Home / Browse projects / Pune, Maharashtra / AARNA REGENCY

Registered No litigation declared Residential / Group Housing project

AARNA REGENCY

By AARNA ASSOCIATES

RG-MH-68214 · RERA P52100051977 · Last updated on MahaRERA portal: 19 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 24 months from the original
3 of 11Construction stages donefurthest along: Basement (if any), 90%
19 of 23Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

AARNA REGENCY is a Residential / Group Housing project by AARNA ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100051977 on 13 Jul 2023. Possession is promised by 29 Jun 2027. The completion date has moved by 24 months from the original filing. 4 of the 23 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameAARNA REGENCY
  • TypeResidential / Group Housing
  • Location
    • PUNAWALE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051977
  • ReraGenie IDRG-MH-68214

Builder

  • NameAARNA ASSOCIATES
  • Entity typePartnership
  • PartnersPRASADH SHIVAJI WAGHERE, RAHUL ANNASAHEB GODSE, SWAPNIL SUBHASH BHUJBAL
  • PartnerAKSHAY CHANDRAKANT DHORE
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJul 2023First promiseJun 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Jul 2023
  • Promised completion29 Jun 2027
  • Revised completionRevised to 29 Jun 2027 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed85 files

Current status

17%4 of 23 units booked
53.0%Work done, per cost certificate

Figures as on 19 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AARNA REGENCYNA7623023

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.

AARNA REGENCY: 51% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered12
Open Space23

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area411 sq m
Land owned byNot the promoter
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Jul 2025
LandownerVillageDistrict
SUKHADEV GAJANAN KUDALEPunawalePune
BHANUDAS GAJANAN KUDALEPunawalePune
DNYANESHWAR S KUDALEPunawalePune
HARI SHANTARAM KUDALEPimpri Chinchawad (M Corp.)Pune
MORESHWAR SHANTARAM KUDALEPunawalePune
PANDURANG SHANTARAM KUDALEPunawalePune
RAJU GAJANAN KUDALEPunawalePune
RAMDAS GAJANAN KUDALEPimpri Chinchawad (M Corp.)Pune
RUKHMINI SHANTARAM KUDALEPunawalePune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI1532.58
Proposed, not sanctioned1,530 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNAVI SANGVI PUNE
Estimated costRs 5.10 cr
Cost incurredRs 2.70 cr
Work done53.0%
BuildingWingEstimatedIncurred
AARNA REGENCYNARs 5.10 crRs 2.70 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHREE SAI ARCHITECTURAL PLANNER
ArchitectNK ASSOCIATES
EngineerGHAWATE SHUBHAM SURYAKANT
EngineerSUYESH WAGHOLE
EngineerSanjay Kawade
EngineerAmit Jadhav
Chartered AccountantA S JANGADA AND ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
AARNA ASSOCIATES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100023008Jun 2025 → Jun 2026

Reason as filed by the promoterNon-availability of resources

EXT52100028322Jun 2025 → Jun 2027

Reason as filed by the promoterDue to revisions in the project plan and the ongoing nature of the associated work, the completion of the project is now expected to extend beyond the initially planned date. Currently, the work related to the revised plan is in progress. Therefore, we are applying for an extension of the project’s completion timeline. To increase the allowed construction area, we included Transfer of Development Rights (TDR) in the project. However, the process of acquiring and obtaining approval for TDR took additional time, which ultimately impacted our project schedule.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 29 Jun 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: FORM 2A 2024.pdf19 May 2026
Form 2A (FY 2024-2025)File: FORM 2A 2025.pdf19 May 2026
Form 2A (FY 2025-2026)File: FORM 2A 2026.pdf19 May 2026
Layout approvalFile: Layout Plan.pdf30 Apr 2026
Building plan approvalFile: Sanction Plan.pdf30 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf17 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf17 Apr 2026
Withdrawal Update Form 3File: FORM 3 Signed.pdf17 Apr 2026
Withdrawal Update Form 1File: Form 1 Q3 2025-26.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Q3 2025-26.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Q3 2025-26.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25.pdf29 Nov 2025
Withdrawal Update Form 1File: Form 1 Q1.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1 Q2.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2 Q1.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2 Q2.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 Q1.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 Q2.pdf17 Oct 2025
Form 1File: Form 1.pdf17 Jul 2025
Form 2File: Form 2.pdf17 Jul 2025
Form 3File: Form 3 Final.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular Final.pdf17 Jul 2025
Declaration in FORM BFile: Form B Final.pdf25 Apr 2025
Other - TechnicalFile: Pert Chart.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Revise.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Circular Final.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FY 2024-25 Q2.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 FY 2024-25.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf18 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Promoter Signed.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Circular (1).pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold circular.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarna Associates Form 3 signed Final.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf4 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf4 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Final.pdf4 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Declaration.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q2 final.pdf20 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2 Q3.pdf20 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q4 Final.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf20 Jun 2024
Declaration in FORM BFile: Form B scanned.pdf13 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Uploaded_compressed.pdf15 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf13 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Final.pdf13 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf13 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf31 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf31 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Circular .pdf31 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form compressed.pdf31 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf30 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf30 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf30 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final FORM 3_compressed.pdf30 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: PROMOTERS DECLARATION FINAL.pdf5 Jul 2023
Proforma of Agreement for saleFile: revised aarna draft final.pdf21 Jun 2023
CERSAI detailsFile: CERSAI_Search_Report_200269094566_For_Asset_Based_Search_19_05_2023_12_56_36_262.pdf19 May 2023
Layout approvalFile: LAYOUT PLAN PUNAWALE PCMC.pdf18 May 2023
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN PUNAWALE PCMC.pdf18 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Upload.pdf12 May 2023
Building plan approvalFile: FLOOR PLAN PCMC.pdf9 May 2023
PAN CardFile: FIRM PAN.pdf9 May 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf9 May 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE.pdf9 May 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE.pdf9 May 2023
Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN PCMC.pdf9 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CC PUNAWLE.pdf9 May 2023
Declaration about Commencement CertificateFile: CIRCULAR 32.pdf9 May 2023

How this compares with Pune

17%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AARNA REGENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNAWALE13,700+ in Pune

2 kmAARNA REGENCYCompleted 65Lapsed / revoked 35Other 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 227 registered projects within 2 km.

Builder: AARNA ASSOCIATES

AARNA ASSOCIATES has 2 registrations on MahaRERA, including PARK VIEW 20 and AARNA REGENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AARNA REGENCY is delayed beyond 29 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AARNA REGENCY?

The registered promoter entity is AARNA ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AARNA REGENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AARNA REGENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AARNA REGENCY?

The professionals named in the filing: Architect: SHREE SAI ARCHITECTURAL PLANNER; Architect: NK ASSOCIATES; Engineer: GHAWATE SHUBHAM SURYAKANT; Engineer: SUYESH WAGHOLE; Engineer: Sanjay Kawade; Engineer: Amit Jadhav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARNA REGENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARNA REGENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARNA REGENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.