSI5155.83
Proposed, not sanctioned2,695 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKarve Nagar, Pune-411052

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Sanjay Rohidas Bhagat
EngineerSuresh Nagorao Gaikwad
Chartered AccountantBalaji Pensalwar
PartnerRole in project
Aarya Construction-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005133Dec 2019 → Dec 2020

Reason as filed by the promoter1) Due to heavy rainfall fallen in the months of September and October 2019, the bridge connecting to the site nearly 200 meter far from the site was broken down and also washed out, therefore the transport of labors and materials could not be reached timely to the site, hence construction activity was totally stopped. 2. Delay in getting NOC from Ministry of Defense in respect of RED Zone which is required for obtaining Completion Certificate from the Pune Municipal Corporation i.e. Planning Authority Therefore, we cannot be completed the project on or before the proposed date of completion i

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 May 2021

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Archict Certificate.pdf9 Nov 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation letter.pdf14 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation letter.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold,unsold inventory.pdf6 Aug 2021
Declaration about Commencement CertificateFile: New Building CC_compressed.pdf5 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Form 2A_compressed (1).pdf5 Aug 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Archict Certificate.pdf25 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Aarya Complition Certificate.pdf28 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.pdf20 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTIFICATE.pdf20 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTIFICATE.pdf20 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2 ENG CERTIFICATE.pdf20 Feb 2020
Certificates of CA (Form 5)File: FORM 5 CA.pdf20 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ANNUAL REPORT 2018-19 (1).pdf20 Feb 2020
Building plan approvalFile: NEW REVISED PLAN - 1 (1).pdf11 Jan 2019
Building plan approvalFile: Club House Plan (1).pdf11 Jan 2019
Building Plan Approval (IOD)File: NEW REVISED PLAN - 1 (1).pdf11 Jan 2019
Building Plan Approval (IOD)File: Club House Plan (1).pdf11 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: New Building CC (1).pdf11 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: Club House CC.pdf11 Jan 2019
Certificates of CA (Form 5)File: FORM 5 CERTIFICATES-FINAL.pdf11 Jan 2019
Building plan approvalFile: 1.pdf22 Jun 2018
Layout approvalFile: Layout .pdf22 Jun 2018
Building plan approvalFile: 2.pdf22 Jun 2018
Building plan approvalFile: 3.pdf22 Jun 2018
Building plan approvalFile: 4.pdf22 Jun 2018
Building plan approvalFile: 5.pdf22 Jun 2018
Copy of Layout Approval (in case of layout)File: Layout .pdf22 Jun 2018
Building Plan Approval (IOD)File: 1.pdf22 Jun 2018
Building Plan Approval (IOD)File: 2.pdf22 Jun 2018
Building Plan Approval (IOD)File: 3.pdf22 Jun 2018
Building Plan Approval (IOD)File: 4.pdf22 Jun 2018
Building Plan Approval (IOD)File: 5.pdf22 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: Building CC-ilovepdf-compressed (2).pdf22 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: Layout CC-ilovepdf-compressed.pdf22 Jun 2018
Layout approvalFile: Layout Approval.pdf31 Jul 2017
Building plan approvalFile: Building Plan Approval.pdf31 Jul 2017
PAN CardFile: Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE REPORT_.pdf31 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE_CERTIFICATE_.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf31 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf31 Jul 2017
Declaration in FORM BFile: FORM-B_DECLARATION.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1_ARCHITECT CERTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE (FORM-2).pdf31 Jul 2017
Certificates of CA (Form 3)File: CERTIFICATE OF CA (FORM - 3).pdf31 Jul 2017
Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT LETTER AND AGREEMENT FOR SALE_.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aarya Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadgaon Bk,13,700+ in Pune

2 kmAarya ResidencyCompleted 51Lapsed / revoked 33Other 72Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: Aarya Construction

Aarya Construction has 1 registration on MahaRERA, including Aarya Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Aarya Residency is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aarya Residency?

The registered promoter entity is Aarya Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aarya Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aarya Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aarya Residency?

The professionals named in the filing: Architect: Mr Sanjay Rohidas Bhagat; Engineer: Suresh Nagorao Gaikwad; Chartered Accountant: Balaji Pensalwar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aarya Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aarya Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aarya Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.